Project+ — CompTIA Project+ (PK0-005) Exam Quick Reference

Compact CompTIA Project+ (PK0-005) quick reference covering lifecycle, artifacts, roles, formulas, change control, risk, communications, and exam decision points.

Exam Identity and How to Use This Page

ItemReference
ProviderCompTIA
Official exam titleCompTIA Project+ (PK0-005)
Official exam codeProject+
Page purposeIndependent quick-reference support for real-exam preparation

Use this page to review high-yield project management distinctions quickly: lifecycle flow, artifacts, roles, governance, change control, risk, stakeholder communication, schedule/cost basics, and scenario decision logic.

Project Lifecycle Quick Map

    flowchart TD
	    A[Need, opportunity, problem, or mandate] --> B[Business case / charter]
	    B --> C{Authorized?}
	    C -- No --> X[Do not execute project work]
	    C -- Yes --> D[Plan scope, schedule, cost, quality, resources, communications, risks, procurement]
	    D --> E[Execute work and manage team, vendors, and stakeholders]
	    E --> F[Monitor performance, risks, issues, changes, quality]
	    F --> G{Change requested?}
	    G -- Yes --> H[Analyze impact and submit through change control]
	    H --> I{Approved?}
	    I -- Yes --> J[Update baselines, plans, logs, and communicate]
	    I -- No --> K[Communicate decision and prevent scope creep]
	    J --> E
	    K --> E
	    G -- No --> L{Deliverables accepted?}
	    L -- No --> E
	    L -- Yes --> M[Close procurements, transition, archive, lessons learned]
Phase / Process AreaMain purposeHigh-yield outputsExam traps
InitiationDecide whether the project should exist and authorize itBusiness case, project charter, high-level scope, sponsor approval, initial stakeholdersStarting execution before authorization; confusing business case with charter
PlanningDefine how the project will be executed, monitored, and controlledScope baseline, WBS, schedule, budget, risk register, communication plan, procurement plan, quality planTreating plans as static; ignoring stakeholder and risk planning
ExecutionProduce deliverables and coordinate people/resourcesWork results, team assignments, vendor work, status updates, quality activitiesDoing unapproved work; bypassing change control
Monitoring and controllingCompare actual performance against plan and manage varianceStatus reports, change log, issue log, updated risks, forecasts, corrective actionsReporting variance without action; approving changes informally
ClosingFormalize acceptance and preserve knowledgeAccepted deliverables, closure report, lessons learned, archived records, transitioned product/serviceClosing before acceptance; skipping contract closure or handoff

Predictive, Adaptive, and Hybrid Selection

SituationBest-fit approachWhy
Requirements are stable, scope is well understood, approvals are formalPredictive / waterfallPlan-driven baselines and formal change control fit stable work
Requirements are uncertain or expected to evolveAdaptive / agileIterative delivery allows feedback-driven refinement
Regulated milestones exist, but parts of the product need iterationHybridCombines formal governance with adaptive delivery
Customer wants early usable incrementsAgile or hybridPrioritizes incremental value
Vendor contract requires fixed deliverables and acceptance criteriaPredictive or hybridContract control and baseline management matter
Infrastructure migration with defined sequence and dependenciesPredictiveSchedule, cutover, risk, and dependency planning dominate
New digital product with evolving user feedbackAdaptiveBacklog, demos, and reprioritization reduce waste

Agile vs Predictive Exam Distinctions

ConceptPredictiveAgile / adaptive
ScopeDefined early; controlled through baselineEvolved through prioritized backlog
ChangeFormal change request and approvalReprioritized by product owner/backlog governance
PlanningUp-front detailed plan, then rolling updatesRolling-wave planning each iteration
DeliveryUsually larger release near the end or at milestonesFrequent increments
Progress measureSchedule/cost variance, milestones, deliverable completionWorking increments, velocity, burndown/burnup
Customer involvementKey reviews and approvalsContinuous feedback
Best exam clue“Approved baseline,” “change control board,” “phase gate”“Sprint,” “backlog,” “iteration,” “daily stand-up,” “retrospective”

Core Roles and Responsibilities

RolePrimary responsibilityDoes / ownsDoes not usually do
SponsorProvides authority, funding, and executive supportCharter approval, major decisions, escalation resolution, business alignmentManage daily tasks
Project managerIntegrates work across scope, schedule, cost, quality, risk, resources, and stakeholdersPlans, status, issue/risk management, change process, communicationsUnilaterally approve major baseline changes
Project teamPerforms project workEstimates, task execution, technical input, quality checksOwn business case approval
Customer / end userReceives or uses deliverablesRequirements input, acceptance feedback, validationManage project governance unless assigned
Product ownerMaximizes product value in agile contextsBacklog prioritization, acceptance of backlog itemsServe as team manager in the traditional sense
Scrum master / agile facilitatorSupports agile process and removes impedimentsFacilitation, coaching, impediment removalPrioritize product scope
Functional managerManages department resourcesStaff assignment, skill development, resource approvalOwn integrated project delivery
PMOStandards, governance, support, reportingTemplates, methodology, portfolio reporting, auditsAlways control every project decision
Change control boardReviews significant changesApprove/reject/defer change requests based on impactReceive informal hallway requests as approval
Vendor / supplierProvides contracted goods or servicesContracted deliverables, service performanceChange contract scope without authorization
StakeholderPerson/group affected by or influencing projectRequirements, constraints, feedback, support/resistanceAlways have decision authority

Artifact Selection Reference

ArtifactUse it to answer questions aboutCreated / refined whenKey distinction
Business caseWhy the project is worth doingInitiationJustifies investment; not the detailed execution plan
Project charterFormal project authorizationInitiationGives PM authority; high-level scope/objectives
Stakeholder registerWho matters and how they are affectedInitiation and updated throughoutIdentification and analysis source
Stakeholder engagement planHow to manage stakeholder involvementPlanningStrategy for support, resistance, and communication
Requirements documentationWhat stakeholders needPlanning, refined as neededBasis for scope and acceptance
Requirements traceability matrixLink requirements to deliverables, tests, and acceptancePlanning through validationPrevents missed or orphan requirements
Scope statementWhat is included/excludedPlanningMore detailed than charter scope
WBSDecomposes deliverables into manageable workPlanningDeliverable-oriented; not a schedule by itself
WBS dictionaryDetails about WBS componentsPlanningAdds descriptions, assumptions, owners, acceptance info
ScheduleWhen work happensPlanning and controllingIncludes activities, sequencing, duration, dependencies
Budget / cost baselineApproved cost planPlanning and controllingUsed to compare actual cost performance
Risk registerUncertain events that may affect objectivesPlanning and continuously updatedRisks may or may not happen
Issue logCurrent problems needing actionExecution/controlIssues are happening now
Change logTracks requested, approved, rejected, deferred changesControlRecords decisions and status
Communication planWho receives what, when, how, and from whomPlanningPrevents under/over-communication
Resource planPeople, equipment, materials, and availabilityPlanningAddresses capacity and skill needs
RACI matrixResponsibility clarityPlanningMaps roles to work; prevents ownership gaps
Quality management planQuality standards and methodsPlanningDefines how quality will be planned, assured, controlled
Procurement planExternal purchasing strategyPlanningCovers make/buy, vendor approach, contract type
Status reportCommunicates project healthExecution/controlSummarizes progress, variance, risks, issues
Lessons learned registerCaptures knowledge during projectThroughout, finalized at closeNot just a closing activity
Closure reportConfirms completion and outcomesClosingDocuments acceptance, performance, open items, handoff

Document Type Distinctions

If the scenario asks for…Choose…Because…
Formal authorization to beginProject charterAuthorizes project and PM authority
Justification for investmentBusiness caseExplains expected value, need, or benefit
Detailed deliverable decompositionWBSBreaks scope into work packages
Link from requirement to test or deliverableTraceability matrixTracks each requirement through validation
Who is accountable or consultedRACI matrixClarifies participation by work item
How to inform stakeholdersCommunication planDefines audience, content, channel, cadence
Current unresolved problemIssue logIssues are active problems
Potential future problem/opportunityRisk registerRisks are uncertain
Formal modification to approved baselineChange requestInitiates change control
Record of change decisionsChange logTracks submitted and decided changes
Acceptance of completed workSign-off / acceptance documentationConfirms deliverables meet criteria
Transition to operationsHandoff plan / transition planMoves product/service into support

“What Should the Project Manager Do Next?” Decision Table

Scenario clueBest next actionAvoid
Stakeholder requests new scope after baseline approvalDocument a change request and perform impact analysisTelling team to start immediately
Team member discovers a possible future problemAdd/update risk register and analyze probability/impactLogging as an issue unless it is already occurring
Risk event has happenedMove/manage as an issue; execute response or workaroundLeaving it only in the risk register
Deliverable fails inspectionRecord defect, perform root cause/corrective action, rework if neededAccepting deliverable to protect schedule
Sponsor asks for statusProvide concise report using agreed metrics and current dataHiding bad news or giving informal guesses
Stakeholder is resistantAnalyze interests and engagement needs; update engagement/communication approachIgnoring resistance until approval fails
Schedule variance exceeds toleranceAnalyze cause, consider corrective action, communicate/escalate per planChanging baseline without approval
Team conflict affects workFacilitate collaboration/problem solving first when practicalImmediately escalating minor interpersonal conflict
Vendor misses a deliverableReview contract/SOW, document issue, communicate with vendor, escalate if neededInformally accepting late work without assessing impact
Requirement is unclearClarify with customer/product owner and update documentationLetting team assume intent
Project objective no longer supports business needEscalate to sponsor/governance for decisionContinuing because work already started
Sensitive data appears in project documentsFollow security/privacy handling procedures and restrict accessSharing broadly for convenience
Final deliverable completedObtain formal acceptance, close procurements, transition, archive, lessons learnedDisbanding team before closure work
An urgent production-impacting defect occursFollow escalation/incident path and communicate impactWaiting for the next routine meeting

Change Control Quick Reference

StepPurposeKey exam point
Identify changeCapture request clearlyAll changes should be documented
Log requestTrack ownership and statusUse a change log, not memory
Analyze impactAssess scope, schedule, cost, quality, risk, resources, procurement, stakeholdersImpact analysis comes before approval
ReviewSponsor/CCB/product owner/governance evaluatesAuthority depends on methodology and thresholds
DecideApprove, reject, defer, or request more infoPM usually facilitates; does not always approve
UpdateRevise baselines, plans, contracts, backlog, and documents if approvedApproved changes must be integrated
CommunicateNotify affected stakeholdersCommunication prevents surprise and rework
Implement and verifyExecute authorized change and validate resultsUnauthorized work is scope creep

Baseline Change vs Routine Update

Work itemFormal change control usually needed?Reason
Correcting a typo in meeting notesNoAdministrative update
Updating actual task completion percentageNoPerformance reporting
Adding a new deliverableYesScope baseline impact
Extending approved milestone dateYesSchedule baseline impact
Increasing approved budgetYesCost baseline impact
Changing acceptance criteriaYesScope/quality impact
Reprioritizing agile backlog before sprint planningUsually handled through backlog governanceNot the same as uncontrolled scope creep
Changing sprint work mid-iterationDepends on agile rules and severityProduct owner/team agreement is key

Scope, Schedule, Cost, and Quality

ConstraintMain questionCommon control toolsExam warning
ScopeWhat work and deliverables are included?Scope statement, WBS, requirements traceability, acceptance criteriaGold plating and scope creep are not acceptable
ScheduleWhen will work finish?Network diagram, Gantt chart, critical path, milestones, burndownAdding people late can increase coordination overhead
CostWhat will it cost and how is spending controlled?Budget, cost baseline, EVM, forecastsActual cost alone does not show value earned
QualityDoes output meet requirements and fitness for use?Quality plan, inspections, tests, control charts, auditsQuality is planned in, not inspected in only
ResourcesWho/what is available?Resource calendar, responsibility matrix, capacity planningOverallocation creates schedule and quality risk
RiskWhat uncertainty could affect objectives?Risk register, risk responses, reservesRisk is not automatically negative; opportunities exist
StakeholdersWho can affect or be affected?Register, engagement plan, communication matrixMissing stakeholders cause late requirements and resistance

Schedule and Estimating Reference

ConceptMeaningHigh-yield point
ActivityWork unit needed to produce deliverablesDerived from WBS work packages
MilestoneSignificant point or eventZero duration
DependencyRelationship between activitiesDrives sequencing
Finish-to-startSuccessor starts after predecessor finishesMost common dependency type
Start-to-startSuccessor starts after predecessor startsAllows parallel starts
Finish-to-finishSuccessor finishes after predecessor finishesFinish alignment
Start-to-finishSuccessor finishes after predecessor startsLeast common
LeadAccelerates successorExample: start testing before all development is complete
LagWaiting time insertedExample: wait for curing/approval period
Critical pathLongest path through networkDetermines shortest project duration
Float / slackTime an activity can slip without delaying targetCritical path typically has zero float
CrashingAdd resources to shorten scheduleUsually increases cost
Fast trackingDo sequential work in parallelUsually increases risk/rework
Rolling-wave planningPlan near-term work in detail, future work at higher levelUseful when details emerge over time

Estimating Formulas

Three-point beta / PERT-style expected estimate:

\[ \text{Expected estimate} = \frac{O + 4M + P}{6} \]

Triangular estimate:

\[ \text{Triangular estimate} = \frac{O + M + P}{3} \]

Where \(O\) = optimistic, \(M\) = most likely, and \(P\) = pessimistic.

Estimating methodUse whenNotes
AnalogousSimilar past project existsFast, less precise
ParametricReliable unit rate existsExample: cost per server, hours per unit
Bottom-upWork packages are definedMore detailed; time-consuming
Three-pointUncertainty existsUses optimistic, most likely, pessimistic values
Expert judgmentSkilled SMEs are availableUseful but should be documented
Vendor bid analysisExternal supplier pricing is neededCompare assumptions, scope, and exclusions

Earned Value and Performance Formulas

Core terms:

TermMeaning
PVPlanned value: budgeted value of scheduled work
EVEarned value: budgeted value of completed work
ACActual cost: actual cost incurred
BACBudget at completion: total approved budget
FormulaPlain-text formulaInterpretation
Cost varianceCV = EV - ACPositive is under budget; negative is over budget
Schedule varianceSV = EV - PVPositive is ahead of schedule; negative is behind
Cost performance indexCPI = EV / ACGreater than 1 is favorable; less than 1 is unfavorable
Schedule performance indexSPI = EV / PVGreater than 1 is favorable; less than 1 is unfavorable
Estimate at completion, simpleEAC = BAC / CPIUse when current cost performance is expected to continue
Estimate to completeETC = EAC - ACExpected remaining cost
Variance at completionVAC = BAC - EACPositive is favorable; negative is unfavorable

High-yield interpretation:

If…It means…
EV is less than PVLess work completed than planned
EV is less than ACWork completed costs more than its planned value
CPI = 0.80Getting 0.80 of planned value for each 1.00 spent
SPI = 1.10Progressing faster than planned by earned-value measure
CV negative and SV negativeOver budget and behind schedule
CPI favorable but SPI unfavorableSpending efficiently but progressing too slowly

Communication Formulas and Methods

Number of communication channels with \(n\) participants:

\[ \text{Channels} = \frac{n(n-1)}{2} \]
MethodBest useWeakness / trap
Interactive communicationComplex, urgent, or ambiguous topicsMeetings can be inefficient if poorly controlled
Push communicationSend information to specific recipientsDoes not guarantee understanding
Pull communicationLarge audience accesses information when neededRequires stakeholders to retrieve it
Formal writtenContracts, approvals, status reports, decisionsSlower but auditable
Informal verbalQuick clarification, relationship buildingPoor for official decisions unless documented
SynchronousReal-time discussionScheduling/time-zone challenges
AsynchronousEmail, dashboards, recorded updatesSlower feedback loop
Communication needBetter choice
Resolve complex conflictInteractive meeting / facilitated discussion
Announce approved changeFormal written notice plus stakeholder briefing if needed
Share routine metricsDashboard or status report
Confirm acceptanceFormal sign-off
Communicate bad newsTimely, factual, with impact and options
Reach distributed stakeholdersMix of asynchronous updates and scheduled interactive sessions

Stakeholder Management

ActivityPurposeExam focus
Identify stakeholdersFind affected/influential people and groupsDo this early and revisit
Analyze stakeholdersUnderstand power, interest, influence, expectationsTailor engagement
Plan engagementDefine strategies to gain support and reduce resistanceNot all stakeholders need same communication
Manage engagementCommunicate, involve, negotiate, resolve concernsActive management, not passive reporting
Monitor engagementCheck whether strategy worksUpdate plan as attitudes change
Stakeholder stateMeaningPossible PM action
UnawareDoes not know project/impactInform and educate
ResistantOpposes project or changeUnderstand concerns, address impact, involve appropriately
NeutralNeither supports nor opposesProvide relevant information
SupportiveWants project successMaintain engagement
LeadingActively advocatesUse as champion where appropriate

Risk, Issue, Action, and Decision Logs

ItemDefinitionExampleCorrect record
RiskUncertain future event/condition“Key engineer may become unavailable”Risk register
IssueCurrent problem“Key engineer resigned”Issue log
Action itemAssigned task to resolve/follow up“PM to identify replacement by Friday”Action item log
DecisionChoice made by authority“Sponsor approved two-week extension”Decision log / meeting minutes
AssumptionSomething treated as true for planning“Vendor API will be available by July”Assumption log
ConstraintLimitation on options“Must complete before data center shutdown”Constraint list / charter / plan
DependencyRelationship that affects sequencing“Testing depends on environment readiness”Schedule / dependency log

Risk Response Strategies

Risk typeStrategyMeaning
ThreatAvoidChange plan to eliminate threat
ThreatMitigateReduce probability or impact
ThreatTransferShift impact ownership, often by contract/insurance/vendor
ThreatAcceptTake no proactive action beyond monitoring/reserve
OpportunityExploitEnsure opportunity occurs
OpportunityEnhanceIncrease probability or impact
OpportunitySharePartner to capture benefit
OpportunityAcceptTake advantage if it occurs

Risk score is commonly expressed as probability times impact:

\[ \text{Risk score} = \text{Probability} \times \text{Impact} \]
Scenario clueBest response
High probability and high impact threatPlan active response; escalate if outside tolerance
Low impact riskMonitor or accept if appropriate
Risk trigger occursExecute planned response
No response exists and issue occursDevelop workaround; update issue/risk records
Risk response changes scope/schedule/cost baselineSubmit change request

Quality Management Quick Reference

ConceptMeaningExam clue
Quality planningDefine standards and how quality will be achieved“What quality criteria apply?”
Quality assuranceEvaluate process effectiveness“Are we following the right process?”
Quality controlInspect/test deliverables“Does this deliverable meet requirements?”
Acceptance criteriaConditions deliverable must satisfyUsed for customer validation
Definition of doneAgile team’s completion criteriaApplies consistently to backlog items
Cost of qualityCost to prevent, detect, and fix defectsPrevention is generally better than rework
Prevention costTraining, standards, process improvementAvoid defects
Appraisal costInspection, testing, auditsDetect defects
Internal failure costRework before customer deliveryDefect found internally
External failure costWarranty, returns, reputation damageDefect found by customer
ToolUse
Cause-and-effect / fishbone diagramIdentify possible root causes
Pareto chartFocus on vital few causes
Control chartDetermine process stability over time
Run chartShow trends over time
HistogramShow frequency distribution
Scatter diagramShow relationship between variables
Check sheetCollect defect/event counts
FlowchartMap process steps and handoffs
AuditCheck process compliance
InspectionExamine deliverable for defects

Procurement and Vendor Reference

Document / termUseExam distinction
Make-or-buy analysisDecide internal vs external sourcingConsiders cost, capability, risk, schedule
RFIRequest informationLearn vendor capabilities; not usually final pricing
RFQRequest quotePrice for well-defined goods/services
RFPRequest proposalVendor proposes solution/approach
SOWStatement of workDefines work, deliverables, acceptance criteria
SLAService-level agreementDefines service performance targets
MSAMaster service agreementGeneral contractual terms across work
NDANondisclosure agreementProtects confidential information
POPurchase orderAuthorizes purchase under defined terms
ContractBinding agreementChanges require formal control
Vendor scorecardPerformance trackingCompares delivery, quality, cost, responsiveness
Contract typeBuyer riskSeller riskBest for
Fixed priceLower if scope is clearHigher if estimates are wrongWell-defined deliverables
Time and materialsMedium to higher without controlsLowerUncertain duration or flexible scope
Cost-reimbursableHigherLower to mediumUncertain work where buyer accepts cost risk
Incentive-basedSharedSharedAligning vendor behavior to targets

Vendor scenario pattern:

  1. Check the contract/SOW/SLA.
  2. Document performance issue.
  3. Communicate with vendor through agreed channel.
  4. Assess project impact.
  5. Escalate or initiate change/claim process if needed.
  6. Update project records and stakeholders.

Resource and Team Management

TopicReference point
Resource calendarShows availability, holidays, assignments, constraints
Responsibility assignment matrixMaps work to roles/people
RACIResponsible, Accountable, Consulted, Informed
Training needAddress skill gaps before they affect quality/schedule
Team charterDefines team norms, decision rules, and working agreements
Virtual teamRequires explicit communication norms and tool discipline
Matrix environmentPM may share authority with functional managers
Resource levelingAdjust schedule to address resource constraints; may change critical path
Resource smoothingAdjust within available float; does not usually change end date

RACI Meanings

LetterMeaningRule of thumb
RResponsibleDoes the work
AAccountableOwns final answer/approval; ideally one per activity
CConsultedTwo-way input before decision/action
IInformedOne-way update after decision/action

Conflict and Leadership Responses

Conflict methodUse whenRisk
Collaborate / problem solveImportant issue, time allows, win-win desiredTakes time
CompromiseNeed acceptable middle ground quicklyEveryone gives up something
Smooth / accommodatePreserve relationship, issue is minorRoot cause may remain
Force / directEmergency, safety, compliance, or authority-based decisionCan damage morale
Withdraw / avoidCooling-off period or issue is trivialDelays resolution

Exam pattern: choose collaboration/problem solving for important project conflicts unless the scenario clearly requires urgent direction, escalation, or compliance action.

Meetings and Status Controls

Meeting / eventPurposeGood output
Kickoff meetingAlign team and stakeholders before executionShared understanding of objectives, roles, plan
Status meetingReview progress, blockers, risks, decisionsUpdated actions, issues, risks
Change control meetingReview change requests and impactsApproved/rejected/deferred decisions
Risk reviewReassess risks, triggers, responsesUpdated risk register
Sprint planningSelect and plan iteration workSprint goal/backlog
Daily stand-upSynchronize agile teamBlockers identified
Sprint reviewDemonstrate increment to stakeholdersFeedback and accepted/rejected items
RetrospectiveImprove team processImprovement actions
Lessons learned sessionCapture reusable knowledgeLessons learned register update
Closure meetingConfirm completion and transitionAcceptance, handoff, archived records

Governance and Escalation

Escalate when…Escalate to…Why
Decision exceeds PM authoritySponsor/governance bodyAuthority and accountability
Baseline impact exceeds toleranceCCB/sponsorFormal change approval needed
Funding or strategic alignment is questionedSponsorBusiness decision
Functional resource conflict cannot be resolvedFunctional manager/sponsorShared authority issue
Vendor breach or major nonperformance occursProcurement/vendor manager/sponsorContractual handling
Compliance/security concern arisesAppropriate governance/security/compliance contactSpecialized authority
Stakeholder conflict blocks acceptanceSponsor or steering groupBusiness-level resolution
Project should be paused or terminatedSponsor/governance bodyPM should not make unilateral strategic termination decision
Do firstBefore escalating
Verify factsAvoid escalating rumors
Document impactScope, schedule, cost, risk, quality, stakeholders
Identify optionsGive decision-makers choices
Follow communication planUse agreed path unless emergency requires faster action
Keep recordsDecisions should be auditable

IT and Operational Transition Focus

CompTIA Project+ candidates often see project scenarios tied to technology delivery, service transition, implementation, or vendor-supported work.

Transition itemPurpose
Cutover planDefines move from old to new system/process
Rollback planDefines how to return to prior state if implementation fails
RunbookOperational procedures for support teams
Support handoffTransfers ownership to operations/service desk
Training planPrepares users/admins/support staff
Release notesCommunicate changes, fixes, known issues
Maintenance windowPlanned time for implementation with reduced impact
Backout criteriaConditions that trigger rollback
Post-implementation reviewConfirms outcomes and captures lessons
Scenario clueBetter response
Deployment affects usersCommunicate schedule, impact, support path
High-risk implementationConfirm rollback/backout plan
Support team not readyDelay handoff or complete training/runbook
Stakeholders dispute readinessReview acceptance criteria and go/no-go checklist
Incident after deploymentFollow incident/escalation process and communicate

Common Exam Traps

TrapCorrect thinking
“The customer asked, so the team should do it”Customer requests still need prioritization or change control
“A risk happened, so update only the risk register”Once it happens, manage it as an issue
“The PM should approve all changes”Approval authority depends on governance and thresholds
“Status reporting solves variance”Reporting informs; corrective action controls
“Quality control and quality assurance are the same”QC checks deliverables; QA checks processes
“A milestone is a task with duration”Milestone has zero duration
“WBS is a task schedule”WBS decomposes deliverables; schedule sequences activities
“More communication is always better”Right information, right stakeholder, right timing, right channel
“Agile means no planning”Agile uses continuous planning and disciplined feedback loops
“Closing is just celebration”Closing includes acceptance, handoff, records, lessons learned, procurement closure
“Negative risk is the only risk”Risks can be threats or opportunities
“Actual cost tells whether the project is healthy”Compare actual cost with earned value and plan

Last-Minute Review Checklist

AreaConfirm you can answer…
LifecycleWhat artifact or action belongs in initiation, planning, execution, control, or closing?
ChangeWhat happens before approval? Who decides? What gets updated after approval?
Risk vs issueIs the event uncertain or already happening?
ArtifactsWhich document fits the scenario clue?
RolesSponsor vs PM vs team vs product owner vs PMO vs CCB
ScheduleCritical path, float, dependencies, lead/lag, crashing vs fast tracking
CostEV, PV, AC, CV, SV, CPI, SPI interpretation
CommunicationPush vs pull vs interactive; formal vs informal
StakeholdersIdentify, analyze, plan, manage, monitor engagement
QualityQA vs QC; acceptance criteria; root cause tools
ProcurementRFI/RFQ/RFP/SOW/SLA; contract type risk
AgileBacklog, sprint, increment, review, retrospective, velocity/burndown
ClosingAcceptance, transition, procurement closure, archive, lessons learned

Practical Next Step

Use this Quick Reference as a checklist, then work through scenario-based CompTIA Project+ (PK0-005) practice questions. For every missed question, identify whether the miss was caused by artifact selection, lifecycle timing, role authority, formula interpretation, or change/risk decision logic.

Browse Certification Practice Tests by Exam Family