Exam Identity and Use
This Quick Reference supports candidates preparing for PMI’s PMI Certified Associate in Project Management (CAPM) exam, code CAPM. It is independent review support and is designed for fast recall, comparison, and practice-question decision making.
Use it to check:
- What artifact, role, or process fits a scenario.
- Whether a situation is predictive, agile, hybrid, or business-analysis focused.
- Which formula applies and how to interpret the result.
- What a project manager, team member, product owner, sponsor, or business analyst should do next.
CAPM Mental Model
| Exam cue | Think first | Then decide |
|---|
| “New project,” “authorization,” “funding” | Initiating | Project charter, sponsor approval, high-level risks/stakeholders |
| “How will we do the work?” | Planning | Management plans, baselines, requirements, estimates |
| “Work is being performed” | Executing | Team, communications, quality assurance, stakeholder engagement |
| “Compare actual to plan” | Monitoring and controlling | Variance, forecasts, change requests, corrective action |
| “Customer accepts deliverable” | Closing | Formal acceptance, lessons learned, final reports, archive |
| “Unclear requirements, frequent feedback” | Agile/adaptive | Iteration, backlog, product owner, inspect and adapt |
| “Stable requirements, regulated sequence” | Predictive | Up-front planning, baselines, change control |
| “Need business value clarity” | Business analysis | Needs assessment, requirements, traceability, acceptance criteria |
| “Someone asks for extra work” | Scope/change control | Do not just do it; evaluate and process the change |
| “Risk event happens” | Issue response | Use response plan, update issue log, assess changes |
Core PMI Project Terms
| Term | Practical meaning | Common exam trap |
|---|
| Project | Temporary effort to create a unique product, service, or result | Temporary does not mean short; operations are ongoing |
| Program | Related projects managed together for benefits | Program focuses on coordinated benefits, not just a big project |
| Portfolio | Projects/programs grouped to meet strategic objectives | Portfolio selection is strategy and investment focused |
| Product | Output or service delivered to users/customers | Product lifecycle can continue after the project ends |
| Project lifecycle | Phases from start to close | Can be predictive, iterative, incremental, agile, or hybrid |
| Development approach | How the product/service is created | Separate from the management lifecycle, though related |
| Deliverable | Verifiable product, result, or capability | Must be accepted against criteria |
| Milestone | Significant point or event | Usually zero duration |
| Constraint | Limitation such as time, cost, scope, quality, resources, risk | Not all constraints are equal in every scenario |
| Assumption | Believed true for planning | Must be validated; uncertainty can become risk |
| Baseline | Approved version of scope, schedule, or cost | Changes require formal control in predictive environments |
| Tailoring | Adapting methods to context | Not skipping discipline; choosing appropriate rigor |
| Value | Benefit, usefulness, or outcome delivered | PMI questions often favor value over mere activity completion |
Project, Program, Portfolio, and Operations
| Situation | Best classification | Why |
|---|
| Implement a new payroll system | Project | Temporary and unique deliverable |
| Maintain payroll every two weeks | Operations | Repetitive ongoing work |
| Modernize HR systems through multiple related projects | Program | Coordinated related projects for benefits |
| Select which internal transformation initiatives receive funding | Portfolio | Strategic prioritization across investments |
| Improve support desk response time continuously | Operations / continuous improvement | Ongoing process improvement unless a temporary initiative is defined |
| Build app v1, then transition support to IT operations | Project then operations | Project creates capability; operations sustain it |
PMI Principles and Performance Domains
PMBOK-Style Principles
| Principle | Exam-ready meaning |
|---|
| Stewardship | Act responsibly, ethically, and with care for resources and impact |
| Team | Build a collaborative, respectful project team environment |
| Stakeholders | Engage stakeholders proactively and continuously |
| Value | Focus decisions on expected benefit and outcomes |
| Systems thinking | Understand interdependencies and broader organizational context |
| Leadership | Influence, guide, motivate, and remove barriers |
| Tailoring | Fit approach, governance, and artifacts to the context |
| Quality | Build quality into processes and deliverables |
| Complexity | Recognize uncertainty, ambiguity, interfaces, and human factors |
| Risk | Address threats and opportunities proactively |
| Adaptability and resilience | Respond effectively to change and disruption |
| Change | Enable beneficial change and transition to new outcomes |
Performance Domains
| Domain | What to watch for in questions |
|---|
| Stakeholders | Identification, analysis, engagement, communication, expectations |
| Team | Culture, leadership, roles, conflict, performance |
| Development approach and lifecycle | Predictive vs agile vs hybrid selection |
| Planning | Progressive elaboration, baselines, plans, estimates |
| Project work | Execution, procurement, resources, issues, knowledge |
| Delivery | Scope completion, quality, acceptance, value delivery |
| Measurement | Metrics, variance, forecasts, performance reporting |
| Uncertainty | Risks, ambiguity, complexity, resilience |
Lifecycle and Approach Selection
| Approach | Choose when | Planning style | Delivery style | Change handling |
|---|
| Predictive / waterfall | Requirements are stable; sequence is known; high need for control | Up-front detailed planning | Deliver near the end or at major phase gates | Formal change control |
| Iterative | Need feedback to refine solution | Plan enough to repeat cycles | Rework/refine through iterations | Expected learning and refinement |
| Incremental | Need usable pieces delivered over time | Plan by increments | Deliver completed subsets | New increments can adjust scope |
| Agile / adaptive | Requirements uncertain; frequent feedback needed | Rolling wave, backlog-driven | Frequent value delivery | Change expected and prioritized |
| Hybrid | Some parts stable, others uncertain | Mix of predictive and adaptive planning | Predictive components plus agile increments | Formal control for baselined parts; backlog control for agile parts |
High-Yield Distinctions
| Pair | Distinction |
|---|
| Iterative vs incremental | Iterative improves the same solution through feedback; incremental delivers usable pieces |
| Predictive vs agile | Predictive protects baselines; agile optimizes learning and value delivery |
| Tailoring vs shortcutting | Tailoring is deliberate fit-for-purpose governance; shortcutting ignores needed controls |
| Product scope vs project scope | Product scope = features/functions; project scope = work to deliver them |
| Verification vs validation | Verification checks correctness against requirements; validation checks fitness for intended use |
| Risk vs issue | Risk may happen; issue has happened |
| Corrective action vs preventive action | Corrective realigns performance; preventive reduces chance of future variance |
| Quality assurance vs quality control | Assurance improves process; control inspects deliverables/results |
| Manage stakeholders vs manage communications | Stakeholders focuses engagement and relationships; communications focuses information flow |
Predictive Process Reference
Process Groups
| Process group | Purpose | Typical outputs |
|---|
| Initiating | Authorize project or phase | Project charter, stakeholder register |
| Planning | Define objectives, scope, approach, baselines | Project management plan, subsidiary plans, baselines |
| Executing | Complete work and coordinate people/resources | Deliverables, work performance data, issue log updates |
| Monitoring and controlling | Track, compare, control, and recommend changes | Work performance information, change requests, forecasts |
| Closing | Formally complete project/phase/contract | Accepted deliverables, final report, lessons learned archive |
Knowledge Area Quick Map
| Knowledge area | Main concern | Key artifacts / outputs | Exam cue |
|---|
| Integration | Coordinate all parts | Charter, project management plan, change log, lessons learned | “Coordinate,” “overall plan,” “change request” |
| Scope | Define and control what is included | Scope statement, WBS, scope baseline, requirements traceability matrix | “Extra feature,” “what work is included” |
| Schedule | Sequence and time work | Activity list, network diagram, schedule baseline | “Delay,” “critical path,” “float” |
| Cost | Estimate, budget, control costs | Cost estimates, cost baseline, forecasts | “Over budget,” “CPI,” “EAC” |
| Quality | Meet requirements and fitness for use | Quality management plan, metrics, quality reports | “Defects,” “inspection,” “process improvement” |
| Resource | Acquire, develop, manage team/resources | Resource management plan, team charter, assignments | “Team performance,” “resource conflict” |
| Communications | Ensure right information reaches right people | Communications management plan, reports | “Who needs what information when” |
| Risk | Manage uncertainty | Risk register, risk report, response plans | “Threat,” “opportunity,” “probability/impact” |
| Procurement | Buy products/services externally | Procurement strategy, bid documents, contracts | “Vendor,” “seller,” “contract” |
| Stakeholder | Identify and engage impacted parties | Stakeholder register, engagement plan | “Resistance,” “expectations,” “influence” |
Key Predictive Artifacts
| Artifact | Purpose | Created/used when | Do not confuse with |
|---|
| Business case | Justifies investment and expected benefits | Before or during initiation | Project charter |
| Benefits management plan | Describes how benefits will be measured and sustained | Initiation/planning | Scope baseline |
| Project charter | Formally authorizes project and PM authority | Initiating | Project management plan |
| Stakeholder register | Lists stakeholders and key attributes | Initiating, updated throughout | Communications plan |
| Project management plan | Integrated plan for executing, monitoring, controlling, closing | Planning, updated by change control | Schedule alone |
| Scope statement | Detailed product/project scope and exclusions | Planning | WBS |
| WBS | Hierarchical decomposition of total scope | Planning | Schedule or org chart |
| WBS dictionary | Detail for WBS components | Planning | Requirements document |
| Scope baseline | Approved scope statement + WBS + WBS dictionary | Planning/control | Product roadmap |
| Schedule baseline | Approved schedule model | Planning/control | Activity list |
| Cost baseline | Approved time-phased budget | Planning/control | Funding limit |
| Issue log | Tracks current problems needing action | Throughout | Risk register |
| Risk register | Records risks, analysis, owners, responses | Throughout | Issue log |
| Change log | Tracks change requests and status | Control changes | Backlog |
| Lessons learned register | Captures learning during the project | Throughout | Final archive only |
| Final report | Summarizes performance and closure | Closing | Status report |
Project Charter vs Project Management Plan
| Attribute | Project charter | Project management plan |
|---|
| Main purpose | Authorize the project | Direct how the project will be executed and controlled |
| Level of detail | High level | Detailed and integrated |
| Approved by | Sponsor or authorized initiator | Appropriate governance/change authority |
| Contains | Purpose, objectives, high-level requirements, high-level risks, milestones, budget, PM authority | Subsidiary plans, baselines, governance, methods |
| Timing | Initiating | Planning and updated through control |
| Exam cue | “Project does not yet exist formally” | “How should the work be managed?” |
Scope and Requirements
| Concept | Meaning | Exam cue |
|---|
| Requirement | Condition or capability needed by stakeholder/product | “The system must…” |
| Acceptance criteria | Conditions that must be met for acceptance | “Done means…” |
| Product scope | Features/functions of the deliverable | User-facing capability |
| Project scope | Work required to deliver product scope | Activities and deliverables |
| WBS | Decomposes total project scope | Work packages |
| Work package | Lowest WBS level typically used for estimating/managing | Assignable work |
| Scope baseline | Approved scope definition | Used to detect scope variance |
| Scope creep | Uncontrolled expansion of scope | Extra work without approval |
| Gold plating | Adding unrequested features | Team adds value not requested; still bad practice |
| Requirements traceability matrix | Links requirements to business need, deliverables, tests, acceptance | Impact analysis and coverage |
Schedule Reference
| Term | Meaning | Decision cue |
|---|
| Activity | Work needed to produce deliverable | Decompose work packages into activities |
| Dependency | Logical relationship between activities | Sequence work |
| Mandatory dependency | Required by nature/contract | Cannot easily change |
| Discretionary dependency | Preferred/best practice | Can be revised for compression |
| External dependency | Outside project control | Monitor and manage |
| Lead | Successor can start before predecessor fully finishes | Overlap work |
| Lag | Waiting time between activities | Delay successor |
| Critical path | Longest path through network; determines shortest project duration | Activities with zero/lowest float |
| Total float | How long activity can slip without delaying project finish | Schedule flexibility |
| Free float | How long activity can slip without delaying successor | Local flexibility |
| Fast tracking | Do activities in parallel that were sequential | Adds risk/rework |
| Crashing | Add resources to shorten duration | Adds cost |
Schedule Compression Decision
| Situation | Better technique | Why |
|---|
| Need shorten schedule and budget is available | Crashing | Adds resources to critical-path work |
| Need shorten schedule with limited budget but risk acceptable | Fast tracking | Overlaps work; increases rework risk |
| Non-critical activity is late but has float | Use float, monitor | May not affect project finish |
| Critical-path activity is late | Compress, re-sequence, or change scope | Directly affects finish date |
| Customer requests earlier date without changing scope/cost | Analyze impact first | Do not commit without evaluating constraints |
Core Earned Value Terms
| Term | Plain formula / meaning | Interpretation |
|---|
| PV | Planned Value | Budgeted value of work planned by a date |
| EV | Earned Value | Budgeted value of work actually completed |
| AC | Actual Cost | Actual cost incurred |
| BAC | Budget at Completion | Total approved budget |
| CV | EV - AC | Positive = under budget; negative = over budget |
| SV | EV - PV | Positive = ahead of schedule; negative = behind schedule |
| CPI | EV / AC | Greater than 1 = cost efficient |
| SPI | EV / PV | Greater than 1 = schedule efficient |
| EAC | Estimate at Completion | Forecast total cost |
| ETC | EAC - AC | Expected cost to finish remaining work |
| VAC | BAC - EAC | Positive = expected under budget; negative = over budget |
| TCPI | (BAC - EV) / (BAC - AC) or (BAC - EV) / (EAC - AC) | Required future cost performance |
\[
\text{CV} = \text{EV} - \text{AC}
\]\[
\text{SV} = \text{EV} - \text{PV}
\]\[
\text{CPI} = \frac{\text{EV}}{\text{AC}}
\]\[
\text{SPI} = \frac{\text{EV}}{\text{PV}}
\]\[
\text{EAC} = \frac{\text{BAC}}{\text{CPI}}
\]\[
\text{ETC} = \text{EAC} - \text{AC}
\]\[
\text{VAC} = \text{BAC} - \text{EAC}
\]
EAC Selection
| Situation | Use | Plain formula |
|---|
| Current cost performance expected to continue | Cost efficiency drives forecast | EAC = BAC / CPI |
| Original estimate no longer valid | Re-estimate remaining work | EAC = AC + bottom-up ETC |
| Future work expected at original budgeted rate | Past variance is atypical | EAC = AC + (BAC - EV) |
| Both cost and schedule performance affect remaining work | Cost and schedule issues continue | EAC = AC + ((BAC - EV) / (CPI x SPI)) |
Earned Value Interpretation
| Result | Meaning | Likely management response |
|---|
| CV < 0 | Over budget | Analyze causes; consider corrective action |
| CV > 0 | Under budget | Verify work is complete and quality is acceptable |
| SV < 0 | Behind schedule | Check critical path and schedule forecast |
| SV > 0 | Ahead of schedule | Confirm sequencing and value actually earned |
| CPI < 1 | Cost inefficient | Investigate spending, productivity, estimates |
| CPI > 1 | Cost efficient | Validate no quality/scope tradeoff hidden |
| SPI < 1 | Schedule inefficient | Consider compression or re-planning |
| SPI > 1 | Schedule efficient | Confirm completed work aligns with plan |
| Concept | Plain formula | Use |
|---|
| Communication channels | n(n - 1) / 2 | Number of potential communication paths |
| Triangular estimate | (O + M + P) / 3 | Simple three-point average |
| PERT / beta expected estimate | (O + 4M + P) / 6 | Weighted estimate favoring most likely |
| Beta standard deviation | (P - O) / 6 | Uncertainty spread |
| Range estimate | Expected estimate ± standard deviation | Quick estimate range |
| Expected monetary value | Probability x impact | Quantitative risk analysis |
| Net present value | Present value of benefits - present value of costs | Investment comparison |
| ROI | (Benefit - Cost) / Cost | Return relative to cost |
| Velocity | Completed story points per iteration | Agile planning trend |
| Cycle time | Time from work start to completion | Flow efficiency |
| Lead time | Time from request to delivery | Customer wait time |
\[
\text{Communication Channels} = \frac{n(n-1)}{2}
\]\[
\text{PERT Expected Duration} = \frac{O + 4M + P}{6}
\]\[
\text{Expected Monetary Value} = \text{Probability} \times \text{Impact}
\]
Quality Reference
| Concept | Meaning | Exam cue |
|---|
| Quality | Degree to which requirements are met | “Conformance to requirements” |
| Grade | Category or rank of functionality | Low grade may be acceptable; low quality is not |
| Prevention | Avoid defects | Preferred over inspection |
| Inspection | Find defects after work | More costly than prevention |
| Cost of quality | Cost of conformance + cost of nonconformance | Invest in prevention/appraisal |
| Cost of conformance | Prevention + appraisal costs | Training, testing, reviews |
| Cost of nonconformance | Internal + external failure costs | Rework, warranty, complaints |
| Quality assurance | Process-focused; ensure correct processes | Audits, process analysis |
| Quality control | Product/result-focused; verify deliverables | Inspection, testing, measurements |
| Continuous improvement | Ongoing process improvement | Retrospectives, lessons learned, Kaizen-style thinking |
| Tool | Use |
|---|
| Check sheet | Collect defect/frequency data |
| Pareto chart | Identify most significant causes |
| Cause-and-effect diagram | Explore root causes |
| Control chart | Determine process stability |
| Histogram | Show distribution/frequency |
| Scatter diagram | Show relationship between variables |
| Flowchart | Visualize process steps |
| Checklist | Verify required steps/items |
| Audit | Check compliance with process |
| Design of experiments | Analyze variable effects on outcomes |
Risk Reference
| Term | Meaning | Exam action |
|---|
| Risk | Uncertain event/condition affecting objectives | Record in risk register |
| Threat | Negative risk | Avoid, mitigate, transfer, accept, escalate |
| Opportunity | Positive risk | Exploit, enhance, share, accept, escalate |
| Trigger | Warning sign that risk may occur | Monitor |
| Risk owner | Person responsible for risk response | Assign clearly |
| Residual risk | Risk remaining after response | Monitor/accept/respond |
| Secondary risk | New risk created by response | Analyze and manage |
| Risk appetite | General willingness to take risk | Align response |
| Risk threshold | Specific measurable limit | Escalate if exceeded |
| Contingency reserve | For identified risks | Part of cost/schedule baseline when approved |
| Management reserve | For unknown-unknowns | Outside baseline; controlled by management |
Risk Response Selection
| Scenario | Threat response | Opportunity response |
|---|
| Remove uncertainty entirely | Avoid | Exploit |
| Reduce probability or impact | Mitigate | Enhance |
| Shift ownership to third party | Transfer | Share |
| Take no proactive action beyond monitoring | Accept | Accept |
| Outside project manager authority | Escalate | Escalate |
Communications and Stakeholder Management
| Need | Best artifact/action |
|---|
| Identify who is affected by the project | Stakeholder register |
| Analyze power, interest, influence, impact | Stakeholder analysis |
| Decide how to engage resistant stakeholders | Stakeholder engagement plan |
| Decide what information goes to whom and when | Communications management plan |
| Track stakeholder concerns and actions | Issue log |
| Report actual project performance | Performance report |
| Communicate urgent blocker | Direct communication/escalation per plan |
| Handle misunderstanding | Use active listening, confirm message, adjust communication method |
Stakeholder Engagement Levels
| Level | Meaning |
|---|
| Unaware | Does not know about project/impact |
| Resistant | Aware but opposed |
| Neutral | Aware but neither supportive nor resistant |
| Supportive | Aware and supportive |
| Leading | Actively engaged in project success |
Communication Method Selection
| Method | Best for | Weakness |
|---|
| Interactive | Meetings, calls, workshops, conflict resolution | Requires availability |
| Push | Email, memo, report sent to recipients | Does not ensure understanding |
| Pull | Portal, repository, dashboard | Requires stakeholder to retrieve information |
| Formal written | Contracts, approvals, baselines | Slower but authoritative |
| Informal verbal | Quick alignment | Poor audit trail |
Resources, Team, and Leadership
| Concept | Meaning | Exam cue |
|---|
| Functional organization | Functional manager has high authority | PM coordinates with departments |
| Projectized organization | PM has high authority | Dedicated project team |
| Matrix organization | Authority shared | Resource negotiation is common |
| RACI | Responsible, Accountable, Consulted, Informed | Clarifies role ambiguity |
| Team charter | Team values, ground rules, working agreements | Conflict prevention |
| Servant leadership | Remove impediments, support team autonomy | Agile and collaborative scenarios |
| Emotional intelligence | Understand/manage self and relationships | Conflict, negotiation, stakeholder trust |
| Conflict management | Address disagreement constructively | Collaborate/problem solve often preferred |
| Virtual team | Team members geographically dispersed | Communication planning is critical |
Conflict Techniques
| Technique | Meaning | When appropriate |
|---|
| Collaborate / problem solve | Seek win-win and root cause resolution | Important issues, time available |
| Compromise / reconcile | Each side gives up something | Moderate urgency |
| Smooth / accommodate | Emphasize agreement | Low-stakes or relationship priority |
| Force / direct | One viewpoint imposed | Emergency or safety issue |
| Withdraw / avoid | Delay or retreat | Cooling-off or low-priority issue |
Procurement Reference
| Contract type | Buyer risk | Seller risk | Best when |
|---|
| Firm fixed price | Lower | Higher | Scope is well defined |
| Fixed price incentive fee | Medium | Medium | Need cost/schedule/performance incentives |
| Fixed price with economic price adjustment | Lower/medium | Medium | Long duration with market uncertainty |
| Cost plus fixed fee | Higher | Lower | Scope uncertain; fixed seller fee |
| Cost plus incentive fee | Higher | Medium | Need seller cost-performance incentive |
| Cost plus award fee | Higher | Medium | Subjective performance award criteria |
| Time and materials | Medium/high | Medium/low | Staff augmentation or undefined quantity; needs oversight |
Procurement Decision Cues
| Scenario | Likely action |
|---|
| Need external goods/services | Plan procurement |
| Need bids/proposals | Conduct procurement |
| Seller performance issue | Control procurement |
| Contract complete | Close procurement |
| Ambiguous contract term | Follow contract and procurement procedures; involve authorized roles |
| Seller requests change | Process through contract/change control |
| Buyer wants lowest risk with clear scope | Fixed price |
| Scope unclear and buyer can manage oversight | Cost-reimbursable or T&M may appear |
Agile and Adaptive Reference
Agile Values in Exam Language
| Agile value | Practical interpretation |
|---|
| Individuals and interactions over processes and tools | Collaboration matters more than rigid procedure |
| Working product over comprehensive documentation | Useful increments demonstrate progress |
| Customer collaboration over contract negotiation | Frequent feedback reduces misunderstanding |
| Responding to change over following a plan | Change can improve value when managed through backlog |
Scrum Reference
| Element | Purpose | Exam cue |
|---|
| Product owner | Maximizes product value; orders product backlog | Owns priorities, acceptance, value |
| Scrum master | Servant leader; removes impediments; supports Scrum | Facilitates, coaches, protects process |
| Developers / team | Create the increment | Self-managing, cross-functional |
| Product backlog | Ordered list of product work | Changes as learning occurs |
| Sprint backlog | Work selected for sprint plus plan | Team-owned during sprint |
| Increment | Usable completed product slice | Meets definition of done |
| Sprint planning | Select sprint goal and backlog items | Start of sprint |
| Daily scrum | Inspect progress toward sprint goal | Short team coordination |
| Sprint review | Inspect product increment with stakeholders | Feedback on product |
| Sprint retrospective | Improve team/process | After sprint review, before next sprint |
| Definition of done | Shared quality/completion standard | Prevents incomplete work from being counted |
Agile Planning Levels
| Level | Focus |
|---|
| Vision | Product purpose and desired outcome |
| Roadmap | Major releases/features over time |
| Release plan | Target capabilities for release |
| Iteration/sprint plan | Near-term work for iteration |
| Daily plan | Immediate coordination and impediments |
Agile Metrics
| Metric | Meaning | Trap |
|---|
| Velocity | Amount of work completed per iteration | Use for planning, not comparing teams |
| Burndown chart | Work remaining over time | Flat line may show blockers or overcommitment |
| Burnup chart | Work completed and total scope | Shows scope growth clearly |
| Cumulative flow diagram | Work across states over time | Widening band may indicate bottleneck |
| Cycle time | Start-to-finish work time | Helps improve flow |
| Lead time | Request-to-delivery time | Customer-focused waiting time |
| WIP limit | Maximum work in progress | Improves focus and flow |
Agile Change Handling
| Situation | Preferred response |
|---|
| Stakeholder requests new feature | Product owner evaluates and orders backlog |
| Team discovers better technical approach | Discuss with team/product owner; adapt if valuable |
| Work does not meet definition of done | Do not count as complete |
| Sprint goal at risk | Team raises impediment; scrum master helps remove |
| Stakeholder wants to change current sprint work | Protect sprint goal; product owner considers tradeoffs |
| Product backlog has too much uncertainty | Refine backlog, split stories, clarify acceptance criteria |
| Velocity drops | Inspect causes; do not punish the team |
| Frequent defects | Strengthen definition of done, testing, engineering practices |
Predictive vs Agile Decision Table
| Question stem says… | Best mindset |
|---|
| Detailed requirements approved and baselined | Predictive control |
| Regulatory phase gate or contractual milestone | Predictive or hybrid governance |
| Customer wants frequent demos and evolving scope | Agile/adaptive |
| Team is delivering usable pieces every few weeks | Agile/incremental |
| Sponsor asks for impact of scope change on cost/schedule | Predictive change analysis |
| Product owner reorders work based on value | Agile backlog management |
| Project has hardware build plus software iteration | Hybrid |
| Requirements cannot be fully known at start | Agile/iterative discovery |
| Late change to signed baseline | Formal change request |
| New feature request in backlog | Product owner prioritization |
Business Analysis Reference for CAPM
| BA concept | Meaning | Exam cue |
|---|
| Needs assessment | Understand problem/opportunity and business need | “Why is this project needed?” |
| Business requirements | High-level organizational needs | Strategic outcomes |
| Stakeholder requirements | Needs of stakeholders/user groups | Expectations and constraints |
| Solution requirements | Product capabilities and qualities | Functional/nonfunctional requirements |
| Functional requirement | What the solution does | Behavior/capability |
| Nonfunctional requirement | How well the solution performs | Security, performance, usability |
| Transition requirement | Temporary capability needed to move to future state | Data migration, training |
| Elicitation | Draw out information from stakeholders | Interviews, workshops, observation |
| Requirements analysis | Organize, model, prioritize, validate requirements | Resolve conflicts and gaps |
| Requirements traceability | Link requirement to source, design, test, deliverable | Impact analysis |
| Acceptance criteria | Conditions for accepting work | Testable completion |
| Product roadmap | High-level product direction | Releases/features over time |
| Backlog refinement | Clarify and split upcoming backlog items | Agile BA work |
Elicitation Technique Selection
| Technique | Best for | Watch out |
|---|
| Interview | Deep individual insight | May be biased or incomplete |
| Workshop | Shared understanding and fast alignment | Needs facilitation |
| Survey/questionnaire | Many stakeholders | Limited depth |
| Observation/job shadowing | Understand actual work process | People may behave differently when observed |
| Document analysis | Existing rules/processes | Documents may be outdated |
| Prototype | Clarify uncertain requirements | Stakeholders may think prototype is finished product |
| Brainstorming | Generate options quickly | Needs later filtering |
| Focus group | Gather reactions from selected users | Not statistically broad |
Requirement Prioritization
| Method | Meaning |
|---|
| MoSCoW | Must, Should, Could, Won’t for now |
| Ranking | Order from highest to lowest priority |
| Weighted scoring | Score options against weighted criteria |
| Kano-style thinking | Basic needs, performance needs, delighters |
| Value vs effort | Prioritize high-value, feasible items |
| Risk-based prioritization | Do risky/uncertain work earlier |
Change Control Decision Reference
| Scenario | What should happen next? | Why |
|---|
| Stakeholder requests scope addition in predictive project | Document change request and analyze impact | Baselines require control |
| Team member starts extra unapproved feature | Stop gold plating; evaluate through change control/backlog | Prevent uncontrolled scope |
| Defect found in deliverable | Log, analyze, correct according to quality/change process | Defect repair may need approval |
| Approved change affects schedule baseline | Update impacted baselines and plans | Keep plans integrated |
| Emergency change needed | Follow approved emergency change procedure if defined | Control still applies |
| Change request rejected | Communicate decision and update change log | Maintain transparency |
| Agile stakeholder requests new feature | Product owner evaluates and orders backlog | Backlog is the change mechanism |
| Change exceeds PM authority | Escalate to change control board/sponsor as appropriate | Authority matters |
Integrated Change Control Flow
flowchart TD
A[Change idea or variance] --> B[Document change request]
B --> C[Analyze impact on scope, schedule, cost, quality, risk, resources, stakeholders]
C --> D{Within PM authority?}
D -- Yes --> E[Approve, defer, or reject per governance]
D -- No --> F[Submit to CCB/sponsor/authorized body]
E --> G[Update change log]
F --> G
G --> H{Approved?}
H -- Yes --> I[Update plans, baselines, documents, communicate]
H -- No --> J[Communicate decision, keep current baseline]
“What Should the Project Manager Do Next?”
| Exam situation | Usually do next | Avoid |
|---|
| Project lacks formal approval | Obtain/confirm charter authorization | Begin full execution |
| Stakeholder is newly identified | Add to stakeholder register and analyze | Ignore until next phase |
| Team reports a risk may occur | Record/analyze in risk register | Treat as issue before it happens |
| Risk event occurs | Implement response; update issue log/risk documents | Re-plan everything immediately |
| Customer requests scope change | Submit/evaluate change request | Add work informally |
| Work performance differs from baseline | Analyze variance and forecast | Jump straight to corrective action |
| Corrective action affects baseline | Process change request | Update baseline without approval |
| Team conflict emerges | Address collaboratively and early | Escalate first unless severe |
| Stakeholder is resistant | Analyze concerns and adjust engagement | Remove stakeholder from communication |
| Vendor misses deliverable | Review contract and manage procurement | Personally redo seller work without process |
| Agile team has impediment | Scrum master/team removes or escalates impediment | Blame individual team members |
| Agile product priorities change | Product owner reorders backlog | PM unilaterally changes sprint scope |
| Deliverable completed | Verify/control quality, then seek acceptance as applicable | Close project immediately |
| Project is ending | Confirm acceptance, close procurements, archive, lessons learned | Skip final administrative closure |
Ethics and Professional Conduct Cues
| Theme | Exam behavior |
|---|
| Responsibility | Own decisions, follow policies, report truthfully |
| Respect | Treat stakeholders fairly and professionally |
| Fairness | Avoid favoritism, discrimination, and improper advantage |
| Honesty | Provide accurate information; do not misrepresent status |
| Conflict of interest | Disclose and follow appropriate guidance |
| Confidentiality | Protect sensitive information |
| Gifts or favors | Avoid anything that could impair objectivity or appear improper |
| Bad news | Report accurately and promptly; do not hide problems |
| Pressure to falsify | Refuse and escalate through proper channels |
Common CAPM Traps
| Trap | Correct exam thinking |
|---|
| “The PM should just approve it” | Check authority, governance, and change process |
| “Agile means no documentation” | Agile uses right-sized documentation |
| “Customer asked, so team should do it” | Customer input still needs prioritization/control |
| “Under budget always good” | Could indicate incomplete scope or quality issues |
| “Fast tracking is free” | It increases risk and potential rework |
| “Crashing always works” | Only useful where added resources shorten critical-path work |
| “Risk response after event is risk management” | Once it occurs, it is issue management using planned responses |
| “High power stakeholder can be ignored if uninterested” | Manage closely or keep satisfied depending analysis |
| “Velocity is a productivity ranking” | It is for team planning, not cross-team comparison |
| “Lessons learned happen only at the end” | Capture throughout and archive at closure |
| “Quality is inspected in at the end” | Quality should be planned and built in |
| “Scope baseline equals requirements list” | Scope baseline includes scope statement, WBS, WBS dictionary |
Last-Minute Review Checklist
- Know the difference between project charter, project management plan, and baselines.
- Practice earned value interpretation: CV/SV/CPI/SPI and common EAC variants.
- Be able to choose predictive, agile, iterative, incremental, or hybrid from scenario clues.
- Memorize risk responses for threats and opportunities.
- Know Scrum roles, events, artifacts, and who owns prioritization.
- Understand business analysis flow: need, stakeholders, elicitation, requirements, traceability, acceptance.
- For “what next” questions, first identify whether the situation is a risk, issue, change, defect, conflict, or stakeholder engagement problem.
- Favor ethical, transparent, documented, and value-focused actions.
- Do not skip analysis before escalation unless there is an immediate safety, legal, or authority issue.
Practical Next Step
Use this Quick Reference as a checklist while working CAPM-style practice questions: after each missed item, tag it as predictive process, agile, business analysis, formula, artifact, role, or decision sequence, then drill that category until the correct next action becomes automatic.