PMI-RMP — PMI Risk Management Professional Quick Reference

Compact PMI-RMP quick reference for risk processes, artifacts, analysis methods, response strategies, formulas, and exam decision points.

Exam Identity and How to Use This Page

This Quick Reference supports candidates preparing for PMI’s PMI Risk Management Professional (PMI-RMP) exam, exam code PMI-RMP. It is independent review support and is not affiliated with PMI.

Use it to quickly reinforce:

  • Risk process flow and decision logic
  • Risk artifacts and ownership distinctions
  • Qualitative and quantitative analysis tools
  • Threat and opportunity response choices
  • Common PMI-RMP exam traps around governance, escalation, reserves, and monitoring

PMI-RMP Risk Management Lens

ConceptExam-use meaningCommon trap
Project riskUncertain event or condition that can affect objectivesTreating every problem as a risk; an occurred risk is usually an issue
ThreatNegative riskOnly mitigating threats and ignoring avoidance, transfer, acceptance, escalation
OpportunityPositive riskForgetting positive risk responses: exploit, enhance, share, accept, escalate
Overall project riskEffect of uncertainty on the project as a wholeConfusing it with the sum of individual risks only
Individual project riskA discrete uncertain event or conditionManaging only high-scoring individual risks while ignoring cumulative exposure
Risk appetiteGeneral willingness to accept riskUsing it as a numeric trigger without tailoring
Risk toleranceDegree of acceptable variation around objectivesConfusing tolerance with threshold
Risk thresholdSpecific point at which action or escalation is requiredIgnoring thresholds when deciding whether to escalate
Risk attitudeStakeholder or organizational view of uncertaintyAssuming all stakeholders perceive risk the same way
Risk governanceStructures, roles, thresholds, reporting, escalation, and decision rightsTreating risk as only a project manager task
TailoringAdjusting risk processes to project contextSkipping tailoring on adaptive, regulated, complex, or high-uncertainty work

Risk Management Process Flow

    flowchart LR
	    A[Plan Risk Management] --> B[Identify Risks]
	    B --> C[Perform Qualitative Risk Analysis]
	    C --> D{Quantitative analysis needed?}
	    D -- Yes --> E[Perform Quantitative Risk Analysis]
	    D -- No --> F[Plan Risk Responses]
	    E --> F
	    F --> G[Implement Risk Responses]
	    G --> H[Monitor Risks]
	    H --> B
	    H --> C
	    H --> F

High-Yield Process Logic

If the question says…Think first
“How will risk be managed?”Plan Risk Management
“New uncertain event discovered”Identify and document the risk
“Which risks deserve attention first?”Qualitative risk analysis
“What is the probabilistic cost or schedule exposure?”Quantitative risk analysis
“What should be done about the risk?”Plan risk responses
“The response owner has not acted”Implement risk responses / follow up
“Risk indicators changed”Monitor risks and reassess
“The risk occurred”Manage as an issue; execute contingency or workaround as appropriate
“Risk exceeds authority or threshold”Escalate using the risk management plan
“Baseline impact is required”Follow integrated change control or applicable governance

Core Artifacts

ArtifactPurposeKey contentsExam distinction
Risk management planDefines how risk management will be performedMethodology, roles, funding, timing, categories, probability/impact definitions, matrix, reporting, thresholdsIt is a plan for the process, not the list of risks
Risk registerDetailed repository for individual risksRisk statement, causes, impacts, owner, analysis results, responses, triggers, residual/secondary risksUsually the primary artifact for tracking individual risks
Risk reportSummary view for stakeholders and governanceOverall project risk, major threats/opportunities, trends, response status, exposureMore executive and aggregate than the risk register
Issue logTracks current problemsIssue owner, due date, status, actionsOnce a risk occurs, it may become an issue
Assumption logTracks assumptions and constraintsAssumption validity, risk implicationsInvalid assumptions often become risks
Lessons learned registerCaptures reusable learningWhat worked, what failed, risk patternsUpdate throughout the project, not only at the end
Stakeholder registerIdentifies stakeholders and risk attitudesInterest, influence, expectations, risk appetiteSupports risk communication and escalation planning
Change logTracks approved/declined changesChange status, decision, implementationNeeded when risk responses change baselines
Risk breakdown structureHierarchical risk categoriesTechnical, external, organizational, management, commercial, etc.Helps systematic identification
Probability and impact matrixDefines qualitative scoringProbability levels, impact scales, priority zonesMust be tailored and understood before scoring
Risk response planSelected strategies and actionsResponse owner, action owner, budget, timing, triggersMust be implementable and monitored
Contingency planPreplanned action if trigger/event occursTrigger, action, owner, reserve useDifferent from fallback plan
Fallback planBackup if primary response failsSecondary action pathUsed when contingency is ineffective
WatchlistLow-priority risks for monitoringOwner or review cadenceLow priority does not mean ignored

Roles and Ownership

RoleRisk responsibilityExam emphasis
Project managerEnsures risk processes are planned, integrated, and monitoredDoes not personally own every risk
Risk manager / PMI-RMP-type roleFacilitates risk strategy, analysis, governance, reporting, and response effectivenessHelps decision quality; coordinates across stakeholders
SponsorProvides authority, escalation path, funding decisions, and tolerance guidanceEscalate when risk exceeds project authority
Risk ownerAccountable for managing an assigned riskOwns the risk outcome and response oversight
Risk action ownerPerforms a specific response actionNot necessarily accountable for the whole risk
Project teamIdentifies risks, estimates impacts, implements responsesTeam participation improves data quality
StakeholdersProvide risk perception, requirements, constraints, and acceptance criteriaRisk attitudes may conflict
PMO / governance bodySets standards, reporting expectations, escalation pathsEspecially important in enterprise or portfolio risk contexts
Procurement / legal / contractsHelps manage supplier, claims, liability, and contract riskTransfer does not eliminate all project risk
Subject matter expertsProvide technical, market, regulatory, or domain insightExpert judgment must still be tested for bias

Risk Statement Reference

A strong risk statement connects cause, uncertain event, and effect.

ElementExample
CauseBecause the supplier design is unproven
Risk eventthe component may fail qualification testing
Effectcausing schedule delay and rework cost

Preferred structure:

Because of cause, risk event may occur, leading to effect on objective.

Avoid vague entries such as “supplier risk” or “testing risk.” They are categories, not actionable risk statements.

Key Distinctions

DistinctionCorrect interpretation
Risk vs issueRisk is uncertain; issue is happening or has happened
Cause vs riskCause exists now; risk may occur because of it
Trigger vs riskTrigger is an early warning sign or condition
Impact vs responseImpact is the consequence; response is what you do
Residual risk vs secondary riskResidual remains after response; secondary is created by the response
Contingency reserve vs management reserveContingency is for identified risks; management reserve is for unknown-unknowns or broader management control
Contingency plan vs workaroundContingency is planned; workaround is unplanned response to an issue or unforeseen event
Risk owner vs action ownerRisk owner is accountable; action owner performs assigned tasks
Escalation vs transferEscalation moves ownership beyond project authority; transfer shifts some impact/accountability to a third party
Avoid vs mitigateAvoid changes plan to remove threat; mitigate reduces probability and/or impact
Exploit vs enhanceExploit seeks to ensure opportunity occurs; enhance increases probability and/or impact
Share vs transferShare is for opportunities; transfer is for threats

Process Reference Table

ProcessPurposeTypical toolsMain outputsExam traps
Plan Risk ManagementDefine risk approach before doing detailed risk workMeetings, expert judgment, stakeholder analysis, tailoringRisk management planJumping into response planning before defining scales, roles, thresholds
Identify RisksFind individual risks and sources of overall riskBrainstorming, interviews, checklists, RBS, SWOT, assumptions analysis, prompt listsRisk register, risk report updatesIdentifying only threats; excluding stakeholders
Perform Qualitative Risk AnalysisPrioritize risks for further actionProbability/impact matrix, data quality assessment, urgency, proximity, expert judgmentUpdated risk register and prioritiesTreating qualitative score as precise math
Perform Quantitative Risk AnalysisNumerically analyze exposure and uncertaintyMonte Carlo, decision tree, EMV, sensitivity/tornado, simulationsProbabilistic forecasts, contingency needsDoing expensive quant analysis when not warranted or data is poor
Plan Risk ResponsesSelect strategies and actionsThreat/opportunity strategies, cost-benefit analysis, decision analysisResponse plans, owners, reserves, change requests if neededSelecting a response without an owner or trigger
Implement Risk ResponsesExecute agreed responsesStatus reviews, action tracking, team coordinationImplemented actions, updatesPlanning responses but failing to execute them
Monitor RisksTrack risks, responses, residual risk, new risks, and overall exposureAudits, reassessment, variance/trend analysis, technical performance analysisUpdates, change requests, lessons learnedClosing risk management too early

Identification Tool Selection

ToolBest whenWatch for
BrainstormingNeed broad team input quicklyDominant voices and groupthink
InterviewsNeed detailed expert or stakeholder insightInterviewer bias and incomplete stakeholder coverage
Delphi techniqueNeed anonymous expert consensusTime and facilitation effort
ChecklistsSimilar past projects existChecklist blindness; missing novel risks
Risk breakdown structureNeed systematic category coverageCategories must be tailored
SWOT analysisNeed internal/external and positive/negative viewCan remain too high-level
Assumptions and constraints analysisMajor uncertainty lies in planning assumptionsAssumptions may be politically sensitive
Root cause analysisRepeated or systemic risk patterns appearDo not confuse symptoms with causes
Document reviewPlans, contracts, estimates, requirements existPoor documents may hide risk
Lessons learned reviewOrganization has historical project dataPast data may not fit current context
Prompt listsNeed structured risk promptsPrompts are aids, not full analysis
DiagrammingNeed causal relationshipsCan imply false precision
Product or technical analysisComplex design or engineering uncertaintyRequires qualified SMEs
External scanningMarket, regulatory, geopolitical, weather, or supplier uncertaintyDo not invent certainty from weak signals

Qualitative Risk Analysis

Qualitative Scoring Reference

FactorMeaningWhy it matters
ProbabilityLikelihood of occurrenceHelps rank likelihood
ImpactEffect on objectives if it occursMay vary by cost, schedule, scope, quality, safety, reputation, benefits
UrgencyHow soon action is neededA near-term moderate risk may outrank a distant one
ProximityHow soon the risk might affect the projectSupports timing of responses
DormancyTime between occurrence and impactUseful for early warning planning
ManageabilityAbility to influence the riskLow manageability may require escalation or reserves
ControllabilityDegree project team can control causes or responsesHelps choose response strategy
DetectabilityAbility to detect trigger or occurrenceLow detectability increases concern
ConnectivityRelationship to other risksHighly connected risks may drive systemic exposure
Data qualityReliability of the data behind the ratingPoor data weakens the ranking
Strategic impactEffect on business value, benefits, or reputationCan elevate priority beyond project metrics

Qualitative Risk Score

Use the organization’s defined scale. A simple conceptual score is:

\[ \text{Risk Score} = \text{Probability Rating} \times \text{Impact Rating} \]

Do not treat this as universally precise. The exam often tests whether the candidate recognizes that scoring scales, thresholds, and definitions must be established in the risk management plan.

Probability and Impact Matrix Traps

TrapBetter exam answer
Use generic scales without stakeholder agreementDefine and tailor probability/impact scales
Rank risks with poor dataassess data quality and gather better information
Ignore positive risksInclude opportunity scoring and response planning
Automatically quantify every riskQuantify when value, complexity, exposure, or governance need justifies it
Score once and stopReassess as conditions change
Treat matrix score as final decisionConsider urgency, proximity, thresholds, and stakeholder risk attitude

Quantitative Risk Analysis

When Quantitative Analysis Is Most Useful

Use quantitative analysis when…Reason
Major cost or schedule exposure existsNeed probabilistic forecast, not single-point estimate
Management asks for confidence levelSupports probability-based commitments
Large contingency decisions are neededHelps justify reserves
Many risks interactSimulation can model combined uncertainty
Competing response options existDecision trees and EMV support comparison
High-stakes go/no-go decision is pendingQuantitative exposure improves governance decisions
Contract or procurement risk is significantCan model financial exposure and allocation

Quantitative Tool Reference

ToolBest forOutputTrap
Expected monetary valueComparing alternatives with probabilities and monetary impactsExpected valueAverage outcome may not represent worst-case exposure
Decision treeSequential decisions and chance eventsPath EMVProbabilities must be credible
Monte Carlo simulationCombined uncertainty in cost/schedule modelsProbability distribution, confidence rangesGarbage in, garbage out
Sensitivity analysisFinding variables with biggest effectTornado chartCorrelation may be ignored
Three-point estimatingEstimating uncertain durations/costsExpected estimate and rangeDo not confuse triangular and beta/PERT
Scenario analysisTesting plausible futuresScenario impactsScenarios are not probabilities unless quantified
Influence diagramsShowing relationships among decisions, uncertainties, outcomesDecision modelCan oversimplify dependencies
Fault tree / event treeAnalyzing failure pathways or event progressionProbability or causal structureRequires reliable technical data
Criticality analysisIdentifying schedule activities likely to be criticalCriticality indexNot the same as total float alone

Expected Monetary Value

\[ \text{EMV} = \text{Probability} \times \text{Impact} \]

For multiple independent risk events:

\[ \text{Total EMV} = \sum_{i=1}^{n} \left(P_i \times I_i\right) \]

Use positive values for opportunities and negative values for threats if the model is set up that way. Be consistent.

Decision Tree Expected Value

\[ \text{Expected Value of Decision} = \sum \left(\text{Probability of Outcome} \times \text{Value of Outcome}\right) - \text{Cost of Decision} \]

Choose the option with the best expected value only after considering thresholds, nonfinancial impacts, stakeholder risk appetite, and feasibility.

Three-Point Estimates

Triangular mean:

\[ \text{Triangular Mean} = \frac{O + M + P}{3} \]

Beta / PERT mean:

\[ \text{PERT Mean} = \frac{O + 4M + P}{6} \]

PERT standard deviation:

\[ \sigma = \frac{P - O}{6} \]

Where:

SymbolMeaning
OOptimistic estimate
MMost likely estimate
PPessimistic estimate
sigmaStandard deviation

Contingency Reserve Concept

For identified risk exposure, contingency reserve may be based on analysis such as EMV, simulation, or risk response cost.

\[ \text{Contingency Reserve} \approx \sum \text{Expected Exposure of Accepted or Residual Risks} \]

Exam caution: contingency reserve is not a substitute for risk responses. It is planned capacity to handle identified uncertainty.

Earned Value and Risk Monitoring Formulas

Earned value metrics are not risk processes by themselves, but they help monitor performance trends that may indicate risk exposure.

MetricPlain formulaMeaning
Cost varianceCV = EV - ACPositive is favorable
Schedule varianceSV = EV - PVPositive is favorable
Cost performance indexCPI = EV / ACAbove 1 is favorable
Schedule performance indexSPI = EV / PVAbove 1 is favorable
Estimate at completionEAC = BAC / CPISimple forecast if current cost performance continues
Estimate to completeETC = EAC - ACRemaining expected cost
Variance at completionVAC = BAC - EACPositive is favorable
If trend shows…Risk interpretation
CPI decliningCost overrun risk increasing
SPI decliningSchedule delay risk increasing
Rework increasingQuality or requirements risk may be materializing
Milestone slippageTrigger thresholds may be crossed
Burn rate faster than progressFunding or scope risk may require escalation
Technical performance below planned valueTechnical risk may be increasing even before schedule impact appears

Threat Response Strategies

StrategyUse whenExampleTrap
AvoidYou can eliminate the threat or protect objective from itChange design to remove risky technologyAvoidance may change scope, schedule, or cost baseline
MitigateYou can reduce probability and/or impactAdd prototype, extra testing, trainingMitigation does not remove all residual risk
TransferAnother party can better bear some impactInsurance, warranty, fixed-price contractTransfer often creates secondary risks and does not remove responsibility to manage
Accept, activeResponse cost is not justified, but contingency is plannedReserve and trigger-based actionActive acceptance needs owner, trigger, and reserve
Accept, passiveNo proactive action beyond monitoringWatchlist low-priority threatPassive acceptance is not ignoring
EscalateThreat is outside project authority or should be managed at higher levelStrategic, portfolio, legal, enterprise riskEscalated risk still needs tracking until accepted by the higher authority

Opportunity Response Strategies

StrategyUse whenExampleTrap
ExploitYou want to ensure the opportunity happensAssign top talent to capture early delivery bonusRequires active commitment
EnhanceYou want to increase probability and/or impactAdd resources to improve chance of earlier finishNot the same as exploit
ShareAnother party can help capture opportunityJoint venture, incentive partnershipBenefits and ownership must be clear
Accept, activeBenefit is possible but not worth major proactive actionPrepare to use savings if they occurStill monitor triggers
Accept, passiveNo action unless opportunity occursLow-value upsideDo not spend more than value
EscalateOpportunity is outside project authorityEnterprise-level market opportunityNeeds higher-level ownership

Response Planning Decision Table

SituationBest response direction
Threat can be fully removed by changing approachAvoid
Threat probability can be reduced through preventive actionMitigate
Threat impact can be contractually shiftedTransfer
Threat is low priority and response cost exceeds expected exposureAccept
Threat exceeds project manager authorityEscalate
Opportunity can be guaranteed through actionExploit
Opportunity can be made more likely or valuableEnhance
Opportunity needs partner capabilityShare
Opportunity exceeds project scope or authorityEscalate
Response introduces new uncertaintyIdentify secondary risk
Response leaves remaining exposureDocument residual risk
Primary response may failCreate fallback plan
Risk has warning signsDefine triggers and monitoring method
Response affects baselineSubmit change request through governance

“What Should the Risk Manager Do Next?” Reference

Exam scenarioStrong next step
A new risk is identified in a meetingClarify cause-event-impact, document in risk register, assign for analysis
A risk owner is missingAssign an accountable risk owner before relying on the response
A response action is overdueFollow up with action owner; update status; escalate if thresholds or commitments are at risk
A risk has occurredTreat as issue, execute contingency if planned, update risk and issue records
No contingency plan exists for an occurred riskDevelop workaround, document, assess change impacts
Risk response requires extra budget or schedule changeSubmit change request per governance
Stakeholders disagree on risk priorityRefer to agreed probability/impact definitions, thresholds, and risk appetite; facilitate alignment
Data quality is poorImprove data, use expert judgment carefully, document uncertainty
Quantitative model gives unrealistic resultCheck assumptions, distributions, correlations, and input quality
Risk exceeds project thresholdEscalate according to the risk management plan
New regulation or market condition appearsIdentify new risks, analyze impact, update risk report
Supplier misses early milestoneCheck triggers, reassess procurement risk, execute response or contingency
Response creates another threatAdd secondary risk and assign owner
Residual risk remains highReanalyze and consider additional response, reserve, or escalation
A high opportunity appearsAnalyze like any risk; choose exploit, enhance, share, accept, or escalate
Team wants to skip risk reviewsReinforce planned cadence and explain monitoring value

Monitoring and Control Reference

Monitoring activityWhat it detectsTypical action
Risk reassessmentNew, changed, obsolete risksUpdate register and priorities
Risk auditEffectiveness of risk process and responsesImprove process or response execution
Variance analysisDeviation from baselinesInvestigate risk causes and triggers
Trend analysisDirection of performanceForecast worsening exposure
Technical performance analysisProduct performance against targetsIdentify emerging technical threats
Reserve analysisAdequacy of contingencyAdjust forecasts or request changes
Status meetingsResponse progress and new risk signalsUpdate owners, actions, dates
Trigger trackingEarly warning signsExecute contingency or response action
Issue reviewRealized risks and current problemsLink lessons back to risk planning
Lessons learnedProcess improvementUpdate organizational knowledge

Risk Reporting: Register vs Report

NeedUse primarily
Detailed risk owner/action owner trackingRisk register
Executive summary of top exposureRisk report
Overall project risk trendRisk report
Individual trigger statusRisk register
Governance escalationRisk report plus supporting register detail
Response due datesRisk register
Portfolio or program visibilityRisk report
Historical lessons and patternsLessons learned plus risk records

Good risk reporting is tailored by audience. Executives usually need exposure, trend, threshold breaches, decisions required, and confidence level. Risk owners need detailed actions, dates, and triggers.

Agile, Adaptive, and Hybrid Risk Reference

ContextRisk management emphasis
Predictive projectUpfront planning, baselines, formal change control, scheduled risk reviews
Agile projectContinuous risk identification, backlog refinement, short feedback loops, visible impediments
Hybrid projectCoordinate formal governance with iterative discovery
High uncertainty product workUse spikes, prototypes, experiments, incremental delivery
Fixed regulatory or contract environmentMaintain traceability, escalation, compliance risks, and change discipline
Rapidly changing stakeholder needsFrequent reprioritization and communication
Complex technical architectureEarly validation and technical risk burn-down
Distributed teamCommunication, cultural, time-zone, and dependency risks

Agile Risk Patterns

PatternRisk benefit
Short iterationsReduces time between risk signal and response
Product backlog refinementSurfaces requirement and priority risks
Definition of doneReduces quality and completeness ambiguity
Sprint reviewsValidates product direction and stakeholder expectations
RetrospectivesImproves process risk response
SpikesReduce technical or estimation uncertainty
Information radiatorsImprove transparency of blockers and trends
Incremental deliveryReduces late discovery of value and integration risk

Exam trap: agile does not eliminate risk management. It changes cadence, visibility, and response mechanisms.

Governance, Escalation, and Change Control

SituationGovernance response
Risk is within project authority and reserveManage through planned response
Risk exceeds thresholdEscalate to defined authority
Response changes scope, schedule, cost, quality, or contract baselineUse change control
Enterprise-level risk appearsEscalate outside project governance
Sponsor decision is requiredPresent options, exposure, recommendation, and impact
Stakeholder risk appetite conflictsFacilitate decision using documented thresholds and objectives
Risk response requires procurement actionInvolve procurement/contracts early
Compliance or safety impact appearsFollow applicable governance and escalation paths

A PMI-RMP candidate should distinguish informing, escalating, and requesting a change:

ActionUse when
InformStakeholders need awareness, but no decision is required
EscalateAuthority, threshold, or ownership exceeds the project level
Change requestApproved baseline, contract, or plan must change
Update recordsRisk status, analysis, owner, or response detail changes
Implement responsePlanned and approved action can be executed within authority

Procurement and Contract Risk

Contract / commercial featureRisk implication
Fixed-price contractMore cost risk may shift to seller, but buyer retains scope, quality, change, and relationship risk
Cost-reimbursable contractBuyer may retain more cost exposure; seller has lower cost risk
Time and materialsFlexibility with potential cost growth risk
IncentivesAlign behavior if metrics are clear
Liquidated damages or penaltiesMay transfer some financial impact but can create relationship or claims risk
WarrantyTransfers certain defect costs but not all operational impact
InsuranceTransfers defined financial exposure, subject to terms
Single-source supplierDependency and continuity risk
Long-lead itemsSchedule and supply chain risk
Ambiguous requirementsClaims, rework, and acceptance risk

Transfer is rarely “set and forget.” Monitor supplier performance, contract assumptions, interfaces, and secondary risks.

Stakeholder and Communication Risk

Risk sourcePractical response
Unclear stakeholder expectationsDefine success criteria and acceptance thresholds
Conflicting risk appetiteFacilitate explicit trade-off decisions
Low stakeholder engagementTailor communications and involve decision makers
Hidden oppositionAnalyze influence and interests; monitor sentiment
Overly optimistic sponsor expectationsUse data, ranges, confidence levels, and scenarios
Technical team underreports riskCreate psychologically safe reporting channels
Distributed stakeholdersUse clear cadence, records, and escalation paths
Executive wants one deterministic dateExplain confidence ranges and assumptions

Common PMI-RMP Exam Traps

TrapBetter answer
Jumping straight to actionFirst identify, analyze, assign, and plan unless immediate action is required
Ignoring the risk management planUse it for roles, thresholds, definitions, reporting, and escalation
Treating risk as only negativeInclude opportunities
Confusing risk and issueOccurred risks are handled as issues while records are updated
Selecting transfer to eliminate responsibilityTransferred risks still require monitoring
Accepting high risks without approvalCheck thresholds and authority
Planning responses without ownersEvery significant response needs ownership
Forgetting residual and secondary risksDocument and analyze both
Using quantitative tools with weak dataValidate assumptions and data quality
Treating simulation as certaintySimulation provides probability-based forecasts
Ignoring stakeholder risk attitudeRisk priority depends partly on tolerance and thresholds
Failing to implement responsesMonitoring should verify response execution
Not updating lessons learnedRisk process improvement is continuous
Escalating everythingEscalate only when authority, threshold, or ownership requires it
Using reserves as a response strategyReserves support responses; they are not the whole response

Compact Formula Sheet

TopicFormula in plain text
Qualitative scoreProbability rating x Impact rating
EMVProbability x Impact
Total EMVSum of all probability x impact values
Triangular mean(Optimistic + Most likely + Pessimistic) / 3
PERT mean(Optimistic + 4 x Most likely + Pessimistic) / 6
PERT standard deviation(Pessimistic - Optimistic) / 6
Cost varianceEV - AC
Schedule varianceEV - PV
CPIEV / AC
SPIEV / PV
Simple EACBAC / CPI
ETCEAC - AC
VACBAC - EAC

Final Review Checklist

Before exam day, make sure you can quickly answer:

  • What artifact defines the risk process?
  • What artifact tracks individual risks?
  • When does a risk become an issue?
  • Who owns a risk versus a response action?
  • When should a risk be escalated?
  • Which response strategies apply to threats?
  • Which response strategies apply to opportunities?
  • What is the difference between residual and secondary risk?
  • When is qualitative analysis enough?
  • When is quantitative analysis justified?
  • What does EMV actually represent?
  • Why does data quality matter before scoring or modeling?
  • How do triggers, contingency plans, and fallback plans relate?
  • When does a risk response require change control?
  • How do agile practices change risk cadence without eliminating risk management?

Practical Next Step

Use this Quick Reference to drill scenario questions: for each practice item, identify the process, artifact, owner, threshold, and best next action before looking at the answer. Then review any missed questions against the tables above and continue with full-length PMI-RMP practice sets.