Try 10 focused AACE Earned Value Professional (EVP) questions on budgeting duties, with answers and explanations, then continue with PM Mastery.
Use this focused AACE EVP page to drill Perform Budgeting Duties decisions before returning to mixed practice, timed mocks, and the full PM Mastery question bank.
| Field | Detail |
|---|---|
| Exam | AACE EVP |
| Topic area | Perform Budgeting Duties |
| Blueprint weight | 15% |
| Page purpose | Focused sample questions before returning to mixed practice |
Use this page to isolate Perform Budgeting Duties for AACE EVP. Work through the 10 questions first, then review the explanations and return to mixed practice in PM Mastery.
| Pass | What to do | What to record |
|---|---|---|
| First attempt | Answer without checking the explanation first. | The fact, rule, calculation, or judgment point that controlled your answer. |
| Review | Read the explanation even when you were correct. | Why the best answer is stronger than the closest distractor. |
| Repair | Repeat only missed or uncertain items after a short break. | The pattern behind misses, not the answer letter. |
| Transfer | Return to mixed practice once the topic feels stable. | Whether the same skill holds up when the topic is no longer obvious. |
Blueprint context: 15% of the practice outline. A focused topic score can overstate readiness if you recognize the pattern too quickly, so use it as repair work before timed mixed sets.
These questions are original PM Mastery practice items aligned to this topic area. They are designed for self-assessment and are not official exam questions.
Topic: Perform Budgeting Duties
At the 30 June status date, a control account manager is preparing the earned value report for a material work package. The approved performance measurement baseline budgets 100 units at $4,000 per accepted unit. The work package uses a units-complete earned value technique based on site acceptance. By cutoff, 40 units have been accepted. The accounting procedure for actual cost in earned value reports uses posted invoice cost plus approved accruals for accepted work at the cutoff date.
Current records show:
What is the best professional action for the 30 June earned value report?
Best answer: A
What this tests: Perform Budgeting Duties
Explanation: Earned value for this work package is based on the approved budget for the work objectively accomplished, not on the supplier’s invoices, commitments, or cash payments. Since 40 accepted units have a budgeted value of $4,000 each, earned value is $160,000. Actual cost is determined by the stated accounting procedure: posted invoice cost plus approved accruals for accepted work at the cutoff date, or $150,000 + $25,000 = $175,000. The purchase order commitment is useful for funding, procurement exposure, and forecast analysis, but it is not earned progress or actual cost under the stated rule. Cash paid is also not the correct actual cost basis when accrual accounting is required for the EVMS report.
Earned value is the budgeted value of accepted work, while actual cost follows the accounting cutoff basis of posted invoices plus accruals.
Topic: Perform Budgeting Duties
At the June status date, a control account manager wants to revise an approved control account plan. The proposal would move $150,000 of budget from a test work package to a design work package, slip two baseline milestones by one month, and change the earned value technique from 0/100 to percent complete. The project change procedure states that changes to control account budget, baseline schedule dates, or measurement technique require a baseline change request approved by the project change control board; changes affecting the contractual reporting baseline also require customer authorization. No change order has been approved. What is the best professional action?
Best answer: A
What this tests: Perform Budgeting Duties
Explanation: An earned value baseline is controlled by authorization, not by convenience or the desire to reduce a variance. Moving budget between work packages, changing baseline milestone dates, or changing the earned value measurement technique affects the performance measurement baseline and the basis for reported performance. Because the project procedure requires change control board approval, the appropriate path is to keep the approved baseline intact, report current performance against it, and submit a baseline change request with the supporting impact analysis. If the change affects the contractual reporting baseline, customer authorization is also required before implementation. Forecasts such as ETC or EAC may be updated to reflect current expectations, but forecast updates do not revise the authorized baseline.
Baseline budget, schedule dates, and earned value technique should not be changed until the required change-control approvals are obtained.
Topic: Perform Budgeting Duties
A control account manager is preparing the March 31 earned value report. The approved performance measurement baseline for the control account has these time-phased budget increments:
| Month | Approved budget |
|---|---|
| January | $100,000 |
| February | $150,000 |
| March | $200,000 |
| April | $150,000 |
Constraints:
What is the best planned value judgment for the March 31 report?
Best answer: C
What this tests: Perform Budgeting Duties
Explanation: Planned value is taken from the approved, time-phased performance measurement baseline as of the status date. For a March 31 report, the relevant baseline budget is the cumulative budget planned for January, February, and March: $100,000 + $150,000 + $200,000 = $450,000. Pending changes are not added to planned value until they are approved and incorporated into the baseline. Early execution of April work may affect earned value if objective accomplishment criteria are met, and it may affect actual cost, but it does not move April planned value into March unless the baseline is formally rephased under change control.
Planned value is the authorized time-phased budget scheduled to be performed by the status date, so January through March totals $450,000.
Topic: Perform Budgeting Duties
At the 30 June status date, a project uses the rule \(\text{contract budget base (CBB)} = \text{performance measurement baseline (PMB)} + \text{management reserve (MR)}\). Contingency inside a control account may be applied only to the identified risk documented for that control account. MR is outside the PMB and may be allocated only by documented management action; it is not used to erase current-period cost variance.
Current budget position before reserve actions:
| Item | Amount |
|---|---|
| PMB, including control-account contingency | $8,700,000 |
| MR | $600,000 |
| CBB | $9,300,000 |
Status evidence:
Which reserve decision is supported at the 30 June status date?
Best answer: B
What this tests: Perform Budgeting Duties
Explanation: Reserve decisions must be traceable to the type of budget and the authorization basis. The $75,000 is supported because it is contingency already tied to an identified risk in CA-220, so it can be applied within that control account. The $200,000 customer-approved scope change is authorized budget and should increase the CBB and PMB, typically through undistributed budget until detailed planning assigns it. MR remains $600,000 because no documented management action authorizes an MR draw, and the $60,000 productivity overrun is a performance variance, not a reserve justification by itself. After the supported action, the PMB becomes $8,900,000 and CBB becomes $9,500,000, while MR remains unchanged.
The identified risk and approved scope change support the contingency use and PMB increase, while the productivity variance has no approved reserve action.
Topic: Perform Budgeting Duties
A project controls lead is reviewing the proposed performance measurement baseline for an authorized control account before baseline approval. The project manager wants monthly variance analysis and a credible estimate at completion.
| Baseline fact | Control account detail |
|---|---|
| Authorized scope | Design, procure, install, and test 20 identical valves |
| Budget | Design $120,000; procurement $300,000; install/test $180,000 |
| Planned timing | Design Jan-Feb; procurement Mar-Apr; install/test Apr-Jun |
| Objective evidence | Accepted drawings, received valves, installed and tested units |
| Scope definition | All listed work is defined and authorized |
Which baseline structure should be approved?
Best answer: A
What this tests: Perform Budgeting Duties
Explanation: A sound performance measurement baseline decomposes authorized work into measurable work packages, time-phases the budget according to the planned work sequence, and defines how earned value will be credited from objective accomplishment. In this case, the work is defined and has clear evidence points: accepted drawings, received valves, and installed/tested units. Separating design, procurement, and installation/testing supports meaningful planned value, earned value, actual cost comparison, variance analysis, and forecast-at-completion reasoning. Combining discrete work into level of effort or earning value from purchase orders would weaken performance visibility. Delaying defined authorized scope outside the baseline until actual costs are known would also undermine baseline integrity.
This structure aligns authorized scope, budget phasing, and objective accomplishment evidence so EV, variances, and EAC can be analyzed by work package.
Topic: Perform Budgeting Duties
An EV analyst reviews the budget basis before issuing the monthly EAC and VAC summary. The control account progress and actual costs have already been validated.
| Budget element in report | Amount | Classification note |
|---|---|---|
| Direct labor | $420,000 | Authorized control account budget |
| Direct material | $260,000 | Authorized control account budget |
| Subcontract | $180,000 | Authorized control account budget |
| Control account contingency | $40,000 | Authorized for identified scope risk |
| Management reserve | $70,000 | Held above control accounts; no change released |
Report settings: EV = $450,000, AC = $510,000, CPI = EV / AC, and EAC = BAC / CPI. The report uses BAC = $970,000.
Which classification error should be corrected before management interprets the forecast?
Best answer: B
What this tests: Perform Budgeting Duties
Explanation: In earned value budgeting, the performance measurement baseline and BAC should represent authorized work scope budget. A contingency amount that has been authorized within a control account for identified scope risk can be part of that baseline. Management reserve is different: it is held outside control accounts for future authorized changes or unknowns and should not be included in BAC, EV, CPI-based EAC, or VAC calculations until it is formally released through change control. Here, the authorized control account budget totals $900,000, but the report uses $970,000 by adding $70,000 of management reserve. That classification can make the forecast and variance appear less severe or otherwise misleading because reserve is being mixed with performance budget.
Management reserve is outside the performance measurement baseline until formally released, so including it in BAC can distort forecast and variance interpretation.
Topic: Perform Budgeting Duties
At the September status review, a project controls manager proposes changing next month’s baseline report based on the following snapshot. The program procedure states that an over-target baseline or over-target schedule may be implemented only after formal customer approval, and prior-period performance history must be retained unless that approval specifically authorizes a reset.
| Item | Current status |
|---|---|
| Contract budget base | $100.0M |
| Performance measurement baseline | $94.0M |
| Management reserve | $6.0M |
| Undistributed budget | $0.0M |
| Cumulative PV / EV / AC | $70.0M / $58.0M / $74.0M |
| Latest EAC | $118.0M |
| Approved baseline finish | 31 Dec 2026 |
| Current forecast finish | 30 Apr 2027 |
| Customer status | OTB/OTS impact assessment requested; no approval issued |
Which interpretation should be used for the management report?
Best answer: D
What this tests: Perform Budgeting Duties
Explanation: An over-target baseline or over-target schedule is a controlled baseline action, not an automatic result of an unfavorable forecast. The data support a serious condition: EAC of $118.0M exceeds the $100.0M contract budget base, and the forecast finish is four months beyond the approved baseline finish. However, the exhibit also states that the customer has only requested an impact assessment and has not approved the OTB/OTS. Until approval is issued, management reporting should continue to use the approved performance measurement baseline and disclose the forecast condition, variance position, schedule slip, and approval status. Undistributed budget, management reserve, and variance resets cannot be used simply to absorb poor performance or make reports look current.
The exhibit shows a forecast overrun and finish slip, but the OTB/OTS has not been approved for baseline implementation.
Topic: Perform Budgeting Duties
At the June 30 status date, a control account has a baseline budget at completion of $900,000. Its reported earned-value data are:
| Measure | Amount |
|---|---|
| Planned value | $540,000 |
| Earned value | $450,000 |
| Actual cost | $585,000 |
The formula is \(CV = EV - AC\). The control account also contains $40,000 of contingency for a supplier retest risk that has not occurred. The project has $120,000 of management reserve outside the performance measurement baseline. A customer-requested interface change estimated at $70,000 is still pending authorization. The control account manager proposes moving $135,000 from reserve into the control account this month so the cost variance reports as zero and using part of the transfer to start the interface work.
Which assessment is most appropriate?
Best answer: D
What this tests: Perform Budgeting Duties
Explanation: Reserve control protects the integrity of the performance measurement baseline. The control account has earned $450,000 of value and incurred $585,000 of actual cost, so the cost variance is -$135,000. Moving exactly $135,000 from contingency or management reserve to make the variance disappear would not reflect improved performance; it would hide an unfavorable cost condition. The contingency is tied to a supplier retest risk that has not occurred, so releasing it for unrelated overrun coverage is not supportable. Management reserve is outside the performance measurement baseline and is not a tool for retroactively improving reported cost performance. The pending interface change is also not authorized, so reserve should not be used to begin that scope. The proper control response is to report the variance, analyze cause and corrective action, and process any scope change through authorization before budget is added.
The current cost variance is $450,000 - $585,000 = -$135,000, and reserve should not be used to erase that variance or start unapproved scope.
Topic: Perform Budgeting Duties
A control account manager is preparing the cost-element budget for an EVMS baseline as of the baseline freeze date. The company’s budgeting rule says direct costs are costs specifically traceable to the control account; indirect costs and overhead are budgeted separately through approved rates; management reserve is outside the performance measurement baseline.
Planned amounts for the control account are:
Which classification and amount best supports the earned value budget structure?
Best answer: A
What this tests: Perform Budgeting Duties
Explanation: For earned value budgeting, cost elements should be classified based on traceability and control. Direct labor, material issued to the scope, a subcontract for the scope, and dedicated equipment are direct costs because they can be specifically assigned to the control account. Site security is charged through an indirect pool, so it is not a direct control account cost. Corporate overhead is an overhead application, not a labor, material, subcontract, or equipment cost element. Contingency and management reserve are reserve-related budget categories; management reserve is explicitly outside the performance measurement baseline under the stated rule. The professional point is to preserve the integrity of the EVMS budget structure rather than inflate direct costs with indirect charges or reserves.
The direct cost amount is the sum of labor, material, subcontract, and dedicated equipment: $420,000 + $260,000 + $180,000 + $40,000 = $900,000.
Topic: Perform Budgeting Duties
A control account in the approved performance measurement baseline has the following time-phased budget. The status date for the monthly earned value report is April 30. Use planned value (PV) as the cumulative baseline budget for work scheduled to be performed through the status date.
| Month | Baseline budget |
|---|---|
| January | USD 20,000 |
| February | USD 30,000 |
| March | USD 25,000 |
| April | USD 40,000 |
| May | USD 35,000 |
At April 30, earned value is USD 100,000 and actual cost is USD 125,000. Which reporting statement correctly interprets planned value for the control account?
Best answer: D
What this tests: Perform Budgeting Duties
Explanation: Planned value is taken from the approved, time-phased performance measurement baseline. For a status date of April 30, the correct cumulative PV includes January through April only: USD 20,000 + USD 30,000 + USD 25,000 + USD 40,000 = USD 115,000. PV does not change because the team earned a different amount of work or incurred a different actual cost. Earned value reflects accomplished work measured against its budget, while actual cost reflects recorded cost. The May budget remains part of the control account BAC, but it is not planned value at the April status date because it is scheduled after the reporting cutoff.
The cumulative baseline budget through April is USD 20,000 + USD 30,000 + USD 25,000 + USD 40,000 = USD 115,000.
Use the AACE EVP Practice Test page for the full PM Mastery practice path, mixed-topic practice, timed mock exams, explanations, and web/mobile app access.
Read the AACE EVP guide on PMExams.com, then return to PM Mastery for timed practice.