Free CPA Canada Finance Practice Questions: Capital Budgeting

Practice 10 free CPA Canada Finance sample exam questions on Capital Budgeting, with answers, explanations, practice tests, topic drills, and the Finance Prep next step.

CPA Canada means Chartered Professional Accountants of Canada. Use this focused CPA Canada Finance page as a short practice test for Capital Budgeting. The items are original Finance Prep sample exam questions built for scenario-based practice, not trivia, puzzle questions, official CPA Canada Finance Elective questions, copied live-exam content, or exam dumps.

Topic snapshot

FieldDetail
Exam routeCPA Canada Finance
IssuerChartered Professional Accountants of Canada (CPA Canada)
Topic areaCapital Budgeting
Blueprint weight13%
Page purposeFocused sample questions before returning to mixed practice

How to use this topic drill

Use this page to isolate Capital Budgeting for CPA Canada Finance. Work through the 10 questions first, then review the explanations and return to mixed practice in Finance Prep.

PassWhat to doWhat to record
First attemptAnswer without checking the explanation first.The fact, rule, calculation, or judgment point that controlled your answer.
ReviewRead the explanation even when you were correct.Why the best answer is stronger than the closest distractor.
RepairRepeat only missed or uncertain items after a short break.The pattern behind misses, not the answer letter.
TransferReturn to mixed practice once the topic feels stable.Whether the same skill holds up when the topic is no longer obvious.

Blueprint context: 13% of the practice outline. A focused topic score can overstate readiness if you recognize the pattern too quickly, so use it as repair work before timed mixed sets.

Sample questions

These are original Finance Prep practice questions aligned to this topic area. They are not official CPA Canada Finance Elective questions, copied live-exam content, or exam dumps. Use them to preview question style and explanation depth before continuing with topic drills, mixed sets, and timed mock exams in Finance Prep.

Question 1

Topic: Capital Budgeting

Harbour Tools Ltd. is evaluating three capital projects using a 10% discount rate. Management has confirmed there is no capital rationing and each project can be funded if it is financially acceptable.

Projects A and B are two alternative automation systems for the same production line, so only one can be installed. Project C is a separate packaging upgrade that can be completed regardless of which automation system is selected.

ProjectRelationshipInitial outlayPresent value of cash inflows
AAlternative automation system$500,000$665,000
BAlternative automation system$300,000$420,000
CIndependent packaging upgrade$200,000$250,000

Which recommendation best applies the capital budgeting decision rules and identifies the total expected increase in value?

  • A. Accept only Project A, for a total NPV of $165,000.
  • B. Accept Project A and Project C, for a total NPV of $215,000.
  • C. Accept Projects A, B, and C, for a total NPV of $335,000.
  • D. Accept Project B and Project C, for a total NPV of $170,000.

Best answer: B

What this tests: Capital Budgeting

Explanation: For independent projects, the usual NPV rule is to accept each project with a positive NPV, assuming no capital rationing or other limiting constraint. For mutually exclusive projects, accepting one prevents accepting the other, so the decision should compare the alternatives and select the one that creates the most value. Project A has an NPV of $165,000 ($665,000 - $500,000), while Project B has an NPV of $120,000 ($420,000 - $300,000). Because A and B are mutually exclusive, Project A is preferred. Project C has an NPV of $50,000 ($250,000 - $200,000) and is independent, so it should also be accepted. The total expected increase in value is $165,000 + $50,000 = $215,000.

  • Selecting Project B and Project C uses the lower-value automation alternative, even though Project A has the higher NPV.
  • Selecting all three projects incorrectly treats mutually exclusive automation systems as if both could be accepted.
  • Selecting only Project A ignores the positive-NPV independent packaging upgrade.

Projects A and B are mutually exclusive, so the higher NPV alternative is selected, and independent Project C is also accepted because its NPV is positive.


Question 2

Topic: Capital Budgeting

Boreal Packaging Inc., a private Canadian manufacturer, is considering a $4.8 million automated filling line. The COO wants the board to approve the purchase at next week’s meeting because the supplier will hold pricing for only 10 days.

The finance manager summarized the available information:

FactCurrent analysis
Base-case NPV$0.9 million positive, using the company’s 9% WACC
Payback3.8 years
Debt capacityProject would use nearly all remaining bank availability
Covenant forecastDebt-to-EBITDA would be 2.9 times; limit is 3.0 times
SensitivityNPV becomes negative if volume is 10% lower or startup is delayed six months

Additional notes: the sales volume assumption is based on a non-binding customer letter, no alternative such as leasing or refurbishing the existing line has been analyzed, and $750,000 of incremental inventory required at startup has not been included in the cash flows. Boreal normally approves projects under $1 million by email and has no formal threshold for independent review, sensitivity analysis, financing review, or post-completion follow-up.

Which interpretation is most appropriate?

  • A. A formal capital budgeting process would improve the decision because the project is material, financing-constrained, sensitive to uncertain assumptions, and missing key cash-flow and alternative analyses.
  • B. The board should approve the project now and complete the formal analysis after installation, because the supplier price hold is the most time-sensitive fact.
  • C. The project should be rejected immediately because one sensitivity case produces a negative NPV.
  • D. The positive base-case NPV means a formal process is unnecessary, because the project already exceeds the company’s required return.

Best answer: A

What this tests: Capital Budgeting

Explanation: A formal capital budgeting process is most useful when a proposed project is material, difficult to reverse, strategically important, capital-constrained, or highly dependent on uncertain assumptions. Boreal’s project has several of these characteristics: it is much larger than routine approvals, nearly exhausts borrowing capacity, is close to a covenant limit, has a base-case NPV that reverses under plausible downside cases, and omits required working capital. The absence of alternatives analysis also weakens the decision support. A structured process would not automatically approve or reject the project; it would require consistent relevant cash flows, review of financing capacity, sensitivity or scenario analysis, comparison of feasible alternatives, clear approval authority, and later accountability through post-completion review.

  • A positive base-case NPV is not enough when key cash flows are missing and the result is highly sensitive to uncertain sales and timing assumptions.
  • A negative downside sensitivity does not, by itself, require immediate rejection; it signals the need for better risk assessment and decision governance.
  • A supplier deadline may create urgency, but committing before completing material financing and cash-flow analysis increases decision risk.

The facts indicate a high-stakes project where structured review, relevant cash-flow discipline, sensitivity analysis, and governance approval would reduce the risk of a poorly supported commitment.


Question 3

Topic: Capital Budgeting

Mera Tools Ltd. uses a two-stage capital allocation screen. A project must first have an NPV of at least $0 using the risk-adjusted discount rate. If a project meets the financial benchmark but has a binding feasibility or strategic constraint, it is revised before approval rather than classified as a financial failure. All cash flows are after tax and occur at year-end except the initial investment today. Use the provided present value factors.

ItemProject AlphaProject Beta
Initial investment$600,000$500,000
Annual cash inflow$220,000 for 3 years$160,000 for 4 years
Terminal cash inflow$90,000 in year 3$0
Risk-adjusted discount rate10%12%
PV annuity factor2.4873.037
PV factor for terminal inflow0.751n/a
Specialized labour required in year 118,000 hours8,000 hours
Specialized labour available15,000 hours12,000 hours

Both projects support Mera’s approved product strategy, and Alpha could be redesigned to reduce the year 1 labour requirement. Which conclusion should the CPA recommend?

  • A. Alpha should be approved as-is because its NPV is positive; Beta should be revised because its NPV shortfall is small.
  • B. Alpha meets the financial benchmark with an NPV of about $14,730 but should be revised for feasibility; Beta fails the financial benchmark with an NPV of about negative $14,080.
  • C. Alpha fails the financial benchmark with an NPV of about negative $52,860; Beta should proceed because it fits the labour and strategy constraints.
  • D. Both projects should be accepted because each has total undiscounted cash inflows greater than its initial investment.

Best answer: B

What this tests: Capital Budgeting

Explanation: The financial screen and the feasibility screen answer different questions. Alpha’s NPV is $220,000 × 2.487 + $90,000 × 0.751 - $600,000 = $14,730, so it passes the NPV benchmark. However, it requires 18,000 specialized labour hours when only 15,000 are available. Since the project is strategically aligned and can be redesigned, the appropriate conclusion is to revise Alpha for feasibility rather than reject it for failing the financial benchmark. Beta’s NPV is $160,000 × 3.037 - $500,000 = negative $14,080, so it fails the financial benchmark even though it fits the labour and strategy constraints.

  • Treating Alpha as a financial failure omits the terminal cash inflow, which changes the NPV from negative to positive.
  • Approving Alpha as-is ignores the binding year 1 labour constraint, even though the financial benchmark is met.
  • Accepting both projects based on undiscounted cash inflows ignores the risk-adjusted NPV benchmark.

Alpha has a positive NPV but exceeds available labour capacity, while Beta fits the constraints but has a negative NPV.


Question 4

Topic: Capital Budgeting

Ridgeway Components approved a five-year automation project to relieve capacity constraints and enter a higher-margin product line. Two years later, you are reviewing management’s capital project post-audit.

MeasureApproval forecastActual/reforecast at audit
Initial capital cost$3,000,000$3,360,000
Commercial startJan. 1, 2024July 1, 2024
Annual operating cash inflow before working capital$950,000$330,000 in 2024; $650,000 in 2025; $720,000 annually for 2026-2028
Working capital tied up until project end$350,000$520,000
NPV at 9%$620,000($540,000)

Management’s draft conclusion states: “The NPV shortfall is adequately explained by the $360,000 capital overrun and the six-month start-up delay. The original demand and working-capital assumptions remain reasonable because the project generated positive operating cash inflows in 2025 and signed orders support profitable operations through 2028.”

Which interpretation is most appropriate?

  • A. The post-audit should replace project cash flows with accounting income after depreciation, because accounting profit is the correct basis for explaining capital project performance.
  • B. The post-audit should ignore the original approval forecast and assess only whether the reforecast NPV is positive using current signed orders.
  • C. The post-audit is incomplete because it identifies some adverse factors but does not explain the sustained operating cash-flow shortfall or higher working-capital requirement against the original assumptions.
  • D. The post-audit is adequate because the project has positive operating cash inflows and therefore the lower NPV must mainly reflect timing differences from the delayed launch.

Best answer: C

What this tests: Capital Budgeting

Explanation: A capital project post-audit should compare actual and reforecast results with the approval case and explain the material variances in the project drivers. Here, the capital overrun and six-month delay are real adverse factors, but they do not address the continuing underperformance. The 2025 cash inflow of $650,000 and the 2026-2028 reforecast of $720,000 are materially below the original $950,000 annual forecast. Working capital is also $170,000 higher than expected. Those facts point to demand, margin, operating, or working-capital assumptions that need to be investigated and incorporated into the variance explanation. Positive cash inflow does not mean the project met expectations, and the original forecast remains the proper benchmark for explaining the NPV decline.

  • Treating positive cash inflows as sufficient ignores whether the project achieved the forecast cash flows used to approve the investment.
  • Ignoring the approval forecast would defeat the purpose of a post-audit, which is to compare actual results with the investment case.
  • Using accounting income after depreciation would use the wrong basis; capital budgeting performance should focus on relevant cash flows and NPV drivers.

The actual and reforecast annual cash inflows remain well below the $950,000 forecast, and working capital is $170,000 higher, so the variance is not fully explained by only the overrun and delay.


Question 5

Topic: Capital Budgeting

Northview Furniture Ltd. is evaluating a four-year automated cutting machine. Management prepared the capital project exhibit below and recommends approval. Income taxes and financing cash flows are to be ignored. All operating cash flows occur at each year-end. The required return is 10%.

Relevant facts:

  • Equipment purchase price paid immediately: $720,000
  • Required installation cost paid immediately: $60,000
  • Operator training paid immediately: $30,000
  • Additional net working capital paid immediately: $100,000, fully recovered at the end of Year 4
  • Annual incremental cash inflow before maintenance and depreciation: $250,000
  • Annual maintenance cash cost: $45,000
  • Straight-line depreciation: $180,000 per year
  • Four-year annuity factor at 10%: 3.170
  • Year 4 present value factor at 10%: 0.683

Management’s exhibit:

Purchase price paid immediately                         ($720,000)
Annual cash benefit: $250,000 - $45,000 + $180,000       $385,000
PV of annual cash benefit: $385,000 × 3.170            $1,220,450
Estimated NPV                                            $500,450

Which weakness has the largest adverse impact on NPV and should be raised first?

  • A. Omitting the $30,000 operator training cost, overstating NPV by $30,000.
  • B. Omitting the net working-capital investment and recovery, overstating NPV by $31,700.
  • C. Omitting the $60,000 installation cost, overstating NPV by $60,000.
  • D. Including the $180,000 annual depreciation in cash benefits, overstating NPV by $570,600.

Best answer: D

What this tests: Capital Budgeting

Explanation: Capital project evaluations should use incremental cash flows, not accounting income. Since taxes are ignored, depreciation creates no cash tax shield and should not be included as a project benefit. The NPV overstatement from including depreciation is $180,000 × 3.170 = $570,600. This is larger than the omitted immediate installation cost of $60,000, the omitted training cost of $30,000, and the net present value effect of working capital: $100,000 outflow less $68,300 recovery, or $31,700. Correcting depreciation alone changes management’s NPV from $500,450 to negative $70,150, before considering the other omitted costs.

  • Installation is an incremental immediate cash outflow, but its NPV impact is only $60,000.
  • Working capital is not a full $100,000 NPV reduction because the Year 4 recovery has a present value of $68,300.
  • Operator training is relevant because it is incremental, but it has a smaller immediate impact than the depreciation error.

Depreciation is non-cash when taxes are ignored, and $180,000 × 3.170 is the largest adverse correction.


Question 6

Topic: Capital Budgeting

A CPA is reviewing a capital project for Maple Components Inc., a private Canadian manufacturer. Management wants a recommendation using the company’s net present value method. The company accepts independent projects only when NPV is at least $30,000.

Project facts:

ItemAmount or timing
Equipment purchase$650,000 at time 0
Installation cost$50,000 at time 0
Initial working capital required$80,000 at time 0
After-tax operating cash inflow, year 1$180,000
After-tax operating cash inflow, year 2$220,000
After-tax operating cash inflow, year 3$260,000
After-tax operating cash inflow, year 4$240,000
After-tax salvage value$90,000 at end of year 4
Working capital recovery$80,000 at end of year 4
Project discount rate10%

Present value factors at 10% are 0.9091 for year 1, 0.8264 for year 2, 0.7513 for year 3, and 0.6830 for year 4.

Which recommendation is best supported by the NPV analysis?

  • A. Proceed, because the undiscounted cash surplus is $290,000, which is higher than the $30,000 benchmark.
  • B. Reject, because NPV is approximately negative $13,800 after ignoring the working capital recovery at the end of year 4.
  • C. Proceed, because NPV is approximately $40,800 after including the initial working capital outflow and the terminal salvage and working capital recovery.
  • D. Proceed, because NPV is approximately $120,800 after excluding initial working capital from the investment cost.

Best answer: C

What this tests: Capital Budgeting

Explanation: NPV should include all incremental project cash flows at the time they occur and discount them at the project discount rate. The time 0 investment is $650,000 + $50,000 + $80,000 = $780,000. The discounted operating cash inflows are about $163,600, $181,800, $195,300, and $163,900. In year 4, the salvage value and working capital recovery add $170,000, with a present value of about $116,100. Total present value of inflows is therefore about $820,800, giving NPV of about $40,800. Since Maple requires NPV of at least $30,000, the project should proceed based on the supplied method and benchmark.

  • Excluding initial working capital overstates the project value because cash is tied up at time 0.
  • Ignoring the terminal working capital recovery understates the project value because that cash is released at the end of the project.
  • Using the undiscounted surplus ignores both timing and the required return, while management’s benchmark is based on NPV.

The project’s present value of inflows is about $820,800, which exceeds the $780,000 initial outflow by about $40,800 and meets the $30,000 benchmark.


Question 7

Topic: Capital Budgeting

Maple Ridge Fixtures Ltd., an Ontario manufacturer, is evaluating a robotic cutting cell. The CFO asks you to critique management’s draft analysis before the capital committee votes. The company has cash available and no bank covenant restriction. Forecast volumes are supported by signed five-year supply agreements.

ItemAmount or fact
Equipment and installation, paid today$2,400,000
Annual after-tax operating cash inflow, years 1-5$650,000
After-tax equipment proceeds, end of year 5$350,000
Additional working capital, required today$300,000
Working capital release, end of year 5$300,000
Management’s draft NPV$347,000 positive, using 8% and excluding working capital
Draft IRR and simple payback13.0%; 3.7 years

Finance policy requires a project-specific discount rate. Treasury has set 11% for this project because the new customer segment is riskier than existing operations. Positive NPV at the appropriate rate is the primary decision criterion; payback is secondary unless financing is constrained. At 11%, the five-year annuity factor is 3.696 and the year-5 present value factor is 0.593.

Which recommendation is most appropriate?

  • A. Revise the analysis to exclude the terminal working-capital recovery and decide based on the draft payback period.
  • B. Accept the project using a corrected NPV of approximately $88,000.
  • C. Defer the project until demand risk is eliminated because the project-specific discount rate exceeds the corporate WACC.
  • D. Reject the project because the draft NPV is unreliable once the higher discount rate and working-capital investment are considered.

Best answer: B

What this tests: Capital Budgeting

Explanation: Capital budgeting should use incremental cash flows discounted at the project-specific rate. The draft analysis is not reliable as presented because it used the 8% corporate WACC and omitted working capital. However, working capital is still a project cash flow: it is invested today and recovered at the end. At 11%, corrected NPV is ($650,000 × 3.696) + (($350,000 + $300,000) × 0.593) - ($2,400,000 + $300,000), or about $87,850. Because the corrected NPV is positive and there are no financing constraints or unresolved volume assumptions, the project meets the primary investment criterion. The positive NPV is modest, so the recommendation should note the reduced margin of safety.

  • Rejecting the project overreacts to the draft errors; the corrected NPV remains positive.
  • Deferring for demand risk is not supported because the required 11% discount rate already reflects the risk and the forecast volumes are contract-supported.
  • Excluding the working-capital recovery ignores a real end-of-project cash inflow and would understate value.
  • Relying on payback would conflict with the stated policy that NPV is the primary decision criterion.

Using the required 11% rate and treating working capital as an immediate outflow with end-of-project recovery gives a positive NPV.


Question 8

Topic: Capital Budgeting

Northern Pack Inc., a private Canadian food-packaging manufacturer, is reviewing a proposed automated inspection line. The board-approved annual capital plan includes a general placeholder for quality automation, but not this specific supplier or technology.

Project facts:

  • Initial cost: $4.8 million, funded with a new term loan and use of the operating line during installation.
  • Finance has independently reviewed the cash-flow forecast and sensitivity analysis. Base-case NPV is positive, but a six-month delay would make the NPV negative.
  • The equipment uses AI camera technology that Northern Pack has not previously operated.
  • Forecast debt-to-EBITDA would rise from 2.6x to 3.1x; the bank covenant maximum is 3.25x.
  • On-time installation is important to support renewal of a major customer contract.

Capital budgeting policy:

  • CFO approval is sufficient for routine replacements up to $1 million.
  • The executive investment committee reviews projects over $1 million after finance signs off the analysis.
  • Board approval is required before any binding commitment for projects over $3 million, projects using novel technology, projects with material financing implications, or decisions that could significantly affect a major customer relationship.

The CFO has signed off, and the executive investment committee has recommended proceeding. Procurement wants to sign a non-cancellable supplier agreement tomorrow. Which governance step is missing before the agreement is signed?

  • A. Ask finance to redo the NPV using a lower discount rate to reflect the customer-renewal benefit.
  • B. Obtain board approval for the specific project before signing the supplier agreement.
  • C. Proceed with signing because the project is included in the annual capital plan and has a positive base-case NPV.
  • D. Defer governance review until the post-completion review because finance has already tested the sensitivities.

Best answer: B

What this tests: Capital Budgeting

Explanation: A formal capital budgeting process should match approval authority to the project’s size, risk, and decision importance. Here, the project is not a routine replacement. It exceeds the $3 million threshold, uses unfamiliar technology, affects financing capacity, and is important to a major customer relationship. Finance review and executive investment committee recommendation are necessary steps, but they do not replace the board approval required before a binding commitment. The general capital-plan placeholder also does not authorize this specific high-risk project. The missing governance step is board approval before procurement signs the non-cancellable agreement.

  • A positive base-case NPV does not override approval limits, especially where downside sensitivity and financing risk are significant.
  • Reworking the discount rate would not address the missing authorization step and could weaken decision discipline if not supported by project risk.
  • A post-completion review is useful after implementation, but it cannot substitute for required pre-commitment approval.

The project triggers multiple board-approval criteria: size, novel technology, financing implications, and importance to a major customer relationship.


Question 9

Topic: Capital Budgeting

Northland Plastics Ltd. has one commissioning window next year and must prioritize one capital project. The board approved up to $3.5 million of capital spending and 2,000 specialized engineering hours. Projects are indivisible and use the listed resources in the same window.

The board’s strategic priority is to grow recurring revenue in regulated medical-device components. A strategic-fit score of 5 means direct support for that priority; a score of 1 means unrelated. Because the credit facility renews next year, management has also set a hard risk screen: the downside NPV estimate must not be negative. Risk-adjusted NPV already reflects project-specific discount rates and probability-weighted cash flows.

ProjectConstraint useValue and riskStrategic fit
Automation line$3.2M; 2,100 hrsRA NPV $0.75M; downside $0.05M2, cost reduction
Medical coating cell$3.0M; 1,850 hrsRA NPV $0.70M; downside $0.12M5, recurring medical
Energy retrofit$1.2M; 450 hrsRA NPV $0.38M; downside $0.22M2, utility savings
Export line$3.4M; 1,950 hrsRA NPV $1.05M; downside -$0.65M4, export growth

Which project should receive priority for the current allocation?

  • A. Prioritize the energy retrofit because it has the lowest capital requirement and the highest NPV per engineering hour.
  • B. Prioritize the export line because it has the highest risk-adjusted NPV and fits within funding and engineering limits.
  • C. Prioritize the automation line because it has a higher risk-adjusted NPV than the medical coating cell and a positive downside NPV.
  • D. Prioritize the medical coating cell because it satisfies funding, capacity, downside-risk, and strategic-fit requirements.

Best answer: D

What this tests: Capital Budgeting

Explanation: Capital rationing decisions should first screen out projects that fail hard constraints, then rank the remaining projects against the entity’s strategic objective and risk tolerance. The automation line is not feasible in the current window because it requires 2,100 engineering hours, exceeding the 2,000-hour capacity. The export line fits the funding and hour limits but violates the hard risk screen because its downside NPV is negative. The energy retrofit is feasible and low risk, but it does not meaningfully advance the board’s priority and creates less total risk-adjusted value. The medical coating cell meets all hard constraints, has positive downside NPV, and directly supports recurring medical-device revenue, so it should receive priority.

  • The export line’s high risk-adjusted NPV does not override the stated requirement that downside NPV cannot be negative.
  • The energy retrofit is financially safe, but scarce capital should not be allocated first to a low-fit project when a feasible high-fit project is available.
  • The automation line cannot be selected for the current window because the engineering-hour constraint is binding.

The medical coating cell is the feasible project that best supports the board’s stated strategic priority while passing the hard risk screen.


Question 10

Topic: Capital Budgeting

A Canadian manufacturer is considering a five-year production line for a new premium product. Management’s draft memo recommends approval because the project has a positive NPV of $333,000.

Assume all amounts are pre-tax cash flows and occur at year-end unless stated.

  • Draft analysis included:
    • Equipment cost paid immediately: $1,800,000
    • Incremental annual cash inflows from the new product: $520,000 for years 1-5
    • Discount rate: 7%, based on the company’s current mature-business WACC
  • Draft analysis excluded:
    • Inventory and setup working capital paid immediately: $220,000, fully recovered in year 5
    • Lost annual contribution from an existing product due to cannibalization: $90,000 for years 1-5
    • Required decommissioning cost in year 5: $150,000
    • Feasibility study already paid and non-refundable: $80,000
  • The new product has no committed customer contracts, and comparable premium-product ventures use risk-adjusted rates of 11%-13%.

Which interpretation best critiques management’s draft analysis?

  • A. The analysis is understated because the lost contribution from the existing product should be added back as a benefit of launching the premium product.
  • B. The only required correction is to exclude the feasibility study, since all other cash flows relate to future operations and are already reflected in the draft NPV.
  • C. The positive NPV is not supportable because the analysis omits relevant incremental cash flows and uses a discount rate that is too low for the project risk.
  • D. The draft NPV is supportable because working capital is fully recovered and the feasibility study confirms management’s commercial intent.

Best answer: C

What this tests: Capital Budgeting

Explanation: A capital project analysis should use incremental cash flows and a discount rate appropriate to the project’s risk. The immediate working capital outlay is relevant even though it is later recovered, because its timing affects value. Cannibalization is also relevant because the company gives up contribution from an existing product as a direct consequence of launching the new line. The required decommissioning cost is a future cash outflow caused by the project. In contrast, the feasibility study is a sunk cost because it has already been paid and cannot be changed by the decision. The 7% mature-business WACC is not appropriate without adjustment because the proposed product has higher demand risk and comparable ventures use 11%-13%. These issues mean management’s positive NPV likely overstates the project’s economics.

  • Fully recovered working capital is still relevant because the initial cash outflow and later recovery occur at different times.
  • Treating cannibalized contribution as a benefit reverses the economic effect; it is an opportunity cost of the project.
  • Excluding only the feasibility study ignores several relevant future cash flows and the need for a risk-adjusted discount rate.

Working capital, cannibalization, and decommissioning are relevant project cash flows, while the higher-risk project should not use the mature-business WACC without adjustment.

Continue in the web app

Use Finance Prep for interactive CPA Canada Finance practice with mixed sets, timed mock exams, topic drills, explanations, and progress tracking.

Practice next step

Use the Finance Prep web app above when you want interactive practice beyond this static page.