CSM: Scrum Team & Accountabilities

Try 10 focused CSM questions on Scrum Team & Accountabilities, with answers and explanations, then continue with PM Mastery.

On this page

Open the matching PM Mastery practice page for timed mocks, topic drills, progress tracking, explanations, and full practice.

Topic snapshot

FieldDetail
Exam routeCSM
Topic areaScrum Team & Accountabilities
Blueprint weight18%
Page purposeFocused sample questions before returning to mixed practice

How to use this topic drill

Use this page to isolate Scrum Team & Accountabilities for CSM. Work through the 10 questions first, then review the explanations and return to mixed practice in PM Mastery.

PassWhat to doWhat to record
First attemptAnswer without checking the explanation first.The fact, rule, calculation, or judgment point that controlled your answer.
ReviewRead the explanation even when you were correct.Why the best answer is stronger than the closest distractor.
RepairRepeat only missed or uncertain items after a short break.The pattern behind misses, not the answer letter.
TransferReturn to mixed practice once the topic feels stable.Whether the same skill holds up when the topic is no longer obvious.

Blueprint context: 18% of the practice outline. A focused topic score can overstate readiness if you recognize the pattern too quickly, so use it as repair work before timed mixed sets.

Sample questions

These questions are original PM Mastery practice items aligned to this topic area. They are designed for self-assessment and are not official exam questions.

Question 1

Topic: Scrum Team & Accountabilities

A Product Owner (Jordan) returns after being out for a week. Sprint Planning is tomorrow, and Jordan sees this Product Backlog excerpt.

Order | PBI | Item                  | “Ordered by” note
1     | 41  | Guest checkout         | Priya (Business Analyst)
2     | 18  | Refactor payment svc    | Developers
3     | 55  | Add loyalty points      | Sales VP

What is the best next action for Jordan, consistent with Scrum?

  • A. Move ordering authority to the Developers for this Sprint
  • B. Ask stakeholders to vote and lock the order for the Sprint
  • C. Accept the order as-is since others already prioritized it
  • D. Review inputs and set the final Product Backlog order

Best answer: D

What this tests: Scrum Team & Accountabilities

Explanation: In Scrum, the Product Owner is accountable for maximizing value and for ordering the Product Backlog. Others can help by providing analysis, recommendations, or even doing the mechanics of reordering, but the Product Owner remains accountable for the final ordering. The next step is to inspect the current order, align it to value and the Product Goal, and make the ordering transparent.

The core concept is delegation of work versus accountability. The Product Owner can delegate tasks like gathering stakeholder input, drafting a proposed order, or facilitating refinement, but cannot delegate accountability for Product Backlog ordering and value.

In this exhibit, multiple parties have influenced the ordering (“ordered by” notes), which is fine as input, but it creates ambiguity about who owns the final order going into Sprint Planning. Jordan should inspect the proposed order, reconcile conflicts (e.g., stakeholder desires vs. technical risk), and then clearly publish and communicate the Product Backlog order as the Product Owner’s decision.

Letting others’ changes stand without PO review blurs accountability and reduces transparency.

The Product Owner may delegate ordering work, but must own and communicate the final ordering decision.


Question 2

Topic: Scrum Team & Accountabilities

A Scrum Team is midway through a Sprint. The Scrum Master notices the Sprint Backlog is organized like this:

Sprint Goal: Enable guest checkout
Sprint Backlog (excerpt):
- Backend Team: Create checkout API (In Progress)
- Frontend Team: Build guest UI form (To Do)
- QA Team: Write test plan (To Do)
- Lead Dev: Approve merges (Blocked)

What is the best next action to align with Scrum’s rule of no sub-teams or titles and strengthen accountability?

  • A. Create separate Definitions of Done for each sub-team
  • B. Make the Lead Dev responsible for overall Sprint delivery
  • C. Coach Developers to reframe as one team owning the Increment
  • D. Ask the Product Owner to assign items to each specialty group

Best answer: C

What this tests: Scrum Team & Accountabilities

Explanation: The exhibit shows work split into specialty sub-teams and a titled gatekeeper, which weakens shared ownership. In Scrum, the Developers are a cohesive unit with no sub-teams or titles, and they collectively own the Sprint Backlog and accountability for a Done Increment. The best move is to help them reorganize around the Sprint Goal and swarm as needed.

Scrum intentionally has no sub-teams or titles within the Scrum Team because creating internal hierarchies and handoffs dilutes clear accountability. The Developers are a single, self-managing group accountable for creating a usable Increment each Sprint that meets the Definition of Done.

In the exhibit, labels like “Backend Team/Frontend Team/QA Team” and “Lead Dev: Approve merges” encourage siloed ownership and a dependency bottleneck. A Scrum-aligned next step is to coach the Developers to manage the Sprint Backlog as one team:

  • Organize work around the Sprint Goal, not functions
  • Share ownership of items and collaborate (swarm/pair) to finish
  • Remove title-based gating so the team can meet the DoD together

This preserves one-team accountability for outcomes instead of component-level accountability for tasks.

Removing sub-team/titled ownership reinforces that Developers are jointly accountable for a Done Increment that meets the Sprint Goal.


Question 3

Topic: Scrum Team & Accountabilities

Midway through a Sprint, the Product Owner starts assigning tasks to individual Developers and is the only person updating the Sprint Backlog in the tool. Developers stop updating their plan and progress there, and focus only on completing the assigned tasks.

What is the most likely near-term impact?

  • A. Reduced Sprint Backlog transparency, making Sprint Goal inspection harder
  • B. The team’s velocity will become unusable for future forecasting
  • C. The Sprint must be canceled due to role confusion
  • D. Stakeholders will lose trust in Scrum over the next quarter

Best answer: A

What this tests: Scrum Team & Accountabilities

Explanation: Developers are accountable for creating and adapting the Sprint Backlog as their plan for achieving the Sprint Goal. If the Product Owner controls updates and Developers stop maintaining it, the Sprint Backlog quickly becomes an unreliable picture of remaining work. That immediately reduces transparency and weakens inspection and adaptation toward the Sprint Goal.

The Sprint Backlog is the Developers’ plan for the Sprint: it is created by Developers in Sprint Planning and then updated by Developers throughout the Sprint as they learn and as work emerges. If Developers stop owning updates (and instead follow assignments while the Product Owner alone updates the artifact), the Sprint Backlog stops reflecting the team’s current understanding of what’s needed to meet the Sprint Goal.

Near-term, this harms empiricism:

  • Transparency drops because the plan/progress is no longer trustworthy.
  • Inspection and adaptation during the Sprint become harder, increasing the risk of drifting from the Sprint Goal.

This is more immediate than downstream effects like forecasting quality or stakeholder confidence.

When Developers don’t own and update the Sprint Backlog, it quickly stops being a transparent, real-time plan to support progress toward the Sprint Goal.


Question 4

Topic: Scrum Team & Accountabilities

Which statement best describes how the Product Owner collaborates with stakeholders while maintaining a single ordered Product Backlog?

  • A. Each stakeholder group maintains its own ordered backlog that is later merged.
  • B. Stakeholders approve Product Backlog ordering before work can be selected in Sprint Planning.
  • C. Developers order the Product Backlog to reflect technical dependencies from stakeholders.
  • D. Stakeholders may suggest items, but the Product Owner maintains one ordered Product Backlog.

Best answer: D

What this tests: Scrum Team & Accountabilities

Explanation: Scrum uses a single Product Backlog to make upcoming work transparent and comparable. Stakeholders can provide input and requests, but the Product Owner is accountable for the content and ordering of that one Product Backlog. Collaboration happens through conversation and feedback, not by splitting ownership of the backlog.

The core Scrum concept is that there is one Product Backlog for a product, and it is an ordered, emergent list used to maximize value. Stakeholders collaborate by sharing needs, feedback, and ideas, which can become Product Backlog items. However, the Product Owner remains accountable for the Product Backlog’s content, ordering, and transparency, so stakeholder input does not create multiple competing backlogs or require stakeholder sign-off to order items.

Key takeaway: stakeholder collaboration influences the backlog, but it does not change the Product Owner’s single-backlog accountability.

The Product Owner is accountable for one transparent, ordered Product Backlog while collaborating with stakeholders for input.


Question 5

Topic: Scrum Team & Accountabilities

Mid-Sprint, the Product Owner tells the Scrum Master, “I’ve delegated Product Backlog ordering to a senior Developer because I’m in back-to-back meetings.” Stakeholders are now asking the Developers to move items around for an upcoming release.

What is the FIRST thing the Scrum Master should clarify before suggesting next steps?

  • A. Whether the Developers can increase their forecast to include the stakeholder requests
  • B. Whether the Definition of Done needs to be updated for the upcoming release
  • C. Whether stakeholders can provide a ranked list of priorities for the next Sprint
  • D. How ordering decisions will be made and how the Product Owner will remain accountable for the Product Backlog

Best answer: D

What this tests: Scrum Team & Accountabilities

Explanation: In Scrum, the Product Owner is accountable for effective Product Backlog management, including ordering to maximize value. The Product Owner can delegate tasks, but not shift accountability. Before acting on stakeholder pressure or team actions, clarify how ordering will be handled and how the Product Owner will stay accountable and available for decisions.

The core issue is delegation versus accountability. The Product Owner remains accountable for maximizing value and for effective Product Backlog management (including ordering), even if they delegate specific backlog management activities to others. When Developers and stakeholders start changing priorities directly, transparency about who makes ordering decisions and how those decisions connect to the Product Goal is missing.

A useful first clarification is:

  • Who currently decides ordering and by what mechanism?
  • How does the Product Owner review/approve changes and stay accountable?
  • How will stakeholder requests be routed so the Product Owner can make value trade-offs?

Only after that is clear should the Scrum Master coach on appropriate collaboration and boundaries between stakeholders, Developers, and the Product Owner.

The Product Owner may delegate backlog management work, but must retain accountability for value and ordering, so decision-making and accountability need to be transparent first.


Question 6

Topic: Scrum Team & Accountabilities

A Scrum Team starts a 2-week Sprint. The Developers can code and design, but they do not have testing skills. The organization decides that all testing must be done by a separate QA group that is only available during the last 2 days of the Sprint.

What is the most likely near-term impact of this decision?

  • A. More waiting and delayed completion as work queues for QA
  • B. Less need for a Sprint Goal since QA controls acceptance
  • C. Immediate improvement in product quality due to specialized testers
  • D. Higher transparency because QA will report progress independently

Best answer: A

What this tests: Scrum Team & Accountabilities

Explanation: A cross-functional Scrum Team has the skills needed to deliver a Done Increment without relying on outside handoffs. Moving testing to an external group late in the Sprint introduces waiting, delayed feedback, and a bottleneck. In the near term, this most directly threatens timely Sprint Goal progress and completion of work to the Definition of Done.

In Scrum, the Developers are expected to be cross-functional as a team: collectively they have all the skills necessary to create a usable Increment each Sprint. When a key skill (like testing) sits outside the Scrum Team, work must be handed off and waits in queues, which reduces flow and delays inspection of quality. With testing only available in the last 2 days, the team gets late feedback and may discover unfinished or failing work too late to adapt, making Sprint Goal progress less predictable. Cross-functionality reduces these handoffs and delays by enabling the team to complete items to the Definition of Done within the Sprint.

The key takeaway is that external dependencies for core skills create near-term bottlenecks and delay completion.

Because the team is not cross-functional, the handoff to QA creates a bottleneck that slows progress toward a Done Increment.


Question 7

Topic: Scrum Team & Accountabilities

Midway through a Sprint, several defects are discovered in new functionality. The Developers decide to fix the defects that threaten the Sprint Goal and adjust their plan to keep the Sprint Goal achievable.

Which option is the best evidence/indicator that the Developers handled the defects appropriately while protecting the Sprint Goal?

  • A. Test execution reports show most test cases passed this Sprint
  • B. A burn-down shows the remaining work trending down each day
  • C. A Done Increment that meets the Definition of Done and achieves the Sprint Goal
  • D. All defects are logged, categorized, and assigned to owners

Best answer: C

What this tests: Scrum Team & Accountabilities

Explanation: In Scrum, the strongest evidence of progress, quality, and value is a usable Increment that meets the Definition of Done. When defects are discovered during the Sprint, protecting the Sprint Goal is validated by still producing a Done Increment that achieves that goal, not by intermediate activity outputs. This keeps inspection focused on real results rather than process artifacts.

Defects found during a Sprint are part of the work needed to produce a usable Increment. Developers adapt their plan as they learn, typically by updating the Sprint Backlog and making trade-offs that preserve the Sprint Goal while ensuring work meets the Definition of Done.

The most reliable indicator that defects were handled appropriately is outcome-based: a Done Increment that meets the Definition of Done (quality) and achieves the Sprint Goal (value). Logs, charts, and test reports can support transparency, but they do not prove the Increment is usable or that the Sprint Goal was met.

The key takeaway is to validate by inspecting the Done Increment against the Definition of Done and Sprint Goal, not by tracking activities.

The most direct validation is an Increment that is actually Done (quality met) and still delivers the Sprint Goal (value).


Question 8

Topic: Scrum Team & Accountabilities

Midway through a Sprint, stakeholders ask how the Scrum Team is preventing technical debt while still delivering new features. The Developers have started several code cleanups and drafted an “architecture improvement plan,” but nothing has been integrated yet.

Which option is the best evidence that progress is being made while maintaining sustainable quality in Scrum?

  • A. A completed architecture improvement plan document
  • B. More hours logged on refactoring tasks this Sprint
  • C. A Done Increment integrated and meeting the Definition of Done
  • D. A growing list of identified technical debt items in the Product Backlog

Best answer: C

What this tests: Scrum Team & Accountabilities

Explanation: In Scrum, the most reliable evidence of progress and quality is a Done Increment that meets the Definition of Done. It demonstrates integrated, tested, potentially releasable work, which is how the team validates sustainable delivery and avoids hidden work and deferred quality. Plans and activity counts do not validate outcomes.

Reducing technical debt and supporting sustainable delivery requires making quality visible in the product, not just in intentions or effort. In Scrum, the key quality commitment is the Definition of Done, and the primary evidence that quality is being maintained is a Done Increment: integrated work that meets the Definition of Done and is usable.

A plan, time spent refactoring, or a larger list of debt items can be helpful signals, but they are not outcome validation. Only a Done Increment provides transparency that improvements and features are actually integrated, verified, and not creating hidden or deferred work that becomes technical debt. The strongest indicator is therefore working product that satisfies the Definition of Done.

A Done Increment is usable and integrated, providing transparent evidence that quality work is complete and technical debt is being managed through the Definition of Done.


Question 9

Topic: Scrum Team & Accountabilities

A Scrum Team has started referring to itself as the “UI Team” and the “API Team.” One Developer is called the “Tech Lead” and assigns work to each group. This Sprint, integration happened late, and the Increment is not “Done.” The Product Owner asks, “Which team owns this failure?”

As Scrum Master, what is the best next step?

  • A. Ask line managers to appoint a single lead accountable for integration
  • B. Escalate to stakeholders and defer the issue until reorganization
  • C. Create separate sub-teams with separate Sprint Backlogs for clarity
  • D. Facilitate inspection in the Sprint Retrospective and realign as one team

Best answer: D

What this tests: Scrum Team & Accountabilities

Explanation: In Scrum there are no sub-teams or titles within the Scrum Team because they weaken the single, shared accountability for delivering a valuable, “Done” Increment each Sprint. The next step is to use an empirical event to inspect how the split and title are affecting outcomes and adapt the team’s way of working back toward one cohesive unit.

Scrum avoids sub-teams and internal titles because they create handoffs, local ownership, and “us vs. them” thinking, which undermines the Scrum Team’s shared accountability for the Increment and the Sprint Goal. Here, the split into “UI” and “API” groups and a “Tech Lead” assigning work contributed to late integration and an unfinished Increment.

A good next step is to use the Sprint Retrospective to inspect and adapt:

  • Make the problem transparent (handoffs, late integration, unclear ownership)
  • Reaffirm that the Developers are collectively accountable for creating the Increment
  • Agree on working agreements that encourage swarming, earlier integration, and shared ownership of meeting the Definition of Done

Clarifying a single team accountability enables faster collaboration and clearer responsibility without creating hierarchy.

Scrum has one Developers accountability, so the team should inspect how sub-team labels/titles harmed collaboration and adapt to restore shared ownership of the Increment.


Question 10

Topic: Scrum Team & Accountabilities

Near the end of a Sprint, the Developers say they are “done,” but the Product Owner is unsure whether the Increment is actually useful and worth showing at the Sprint Review. Stakeholders have not been engaged during the Sprint.

As the Scrum Master, what is the most important thing to clarify first before deciding what to do next?

  • A. What is each Developer’s current capacity and utilization?
  • B. What is the Sprint Goal and what outcome would make this Increment valuable?
  • C. How many Product Backlog items were completed compared to the plan?
  • D. Which stakeholders should approve the Increment before it is shown?

Best answer: B

What this tests: Scrum Team & Accountabilities

Explanation: A valuable, useful Increment is evaluated against the purpose it was built to achieve. Clarifying the Sprint Goal and the expected outcome creates transparency about what “valuable and useful” means for this Sprint, enabling inspection and adaptation at the Sprint Review.

In Scrum, the Scrum Team is responsible each Sprint for creating an Increment that is valuable and useful, and the Sprint Goal provides the primary context for assessing that. If the Product Owner is unsure whether the Increment is worth showing, the first clarification is what outcome the Sprint was meant to achieve (Sprint Goal) and what “value” looks like for that goal. With that shared understanding, the team can then inspect whether what was built supports the goal and decide what to adapt (e.g., scope, collaboration, or how to make the Increment demonstrably usable). Without clarity on the Sprint Goal and intended outcome, discussions about completion or progress metrics risk optimizing for activity rather than value.

You first need a shared understanding of the Sprint Goal and intended outcome to judge whether the Increment is valuable and useful.

Continue with full practice

Use the CSM Practice Test page for the full PM Mastery route, mixed-topic practice, timed mock exams, explanations, and web/mobile app access.

Open the matching PM Mastery practice page for timed mocks, topic drills, progress tracking, explanations, and full practice.

Free review resource

Read the CSM guide on PMExams.com, then return to PM Mastery for timed practice.

Revised on Thursday, May 14, 2026