Try 120 free AACE Earned Value Professional (EVP) practice questions across the exam domains, with answers and explanations, then continue in PM Mastery.
This free full-length AACE Earned Value Professional (EVP) practice exam includes 120 original PM Mastery questions across the exam domains.
The questions are original PM Mastery practice questions aligned to the exam outline. They are not official exam questions and are not copied from any exam sponsor.
Count note: this page uses the full-length practice count maintained in the Mastery exam catalog. Some exam sponsors publish total questions, scored questions, duration, or unscored/pretest-item rules differently; always confirm exam-day rules with the sponsor.
Format note: this practice set uses selected-response items for communication and memo judgment. It does not ask you to submit or score a written memo.
Need concept review first? Read the AACE Earned Value Professional (EVP) cheat sheet for EVMS baseline integrity, earned value, actual cost, variance analysis, forecasting, data maintenance, and reporting cues before starting the diagnostic.
| Item | Detail |
|---|---|
| Issuer | AACE International |
| Exam | AACE EVP |
| Official exam name | AACE Earned Value Professional (EVP) |
| Full-length set on this page | 120 questions |
| Exam time | 300 minutes |
| Topic areas represented | 7 |
| Topic | Approximate official weight | Questions used |
|---|---|---|
| Organizing | 15% | 15 |
| Communication Competency | 1% | 1 |
| Perform Planning and Scheduling Duties | 16% | 16 |
| Perform Budgeting Duties | 15% | 15 |
| Account Considerations | 13% | 13 |
| Analysis and Management Reports | 41% | 41 |
| Revisions and Data Maintenance | 19% | 19 |
Topic: Perform Planning and Scheduling Duties
A control account manager is time-phasing the installation work package for the performance measurement baseline. The CPM logic excerpt below is the approved baseline logic for the work sequence.
| Activity | Description | Predecessor logic | EV credit rule |
|---|---|---|---|
| M120 | Complete factory acceptance test | M110 FS | 100% at accepted test record |
| M130 | Ship skid to site | M120 FS + 2 workdays | 100% at site receipt |
| M210 | Install skid | M130 FS | 100% at signed installation checklist |
| M220 | Perform tie-in test | M210 FS | 100% at accepted test record |
Which interpretation is best supported by the exhibit?
Best answer: B
What this tests: Perform Planning and Scheduling Duties
Explanation: CPM logic defines the authorized sequence used to time-phase planned value and support objective earned-value measurement. In the excerpt, activity M210, Install skid, has a direct predecessor of M130 with a finish-to-start relationship. That means installation is not logically planned to start until shipping and site receipt are complete. Because the installation work package earns value at the signed installation checklist, its planned value should not be placed before the controlling predecessor allows the work to occur. Factory acceptance is an upstream predecessor to shipping, not the direct controlling relationship for installation. Crew availability alone does not override approved CPM logic, and a successor activity such as tie-in testing does not control the planned start of installation.
M210 has an approved finish-to-start predecessor from M130, so installation PV and EV timing should follow completion of site receipt.
Topic: Organizing
A control account manager is preparing to release work packages for next month. The approved work authorization document includes fabrication of 40 valve skids under WBS 3.2.1, with budget and schedule baseline loaded for those 40 units. The customer has verbally asked the team to “start preparing” for 10 additional skids that are expected to be added by contract modification next quarter. Engineering has also assumed a different test fixture to improve productivity, but the fixture change has not been approved through configuration control. What is the best professional action before allowing earned value to be claimed?
Best answer: B
What this tests: Organizing
Explanation: Earned value must be claimed against authorized work that is traceable to the approved scope, budget, schedule, and work authorization. In this case, the 40 valve skids are in the approved work authorization and baseline, so they can be released and measured. The 10 additional skids are only a pending change, even though the customer verbally requested preparation. The alternative test fixture is also not authorized because it has not cleared configuration control. Both items may be tracked as change activity, planning assumptions, or risks, but they should not be included in baseline performance measurement or used to claim earned value until properly approved.
Only the 40 skids are authorized baseline scope, while the extra units and fixture change lack formal approval for earned-value performance measurement.
Topic: Revisions and Data Maintenance
During an internal EVMS surveillance review, the project controls lead compares the March customer report with the current data-maintenance log for control account CA-220. Values are cumulative, in USD 000s.
| Record | PV | EV | AC | Note |
|---|---|---|---|---|
| March customer report issued April 5 | 1,200 | 900 | 1,050 | CV = -150; SV = -300 |
| Data-maintenance entry dated May 10 | 1,080 | 1,080 | 1,050 | “Restated March to match recovery plan” |
| Current report showing March history | 1,080 | 1,080 | 1,050 | CV = +30; SV = 0 |
Additional review notes: no approved baseline change applies to March or April, no accounting correction was recorded, and no source progress documentation supports a different March accomplishment value.
Which data-maintenance weakness would most undermine EVMS credibility during review, audit, or customer reporting?
Best answer: C
What this tests: Revisions and Data Maintenance
Explanation: EVMS data maintenance must preserve traceability between reported performance, approved baseline changes, accounting corrections, and objective progress evidence. Prior-period corrections can be legitimate when they fix documented errors, but they need approval, a clear audit trail, and disclosure when they affect previously reported results. In this case, March PV and EV were restated to match a recovery plan, not to reflect an approved baseline change or supported progress correction. The restatement also changes the historical variance from unfavorable to favorable or neutral, which can mislead reviewers and customers about what was known at the March status date. That weakens confidence in baseline integrity, earned value credibility, and management reporting transparency.
The exhibit shows an unsupported retroactive restatement of baseline and earned value data that changes previously reported performance history.
Topic: Revisions and Data Maintenance
At the July 31 status date, a control account manager requests a data-maintenance adjustment. Authorized scope is unchanged, and no change request has been approved. Acceptance testing failed, rework has already occurred, and the revised estimate to complete the remaining authorized work is $1,550,000. Current control account data are: BAC $2,400,000, PV $1,200,000, EV $1,000,000, AC $1,150,000, and management reserve balance $350,000. The manager proposes moving $300,000 from management reserve into the control account BAC in the current period so the forecast no longer shows an overrun. Using EAC = AC + ETC and VAC = BAC - EAC, how should the adjustment be reflected?
Best answer: C
What this tests: Revisions and Data Maintenance
Explanation: Baseline changes should be tied to approved scope, budget, or authorized replanning—not used to eliminate unfavorable performance. Here, the scope is unchanged and no change request has been approved. The failed acceptance test and rework are current performance facts that should be explained in variance analysis and reflected in the forecast. The forecast is EAC = AC + ETC = $1,150,000 + $1,550,000 = $2,700,000. The VAC is BAC - EAC = $2,400,000 - $2,700,000 = -$300,000. Management reserve should not be transferred simply to make the VAC zero. EV also should not be increased for rework unless objective earned-value accomplishment criteria were met.
The rework is a performance issue on unchanged authorized scope, so it should update the forecast and variance explanation rather than revise the baseline or consume management reserve.
Topic: Analysis and Management Reports
A prime contractor must include a major fabrication subcontract in the month-end earned value report for control account 3.2. Review the subcontract status package.
| Item | Subcontractor submission at 30 Jun |
|---|---|
| Scope | Contract value is $4,000,000, including $300,000 of approved modifications; a $250,000 change request is pending. |
| Schedule | Baseline shipment milestone is 1 Aug; forecast shipment is 15 Aug; no statused activity detail was provided. |
| Budget/EV | Narrative says fabrication is “about 70% complete”; no time-phased budget or EV method by work package was provided. |
| Cost | Cumulative invoices are $1,800,000 and cumulative cash payments are $1,500,000; no accrual or actual-cost split by authorized work was provided. |
Which action is best supported before integrating the subcontract into the project EV report?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: Subcontract performance can be integrated into a project EV report only when the data is traceable to the authorized scope and reporting structure. The package gives contract value, invoices, payments, and a subjective progress statement, but it does not provide enough information to calculate or validate PV, EV, AC, schedule variance, cost variance, or forecast impact. Invoices and cash payments are not automatically actual cost, and narrative percent complete is not a substitute for objective accomplishment criteria. The pending change must remain separate from the performance measurement baseline until approved. The appropriate professional action is to request data aligned to the WBS or control account, including authorized scope, statused schedule, time-phased budget, EV method and earned progress, actual-cost/accrual basis, and EAC.
The exhibit lacks the scope, schedule, budget, actual-cost, and earned-value traceability needed to integrate subcontract performance reliably.
Topic: Perform Planning and Scheduling Duties
A control account manager is presenting the proposed schedule baseline for a qualification work package. The project controls procedure says risk mitigation may be in the performance measurement baseline only when it is an approved risk response with WBS/control account budget, objective accomplishment criteria, and schedule logic; schedule reserve must be separately identified and approved.
| Exhibit item | Baseline excerpt |
|---|---|
| Risk R-17 | Test-chamber unavailability could delay qualification. |
| Approved response | Reserve alternate chamber and perform pre-test checkout. |
| Budget coding | Both response activities charged to CA 1.3.2, USD 28,000. |
| Schedule logic | Pre-test checkout precedes qualification test; alternate chamber reservation precedes test start. |
| Added lag | Eight workdays after qualification test, note says protect demo date. |
| Lag coding | No WBS, control account, risk ID, budget, or approval record. |
Which interpretation is best supported by the exhibit?
Best answer: B
What this tests: Perform Planning and Scheduling Duties
Explanation: Risk mitigation can be incorporated into an earned value baseline when it represents authorized work or approved schedule reserve that is visible, traceable, budgeted, and logically connected to the plan. In the exhibit, the alternate chamber reservation and pre-test checkout satisfy those conditions: they are tied to an approved response, control account, budget, and schedule logic. The eight-day lag does not. It has no WBS or control-account identity, no budget, no risk reference, and no approval record. Leaving it in the baseline as informal protection would obscure float, weaken schedule credibility, and make variance and forecast analysis less transparent. The proper professional judgment is to preserve the authorized mitigation while either obtaining formal approval and identification for the schedule reserve or removing the hidden margin.
The response activities are traceable and authorized, while the unlabeled lag lacks the required control-account, budget, risk, and approval basis.
Topic: Perform Planning and Scheduling Duties
A control account manager submitted a May 31 earned value update for a work package with a budget of $200,000. The approved measurement method is weighted milestones with no partial credit; a milestone earns value only when its objective accomplishment criterion is met by the status date.
| Milestone | Weight | Objective criterion | May 31 evidence |
|---|---|---|---|
| Design package approved | 30% | Customer approval recorded | Approval recorded May 18 |
| Procurement specification released | 20% | Released in document control | Release recorded May 27 |
| Prototype test passed | 25% | All acceptance tests passed | Test run completed; two failures open |
| Installation readiness review complete | 25% | Review minutes signed | Review scheduled June 6 |
The control account manager claimed 70% earned value, or $140,000. Which professional judgment is best supported by the exhibit?
Best answer: D
What this tests: Perform Planning and Scheduling Duties
Explanation: Weighted milestones support earned value only when the approved accomplishment criteria are objectively satisfied at the status date. Here, the design approval and procurement release have documented evidence by May 31, so 50% of the $200,000 work package budget is earned. That supports $100,000 of earned value. The prototype test milestone cannot be earned because the criterion was passing all acceptance tests, and two failures remain open. The installation readiness review also cannot be earned because it is only scheduled after the status date and has no signed minutes. Crediting near-complete, scheduled, or partially successful work would weaken schedule-status integrity and overstate physical accomplishment.
The approved no-partial-credit milestone method supports earning only the 30% and 20% milestones completed by the status date.
Topic: Perform Budgeting Duties
At the 30 June status date, a project uses the rule \(\text{contract budget base (CBB)} = \text{performance measurement baseline (PMB)} + \text{management reserve (MR)}\). Contingency inside a control account may be applied only to the identified risk documented for that control account. MR is outside the PMB and may be allocated only by documented management action; it is not used to erase current-period cost variance.
Current budget position before reserve actions:
| Item | Amount |
|---|---|
| PMB, including control-account contingency | $8,700,000 |
| MR | $600,000 |
| CBB | $9,300,000 |
Status evidence:
Which reserve decision is supported at the 30 June status date?
Best answer: D
What this tests: Perform Budgeting Duties
Explanation: Reserve decisions must be traceable to the type of budget and the authorization basis. The $75,000 is supported because it is contingency already tied to an identified risk in CA-220, so it can be applied within that control account. The $200,000 customer-approved scope change is authorized budget and should increase the CBB and PMB, typically through undistributed budget until detailed planning assigns it. MR remains $600,000 because no documented management action authorizes an MR draw, and the $60,000 productivity overrun is a performance variance, not a reserve justification by itself. After the supported action, the PMB becomes $8,900,000 and CBB becomes $9,500,000, while MR remains unchanged.
The identified risk and approved scope change support the contingency use and PMB increase, while the productivity variance has no approved reserve action.
Topic: Analysis and Management Reports
At the June 30 status date, a project has the following cumulative earned value data. Values are in USD millions.
Use \(CPI = EV / AC\). If current cost efficiency continues, use \(EAC = BAC / CPI\). The project director needs analysis for the quarterly executive review to decide whether senior management action is required. Which analysis is most appropriate for that audience?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: Executive earned value analysis should translate project-control data into business impact and required decisions. Here, CPI is \(44.0 / 46.4 \approx 0.95\). Continuing that cost efficiency gives \(EAC = 120.0 / 0.948 \approx 126.5\). That forecast is 6.5 above the PMB and 1.5 above the PMB plus management reserve, so the executive-level issue is not the detailed variance mechanics; it is whether to direct recovery, approve a formal budget or funding action, or change management strategy. Working-level groups need different analysis: CAMs need control-account root cause and corrective action, schedulers need logic and float analysis, and accounting needs traceability of actual costs.
Executives need an aggregate forecast, exposure against available budget authority, and a decision-oriented management action.
Topic: Analysis and Management Reports
At the 30 June status date, a control account manager is preparing the monthly earned-value report for a work package with a BAC of $200,000. The approved performance measurement rule is objective units complete: each of 100 identical units earns 1% of the BAC only after installation and quality acceptance.
Status facts:
| Item | Amount or quantity |
|---|---|
| Planned units accepted by 30 June | 50 units |
| Units installed and quality accepted by 30 June | 35 units |
| Actual costs accrued through 30 June | $90,000 |
| Supplier invoices paid through 30 June | $60,000 |
| Open purchase commitments | $80,000 |
The manager says the package is “about half done” because half the duration has elapsed and several materials are already committed. What should be reported for earned progress, and what is the management meaning?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: Earned value must be based on the approved physical progress measurement method, not on time elapsed, money spent, invoices paid, commitments, or optimistic narrative. The work package earns 1% of its $200,000 BAC for each unit installed and quality accepted. With 35 accepted units, earned value is 35% × $200,000 = $70,000. Planned value at the status date is 50 planned units, or $100,000. The correct management message is that the package is behind the planned earned progress. Actual costs of $90,000 are relevant for cost performance, but they do not create earned progress. Paid invoices and open commitments may support accounting and forecast review, but they are not physical accomplishment.
Only the 35 accepted units earn value, so EV is 35% × $200,000 = $70,000, which is below the $100,000 planned value.
Topic: Analysis and Management Reports
A control account manager is preparing the March earned-value management report. Which interpretation is best supported by the status data?
| Status item | March status |
|---|---|
| PV | 1,200 (USD 000s) |
| EV | 1,050 (USD 000s) |
| AC | 1,180 (USD 000s) |
| EV credit rule | Accepted test procedures only |
| Risk response | Extra supplier test planned next month; estimated cost 90 (USD 000s) |
| Authorization status | Approved as mitigation within current scope; no accepted procedure and no baseline change |
Best answer: C
What this tests: Analysis and Management Reports
Explanation: Risk response spending is not earned performance unless it completes work under the approved earned-value measurement criteria. Here, EV is credited only for accepted test procedures. The extra supplier test is planned for next month, has not produced an accepted procedure, and has not changed the baseline. Its estimated cost should therefore be reflected in the remaining forecast, such as ETC and EAC, so management sees the expected cost impact of the mitigation. Crediting EV for risk reduction would overstate physical accomplishment and distort CPI and SPI. If a response later creates authorized new scope or changes the baseline, that would be handled through change control, not by treating the forecasted mitigation cost as earned value.
The mitigation cost is a forecasted cost of future work, while earned value remains tied to accepted test procedures.
Topic: Organizing
During a monthly EVMS review, a control account for software integration shows CPI 0.88 and SPI 0.82 at the status date. The approved WBS defines the integration deliverable, but the OBS/RAM lists both Systems Engineering and Test as responsible organizations with no single accountable control account manager. The variance narrative says the delay is caused by “the other group,” and the EAC assumes full recovery without a named corrective-action owner. Baseline changes require change-control board approval. What is the best professional action before finalizing the management report?
Best answer: D
What this tests: Organizing
Explanation: An EVMS control structure must connect authorized scope to a responsible organization and an accountable manager. When ownership is unclear, variance narratives often become unsupported, corrective actions lack authority, and EAC assumptions become optimistic rather than traceable. The immediate professional action is not to hide or rebaseline the variance, but to disclose the accountability weakness, correct the RAM/work authorization alignment, and require variance analysis and forecast assumptions from the accountable control account manager. This protects baseline integrity while improving report credibility and management actionability.
Clear organizational accountability is needed before the variance explanation, recovery plan, and forecast can be credible.
Topic: Analysis and Management Reports
As of the June 30 status date, a control account has the following cumulative data:
| Measure | Amount |
|---|---|
| BAC | $8,000,000 |
| PV | $4,500,000 |
| EV | $3,600,000 |
| AC | $4,500,000 |
| CPI | 0.80 |
| SPI | 0.80 |
The variance analysis says the schedule slip was caused by a temporary access restriction that has now been removed. The cost overrun is from recurring lower labor productivity on installation work, and the remaining scope is mostly the same type of installation work. No approved recovery plan or validated bottom-up estimate exists.
Use these formulas as applicable:
Which forecast is most supportable for the management report?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: The appropriate EAC method depends on what the performance data says about the remaining work. Here, the cost overrun is not described as a one-time event; it is a recurring labor productivity trend on work that is similar to the remaining scope. That supports applying the cumulative CPI to the remaining budget. The remaining budget is $8,000,000 - $3,600,000 = $4,400,000. Dividing by CPI gives ETC = $4,400,000 / 0.80 = $5,500,000. Adding AC gives EAC = $4,500,000 + $5,500,000 = $10,000,000. Since BAC is $8,000,000, the VAC is $8,000,000 - $10,000,000 = -$2,000,000. SPI should not be applied because the schedule driver has been removed and is not expected to affect remaining cost efficiency.
The recurring cost productivity problem is expected to continue, while the schedule cause has been resolved, so the remaining budget of $4,400,000 should be divided by CPI only.
Topic: Revisions and Data Maintenance
A project controls manager is preparing a message to accompany a corrected May earned value report. The correction is required before the June customer submittal.
| Exhibit item | Fact |
|---|---|
| Original May report | Control account 3.2 showed PV = $1,200,000, EV = $1,050,000, AC = $1,100,000. |
| Approved correction | Change notice CN-48 was approved on June 12 with an effective date of May 20. |
| Data impact | May PV and EV each increase by $90,000 for authorized scope completed in May; May AC is unchanged. |
| Reporting requirement | Prior-period restatements must identify the approval source, show the variance impact, and preserve the original report in the audit file. |
Which communication is most appropriate?
Best answer: D
What this tests: Revisions and Data Maintenance
Explanation: When a retroactive data or baseline change affects a prior earned value report, the communication should be transparent, traceable, and decision-oriented. The corrected report should identify the approved source of the change, explain which prior values changed, show the effect on performance measures, and preserve the original report for auditability. In this case, CN-48 is an approved change with a May effective date, so May PV and EV should be restated while AC remains unchanged. The message should not hide the restatement because the variance improved, and it should not overwrite history without an audit trail. The correction is a baseline/data maintenance action, not a forecast improvement by itself.
This response is factual, traceable to the approved retroactive change, and transparent about the prior-period reporting impact.
Topic: Perform Budgeting Duties
At the 30 June status date, control account CA-230 has no approved scope change and no accounting correction in process. The control account manager wants to replace the unstarted July-December planning package with detailed work packages. Work planned through June will remain in the existing work packages.
Current records:
Assume the future baseline budget affected by this planning change is calculated as authorized BAC minus cumulative PV through the status date. Which planning change best protects EVMS traceability across baseline, actual-cost, and forecast records?
Best answer: B
What this tests: Perform Budgeting Duties
Explanation: A planning change that details future work should not rewrite historical performance or accounting records when there is no approved scope change or accounting correction. The authorized BAC remains USD 1,200,000, and the cumulative PV, EV, and AC through 30 June remain traceable to the status record. The future baseline budget affected by the planning change is USD 1,200,000 - USD 700,000 = USD 500,000. The EAC is a forecast record, not a new budget authorization. Preserving these distinctions keeps the PMB, earned progress, actual costs, and forecast mutually traceable while allowing legitimate future planning detail.
This preserves historical performance and actual-cost traceability while replanning only the authorized future baseline budget: USD 1,200,000 minus USD 700,000.
Topic: Revisions and Data Maintenance
At the September 30 status cycle, an audit finds that approved change CR-27 was omitted from the August 31 performance measurement baseline. CR-27 was approved by the change control board on July 10 with an effective date of July 1.
August 31 report originally issued:
| Measure | Amount |
|---|---|
| PV | $1,000,000 |
| EV | $920,000 |
| AC | $990,000 |
| BAC | $2,000,000 |
CR-27 adds BAC of $200,000. Its approved time-phased PV through August is $140,000. Objective accomplishment on CR-27 through August supports EV of $100,000. The $115,000 of actual costs for CR-27 was already included in the August AC above. Use SV = EV - PV and CV = EV - AC.
Which retroactive-change control best preserves the audit trail, approval evidence, baseline history, and management understanding?
Best answer: D
What this tests: Revisions and Data Maintenance
Explanation: An approved change that was effective in a prior period but omitted from the baseline should be handled as a controlled prior-period correction, not hidden in the current period or erased from history. The calculation is cumulative: PV increases by $140,000, EV increases by $100,000, and BAC increases by $200,000. AC stays at $990,000 because the CR-27 actual costs were already included. The corrected August values are PV $1,140,000, EV $1,020,000, AC $990,000, and BAC $2,200,000. Therefore, SV is $1,020,000 - $1,140,000 = -$120,000, and CV is $1,020,000 - $990,000 = $30,000. Preserving the original report, linking the change to its approval, and explaining the restatement gives management a clear and auditable view of what changed and why.
This keeps the approval trail and original history while transparently restating the cumulative baseline and performance values affected by the omitted approved change.
Topic: Perform Budgeting Duties
A control account manager submits the following rolling-wave planning change for approval on May 31. All work remains authorized in the contract, and no actual costs have been recorded yet against the existing planning package. Which professional judgment is best supported by the exhibit?
| Record | Current approved baseline | Proposed change effective Jun 1 |
|---|---|---|
| Scope | PP-220: system integration testing | Three work packages with same deliverables |
| Budget | PP-220 BAC $600,000 | WP-221 $150,000; WP-222 $250,000; WP-223 $200,000 |
| Schedule | PP-220 planned Jul-Aug | Activities A221-A223 tied to work packages |
| Actual-cost collection | PP-220 charge code closes Jun 1 | WP-221 and WP-223 codes issued; WP-222 code pending |
| Forecast | Current EAC $640,000 | WP-221 $160,000; WP-223 $210,000; remainder left on PP-220 |
Control note: PMB total is unchanged, and no management reserve is requested.
Best answer: A
What this tests: Perform Budgeting Duties
Explanation: A rolling-wave planning change can protect baseline integrity when it converts authorized planning-package scope into detailed work packages without changing the total PMB unless an approved scope or budget change exists. However, EVMS traceability requires more than matching budget totals. Each new work package must connect to schedule activities, budget, authorized work, actual-cost collection, and forecast records. In the exhibit, scope, BAC, and schedule links are mostly preserved, but WP-222 has no issued charge code and part of the EAC remains on the closed planning package. That creates a break between future actual costs, earned value, and the forecast. The proper judgment is to condition approval on completing those traceability links, not to reject valid rolling-wave planning or force the forecast to equal the budget.
The change preserves scope and budget totals, but it does not yet maintain actual-cost and forecast traceability for all replacement work packages.
Topic: Analysis and Management Reports
At the 30 June status date, a control account for 20 identical modules has the following earned value rule: each module has a budget of $200,000, and 100% credit is earned only when the module is installed and accepted in integration testing.
The draft performance report shows:
| Measure | Amount |
|---|---|
| PV | $2,000,000 |
| EV | $2,200,000 |
| AC | $1,800,000 |
The quality log shows 11 modules installed, but only 8 accepted; 3 failed integration testing and require rework before acceptance. The rework estimate is $450,000 and is not yet included in AC or ETC. Use CV = EV - AC, SV = EV - PV, CPI = EV / AC, and SPI = EV / PV.
Which management-reporting conclusion is most appropriate?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: Favorable variance can be misleading when earned value is credited before the required technical or quality accomplishment has occurred. The report credited 11 installed modules, but the stated measurement rule requires integration-test acceptance. Only 8 modules qualify, so EV should be 8 × $200,000 = $1,600,000. Against PV of $2,000,000 and AC of $1,800,000, performance is unfavorable: CV is -$200,000 and SV is -$400,000. The failed tests are not merely a future uncertainty; they are a current technical quality issue that affects earned progress and should drive variance analysis, corrective action, and forecast review. Reporting the draft CPI and SPI as green would overstate performance and weaken management decision quality.
Only 8 accepted modules meet the EV rule, so the apparently favorable draft variances are misleading and the failed tests threaten both current performance and future work.
Topic: Account Considerations
At the May 31 status date, a control account manager reviews the following EVMS report before approving the monthly forecast.
| Item | Value or note |
|---|---|
| BAC | $1,000,000 |
| PV | $600,000 |
| EV | $540,000 |
| AC reported in EVMS | $450,000 |
| Reported CPI | 1.20 |
| Formula EAC used | BAC / CPI |
Reconciliation note:
Which interpretation is best supported by the exhibit?
Best answer: D
What this tests: Account Considerations
Explanation: Earned value comparisons must use a consistent cost basis. If the baseline and EV include an overhead burden, then AC used for CPI, cost variance, and EAC should include the corresponding incurred overhead or a properly supported accrual/allocation. Here, EV is measured against a burdened budget, but AC omits $80,000 of incurred overhead. The reported CPI of 1.20 is therefore overstated; including the overhead would make AC $530,000 and CPI about 1.02. A formula EAC based on the overstated CPI would also be too optimistic. The professional response is not to change the baseline to fit incomplete actuals, but to reconcile indirect cost treatment between accounting and EVMS reporting before drawing variance or forecast conclusions.
The performance measures are distorted because budgeted overhead is included in EV but the matching incurred overhead is missing from AC.
Topic: Perform Planning and Scheduling Duties
During baseline planning for a control account, the project controls manager reviews this integrated master schedule excerpt. Which professional interpretation is best supported by the exhibit?
| Item | Planning fact |
|---|---|
| Milestone M-310 | Integration Test Ready; earns 35% of the control account budget when the signed readiness checklist is complete |
| Baseline finish | 30 Sep; forecast also shows 30 Sep |
| Required input | Vendor simulator must be available before the readiness checklist can be signed |
| Current schedule logic | Simulator availability is modeled only as a 5-day lag after internal installation; no link to procurement award or vendor lead time |
| Procurement status | Purchase order not awarded; earliest award is 22 Jul; quoted lead time is 12 weeks |
| Risk register | No schedule risk or mitigation is recorded for simulator delivery |
Best answer: A
What this tests: Perform Planning and Scheduling Duties
Explanation: A planning and scheduling risk exists when the schedule basis for a baseline milestone does not reflect the work, dependencies, or lead times needed to achieve it. Here, the milestone is a major earned-value point and cannot be completed without the vendor simulator. The schedule forecast still shows the baseline date, but the simulator is not tied to procurement award or the quoted 12-week lead time. That makes the milestone forecast unreliable and could distort the performance measurement baseline if accepted without mitigation. The professional response is to identify the risk, correct the schedule logic, assess the forecast impact, and define mitigation or management action before relying on the milestone for baseline credibility.
The exhibit shows that the readiness milestone depends on vendor simulator delivery, but the schedule omits the procurement dependency and ignores the 12-week lead time.
Topic: Revisions and Data Maintenance
During the month 8 EVMS data maintenance cycle, a ledger reconciliation finds that a £180,000 material accrual recorded in month 6 was charged to Control Account B instead of Control Account A. The cost was for authorized work physically performed in Control Account A. Finance and both control account managers have approved the accounting correction.
Constraints:
What is the best professional action?
Best answer: D
What this tests: Revisions and Data Maintenance
Explanation: A retroactive accounting correction should preserve the integrity of the earned value record. Because the cost was incurred in month 6 for authorized work in Control Account A, the actual cost history and affected control account variances should be corrected with a clear audit trail. Since PV and EV are unchanged and no baseline change is authorized, the performance measurement baseline must not be moved to offset the variance. The current EAC should be reviewed using corrected actual costs and valid remaining ETC assumptions; the project total may or may not change, but the control account forecasts and variance explanations must reflect the corrected data. Stakeholder reporting should be transparent: identify the correction, show the effect on prior variances, state that the baseline was not changed, and explain any current forecast impact.
This preserves data integrity while clearly distinguishing an accounting correction from a baseline change and from current forecast impacts.
Topic: Organizing
An EV analyst is reviewing the WBS before approving the performance measurement baseline for a pump-station upgrade. Which WBS boundary interpretation is best supported by the exhibit?
| Exhibit item | Relevant facts |
|---|---|
| Authorized contract scope | Engineering package; pump skid procurement; mechanical installation and tie-ins; commissioning and acceptance testing |
| Explicit exclusions | Owner-funded foundation upgrade under a separate civil contract; remote monitoring dashboard pending approval under CR-12 |
| Draft WBS baseline | Includes Site readiness for foundation work; includes Remote monitoring as a planning package; includes site-readiness support inside Mechanical installation; has no separate commissioning work package |
Best answer: D
What this tests: Organizing
Explanation: A WBS boundary for earned value should reflect the authorized scope of work and provide traceability for each deliverable in the performance measurement baseline. The exhibit shows three boundary problems: owner civil foundation work is outside the contract, the remote monitoring dashboard is only a pending change, and site-readiness support appears in more than one place. It also shows missing authorized scope because commissioning and acceptance testing are part of the contract but are not separately planned. The proper interpretation is to exclude unauthorized or externally funded work, prevent duplicate scope, and ensure every authorized deliverable is represented once in the WBS so earned value cannot be claimed for missing, duplicated, or unapproved work.
This protects the baseline by including all authorized deliverables once and excluding work that is not yet authorized.
Topic: Perform Budgeting Duties
At the 31 July status date, Control Account CA-210 has the following approved budget and performance data. Cost variance is calculated as CV = EV - AC. Management reserve is held outside the performance measurement baseline.
| Item | BAC | EV | AC |
|---|---|---|---|
| WP-1, completed | $500,000 | $500,000 | $575,000 |
| WP-2, not started | $300,000 | $0 | $0 |
| Planning package PP-3 | $200,000 | $0 | $0 |
There is no approved scope change, no accounting correction, and no transfer of responsibility. The CAM proposes moving $75,000 of budget from WP-2 to the completed WP-1 in the July baseline. This would make WP-1 BAC and EV equal $575,000 and reduce WP-2 BAC to $225,000, while total PMB and management reserve remain unchanged.
How should this proposed budget movement be classified?
Best answer: A
What this tests: Perform Budgeting Duties
Explanation: WP-1 is complete with EV of $500,000 and AC of $575,000, so its current cost variance is $500,000 - $575,000 = -$75,000. The proposed movement would raise the completed work package BAC and EV to $575,000 and make the variance disappear. Because there is no approved scope change, responsibility transfer, accounting correction, or documented baseline correction, the movement is not legitimate baseline maintenance. It is also not normal budget distribution, since budget distribution should allocate authorized budget to planned work without rewriting completed performance. Management reserve is not being drawn, and MR should not be used simply to erase realized cost overruns. The proper classification is unauthorized replanning because it compromises baseline integrity and performance history.
The movement would change earned value history from a $75,000 unfavorable CV to zero without authorized scope, responsibility, or accounting justification.
Topic: Account Considerations
At the March 31 status date, the project controls analyst is reviewing Control Account CA-220 before the monthly earned value report is issued. Which interpretation is best supported by the reconciliation notes?
| CA-220 reported status | Amount |
|---|---|
| PV | $500,000 |
| EV | $450,000 |
| AC | $530,000 |
| Reported CV | -$80,000 |
Reconciliation notes:
A $60,000 subcontractor invoice was posted to CA-220 on March 29 for April mobilization work; no March work was performed for that invoice.
Materials costing $40,000 were received and installed by March 31, but no accrual has been recorded because the supplier invoice has not arrived.
Labor charges and EV accomplishment are supported by March time records and physical progress evidence.
A. Use the reported AC of $530,000 for the forecast because posted invoices are the controlling source for earned value cost performance.
B. Increase EV by $40,000 because the installed materials were not included in the accounting system by March 31.
C. Adjust March AC to $510,000; CA-220 remains in an unfavorable cost variance, but the forecast should be based on reconciled actual costs.
D. Treat the entire reported cost variance as an accounting timing issue and remove it from the variance analysis narrative.
Best answer: C
What this tests: Account Considerations
Explanation: Actual cost used in earned value reporting should reflect costs applicable to the work performed by the status date and be traceable to the correct period and control account. The April mobilization invoice is a cutoff error for March because the work had not occurred by March 31, so it should not be included in March AC. The installed materials are a missing accrual because the cost was incurred for March work even though the supplier invoice had not arrived. The net correction is $530,000 - $60,000 + $40,000 = $510,000. With EV of $450,000, the corrected cost variance is still unfavorable at -$60,000. The professional response is to reconcile actual costs before interpreting CPI, variance causes, or EAC.
Removing the April invoice and adding the missing March accrual changes AC to $510,000, leaving CV at -$60,000 rather than the reported -$80,000.
Topic: Revisions and Data Maintenance
At the February data-maintenance review, an accounting reconciliation finds that a January subcontract accrual of $50,000 was charged to Control Account A but belongs to Control Account B. The January status report has already been issued. No scope was added or deleted, the work packages and earned value methods were correct, and no baseline change was approved.
January cumulative data before correction:
| Control account | PV | EV | AC |
|---|---|---|---|
| A | $600,000 | $540,000 | $620,000 |
| B | $400,000 | $380,000 | $330,000 |
Use: \(CV = EV - AC\). What is the best classification and reporting treatment?
Best answer: C
What this tests: Revisions and Data Maintenance
Explanation: A mischarged accrual is an accounting data correction, not a performance reclassification or baseline revision. The correction moves actual cost from the wrong control account to the right one: Control Account A AC becomes $620,000 - $50,000 = $570,000, and Control Account B AC becomes $330,000 + $50,000 = $380,000. PV and EV remain unchanged because authorized scope, baseline plan, physical progress, and earned value methods did not change. The corrected CVs are A: $540,000 - $570,000 = -$30,000 and B: $380,000 - $380,000 = $0. Because the January report was already issued, the correction should be traceable and disclosed rather than hidden through budget movement, reserve use, or after-the-fact measurement changes.
The $50,000 transfer fixes actual-cost traceability without changing authorized scope, earned progress, or the performance measurement baseline.
Topic: Analysis and Management Reports
At the June 30 status date, a piping installation control account must be summarized for the monthly management report. BAC is $2,000,000. Use: CV = EV - AC; SV = EV - PV; CPI = EV / AC; SPI = EV / PV; EAC at cumulative CPI = BAC / CPI.
| Measure | May 31 cumulative | June 30 cumulative |
|---|---|---|
| PV | $900,000 | $1,200,000 |
| EV | $820,000 | $1,050,000 |
| AC | $910,000 | $1,260,000 |
June cause evidence: 20% of welds failed inspection after a late design clarification, causing rework. The clarification has been issued, but no post-correction productivity data will be available until July. The control account manager proposes an EAC of $2,250,000 assuming productivity returns to plan next month.
Which variance explanation best supports the management report?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: A useful variance explanation does more than state the numbers. It connects performance data to the reason for the variance, the direction of the trend, the forecast implication, and the action needed to manage uncertainty. At June 30, CV is $1,050,000 - $1,260,000 = -$210,000 and SV is $1,050,000 - $1,200,000 = -$150,000. Both are worse than May. CPI is about 0.83, so a simple CPI-based EAC is approximately $2,000,000 / 0.83, or about $2,400,000. The proposed $2,250,000 EAC may be reasonable only if the recovery assumption is validated. The report should therefore disclose the rework cause, declining trend, forecast sensitivity, and the corrective action with follow-up evidence.
This explanation links the calculated variances, root cause, adverse trend, forecast uncertainty, and evidence-based corrective-action follow-up.
Topic: Perform Planning and Scheduling Duties
Before using a CPM schedule as the time-phased basis for earned-value planning, the planner reviews this excerpt. Project start is day 0. Use a forward pass: for an FS predecessor, successor earliest start is predecessor finish; for an SS+n predecessor, successor earliest start is predecessor start + n. Finish = start + duration. There are no external date constraints.
| Activity | Duration | Current predecessor logic |
|---|---|---|
| A: Design release | 5 days | FS from Start milestone |
| B: Build skid | 20 days | FS from A |
| C: Complete foundations | 15 days | FS from A |
| D: Set skid | 3 days | SS+18 from B; FS from C |
| E: Hookup and test | 7 days | FS from D; FS to Finish milestone |
Physical sequence: the skid cannot be set until both the skid build and the foundations are complete. Which schedule correction best resolves the logic defect before baseline use?
Best answer: D
What this tests: Perform Planning and Scheduling Duties
Explanation: The current model lets Activity D start on day 23 because B starts on day 5 and SS+18 gives 5 + 18 = 23. However, B does not finish until day 25, so the current logic allows skid setting to begin two days before the skid build is complete. The correct schedule correction is to replace the B-to-D SS+18 lag with an FS relationship from B to D, while retaining the FS relationship from C to D. Then D starts at max(B finish day 25, C finish day 20) = day 25, finishes day 28, and E finishes day 35. For earned-value baseline use, the schedule should represent physical accomplishment logic, not artificial dates or lags that only happen to work for the current duration.
This ties skid setting to completion of the skid build, preserves the foundation dependency, and produces a logic-driven day 35 finish.
Topic: Perform Planning and Scheduling Duties
A control account manager is finalizing the integrated baseline for a critical-path work package. The work has not started, and no trigger has occurred.
| Planning fact | Detail |
|---|---|
| Work package | Vendor drawing approval supports fabrication release on May 15 |
| Current schedule | 0 days total float |
| Risk probability | 60% chance that customer comments will not be received by April 12 |
| Impact if triggered | 8 working days of delay to fabrication release |
| Authorized mitigation | Add an interim technical review by April 5 using 80 planned engineering hours |
| Contingency plan | If comments are not received by April 12, use an alternate fabrication slot requiring 120 additional hours |
Which earned-value planning response is best supported by the exhibit?
Best answer: A
What this tests: Perform Planning and Scheduling Duties
Explanation: Earned-value planning should distinguish mitigation from contingency. The interim technical review is an authorized preventive action with planned hours and a scheduled date, so it belongs in the baseline schedule and budget for the control account. The alternate fabrication slot is a contingency plan for a defined trigger: customer comments not received by April 12. Since the trigger has not occurred, the plan should be documented and ready, but not treated as current earned work simply because the probability is high. The risk also cannot be ignored because the work package is on the critical path with no float and has a material schedule impact. The professional response protects baseline integrity while ensuring the risk response is visible, actionable, and traceable to objective trigger facts.
The authorized mitigation should be planned now, while the contingency should be tied to its trigger rather than treated as current earned work.
Topic: Organizing
A contractor is preparing an integrated baseline and wants to open WBS element 1.3 as a control account. Review the WBS maturity notes:
| Attribute | Current WBS element 1.3 notes |
|---|---|
| Scope statement | “Plant integration, vendor coordination, startup support, and management reviews” |
| Authorization | Vendor interface scope is still pending customer approval |
| Responsibility | Engineering and construction managers are both listed as accountable |
| Schedule basis | One 10-month activity with no interim objective milestones |
| Budget basis | $2.4 million held as one amount across engineering, field labor, vendor support, and level-of-effort reviews |
| EV method | Monthly percent complete proposed by manager judgment |
Which interpretation is best supported by the exhibit?
Best answer: A
What this tests: Organizing
Explanation: A WBS element that supports earned value control must define authorized scope clearly enough to plan, schedule, budget, assign responsibility, and measure accomplishment objectively. The exhibit shows several maturity weaknesses: part of the scope is not yet approved, the work combines multiple deliverables and level-of-effort activities, accountability is split, the schedule has no measurable interim points, and the proposed EV method relies on subjective judgment. Before release into the performance measurement baseline, the element should be decomposed or clarified so work packages and planning packages are traceable to authorized scope, a responsible manager, objective completion criteria, and time-phased budget.
The exhibit shows pending scope, ambiguous accountability, weak schedule detail, and subjective progress measurement, so it is not ready for EVMS control.
Topic: Analysis and Management Reports
As of the May 31 status date, a control account uses an accepted-deliverable earned value method: each accepted test pack earns 100k, and in-process packs earn no value until accepted. Use SV = EV - PV, CV = EV - AC, SPI = EV / PV, and CPI = EV / AC. All values are in thousands of dollars.
| Fact | Status |
|---|---|
| Planned accepted test packs | 8 |
| Actually accepted test packs | 5 |
| Actual cost recorded | 510k |
| In-process packs not accepted | 2 |
The two in-process packs are waiting for late upstream calibration approval. Labor rates and material prices are within 2% of plan, and no rework has been recorded. Which conclusion best identifies the variance type and likely root-cause category?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: The planned value is 8 accepted packs × 100k = 800k. The earned value is 5 accepted packs × 100k = 500k. Actual cost is 510k. Therefore, SV = 500k - 800k = -300k, and SPI = 500k / 800k = 0.625, showing a significant unfavorable schedule variance. CV = 500k - 510k = -10k, and CPI is about 0.98, so cost performance is close to plan. The work-status facts point to a schedule or accomplishment root cause: two packs are in process but cannot earn value because late calibration approval prevents acceptance. The data does not support a primary cost-rate, material-price, or rework cause.
EV is 500k versus PV of 800k, creating a large unfavorable SV while CV is only -10k, so the main issue is delayed earned accomplishment.
Topic: Perform Budgeting Duties
A project team is preparing the initial performance measurement baseline for an authorized engineering control account. The work authorization is signed, the control account budget is $2.4 million, and execution begins next month. The draft schedule has the correct deliverables but several activities are not logic-linked, two long-duration work packages have only start and finish dates, and the budget has been spread evenly by month to match the finance cash-flow plan. What is the best action before approving the baseline?
Best answer: C
What this tests: Perform Budgeting Duties
Explanation: The performance measurement baseline is not just an authorized budget total. It is the time-phased budget plan for authorized work, integrated with the schedule and supported by measurable accomplishment criteria. If activities are not logically connected, long work packages lack interim objective measures, and the budget is spread to match cash flow, planned value will not represent planned physical progress. The professional action is to fix the integration before approval: align the WBS/control account scope to the schedule, establish credible logic and milestones, define how earned value will be claimed, and phase the budget according to when work is planned to be accomplished. Cash-flow and expenditure timing may support funding analysis, but they should not substitute for the performance baseline.
A credible performance measurement baseline requires authorized scope, budget, and schedule to be integrated around planned accomplishment rather than cash flow or unsupported dates.
Topic: Account Considerations
A project team is preparing its first monthly earned value report after baseline approval. The EV tool is organized by WBS, OBS, and control account, but the corporate accounting system currently records labor and material actuals by department, general ledger account, and purchase order. Work authorization documents identify the responsible control account manager and authorized WBS element. Finance will not redesign the chart of accounts before the reporting cutoff.
What is the best action to make the actual costs traceable for earned value reporting?
Best answer: C
What this tests: Account Considerations
Explanation: Earned value actual cost must be traceable from the accounting system to the same authorized work structure used for planning, earning value, and reporting. When the accounting system does not naturally align with WBS and control accounts, the professional control is to establish a disciplined coding or crosswalk mechanism. That link should connect labor, purchase orders, accruals, and other actual-cost transactions to the correct authorized WBS/control account and responsible manager. This preserves accounting integrity while enabling reconciliation between finance records and earned value reports. The link should be controlled, auditable, and used consistently at the transaction or feeder-system level where possible. It should not be replaced by progress-based allocations, cash-payment timing, or a restructuring of the EV baseline to fit accounting convenience.
A controlled charge-code crosswalk links actual costs from the accounting system to authorized work and the EV control account structure without waiting for a chart-of-accounts redesign.
Topic: Perform Budgeting Duties
A control account manager is selecting the earned value technique for a budgeted work package before baseline approval. The work will be performed over three months and reported monthly.
| Work package fact | Baseline detail |
|---|---|
| Scope | Fabricate and test 120 identical cable harnesses |
| Budget | $240,000 total; each harness has the same budgeted value |
| Completion evidence | Serial-numbered harness passes final electrical test and quality acceptance |
| In-process visibility | Labor hours vary by operator; partially assembled harnesses are not usable deliverables |
| Measurement concern | Avoid subjective percent-complete estimates and avoid earning value for unaccepted units |
Which earned value technique best fits this work package?
Best answer: A
What this tests: Perform Budgeting Duties
Explanation: The best earned value technique matches how progress can be objectively demonstrated. For repeated, equal-value deliverables, a units-complete method is appropriate when each unit has a clear completion point and acceptance record. Here, each harness has the same budgeted value, and completion is evidenced by serial-numbered test and quality acceptance. That gives a defensible basis for earning value without relying on subjective estimates or labor-hour consumption. The method also protects baseline integrity by preventing value from being earned for partially assembled or rejected units. Techniques that earn value simply because time has passed, work has started, or a supervisor estimates progress would increase measurement risk for this work package.
The work has repeatable equal-value units and objective acceptance evidence, so earned value should be based on the count of completed accepted units.
Topic: Account Considerations
At the June 30 status date, a control account manager is reviewing the material lot forecast for cable tray assemblies. The EVMS accounting practice for this analysis is to use accepted receipts, recorded accruals, and allocated freight, not cash paid only.
| Fact | Amount |
|---|---|
| Baseline material quantity | 1,000 units |
| Baseline material budget | $200,000 |
| Accepted receipts to date | 650 units |
| Installed and earned to date | 600 units |
| Supplier unit price on accepted receipts | $218 per unit |
| Allocated inbound freight | $3,250 |
| Paid invoice quantity | 500 units |
| Accrued but unpaid receipt quantity | 150 units |
Assume the remaining 350 units will be purchased at the same loaded actual unit cost as the accepted receipts. Which statement best describes the material-cost implication for management reporting?
Best answer: C
What this tests: Account Considerations
Explanation: Material cost analysis should follow the accounting basis stated for the status date. Accepted receipts include both the paid 500 units and the accrued 150 units, and allocated freight is part of the loaded material cost. The received lot cost is \(650 \times \$218 + \$3,250 = \$144,950\). Dividing by 650 accepted units gives a loaded actual unit cost of $223. Applying that rate to the full 1,000-unit requirement gives a material EAC of $223,000. Compared with the $200,000 baseline material budget, the forecast lot impact is an unfavorable $23,000. The 600 installed units matter for earned value, but using installed quantity as the denominator would mix cost timing with physical accomplishment.
Accepted receipt cost plus freight is $144,950, so the loaded unit cost is $223 and the full 1,000-unit lot forecasts $23,000 over the $200,000 budget.
Topic: Organizing
A control account manager submits the month-end earned value update for a test facility project. The project rule is that earned value may be recorded only for work packages released by a signed work authorization tied to approved scope and budget.
| Exhibit item | Current status |
|---|---|
| WBS 1.4.2 Test Rack Installation | Authorized work package, budget $180,000 |
| Thermal shield fabrication | Requested by customer engineer by email; change request not approved |
| Charge code used | Temporary code opened under WBS 1.4.2 |
| Physical progress reported | Shop reports 30% complete on the thermal shield |
| EV proposed | CAM proposes $24,000 EV using unused WBS 1.4.2 budget |
Which work authorization control should be applied?
Best answer: B
What this tests: Organizing
Explanation: Work authorization protects the integrity of the performance measurement baseline by ensuring that only approved scope is released for execution and performance measurement. Physical progress alone is not enough to earn value if the work is outside the authorized baseline. In this case, the thermal shield was requested informally and the change request has not been approved. A temporary charge code and unused budget in a related work package do not create authorized scope. The appropriate control is to stop earned value credit until change control approves the work, assigns it to the correct WBS/control account structure, budgets it, and releases it through formal work authorization.
Earned value should be measured only after the work is within authorized scope, budget, responsibility, and work release controls.
Topic: Organizing
A control account manager reports earned value for completed field work at the monthly status date. During review, the project controls analyst finds that part of the reported accomplishment is for added cable routing requested verbally by the site supervisor.
Constraints:
What is the best professional action?
Best answer: B
What this tests: Organizing
Explanation: Earned value must be traceable to authorized scope released for execution and included in the performance measurement baseline. Physical completion alone is not enough to claim earned value if the work was directed informally and has not passed change control or work authorization. The professional action is to protect baseline integrity: remove or segregate the unauthorized accomplishment from reported EV, report the authorized status accurately, and initiate the required change process so scope, budget, schedule, and responsibility can be formally established if approved. This also prevents double counting, unsupported favorable performance, and loss of audit traceability.
Earned value should be claimed only for formally authorized scope, while the unauthorized work is handled through change control and work authorization.
Topic: Perform Budgeting Duties
A control account manager is defining the cost-element budget structure for a new control account before baseline approval. The structure must support actual-cost collection, variance analysis, and the monthly management report.
| Planning fact | Detail |
|---|---|
| Finance actual-cost feeds | Company labor; material; subcontract; travel/ODC; applied indirect burden |
| Subcontract PO | Site installation labor and material posted only as subcontract |
| WBS work packages | Design; build; site installation |
| Report need | Variance by cost element and total control account |
| Control rule | One actual cost in one cost element only |
Which cost-element structure should be used for the control account?
Best answer: C
What this tests: Perform Budgeting Duties
Explanation: Cost elements should be mutually exclusive categories that align with how actual costs are collected and how management needs to analyze variances. In the exhibit, finance provides actual-cost feeds for company labor, material, subcontract, travel/ODC, and applied indirect burden. The subcontract purchase order is posted only as subcontract, even though the subcontractor performs installation labor and supplies material. Therefore, splitting that PO into labor and material, or adding a separate installed-cost total as another cost element, would create double counting or reconciliation problems. WBS work packages remain the scope structure; they are not a substitute for cost-element classification. The best structure preserves traceability from budget to accounting actuals and allows meaningful cost-element variance analysis.
This structure matches the accounting feeds, supports cost-element variance reporting, and keeps each actual cost in a single element.
Topic: Analysis and Management Reports
A project director is reviewing the month-end earned value package for a major control account. The control account manager recommends reporting the account as recoverable with no EAC increase.
Status at the data date:
| Measure | Value |
|---|---|
| BAC | $10.0M |
| PV | $5.0M |
| EV | $4.4M |
| AC | $5.2M |
Constraints:
What is the best professional judgment for the management report?
Best answer: C
What this tests: Analysis and Management Reports
Explanation: A management report should distinguish objective performance from assumptions and pending actions. The account is behind plan and over cost: EV is below PV, and AC is above EV. The approved baseline remains the basis for current variance reporting until an authorized change is incorporated. A pending change request may affect future baseline or forecast treatment, but it does not justify suppressing current variance. Likewise, weekend overtime is not a credible recovery basis unless resources, funding, and schedule feasibility are confirmed. The appropriate judgment is to report the unfavorable status transparently, identify the uncertainty around the pending change and recovery plan, and update or qualify the EAC based on supportable assumptions.
The data show unfavorable performance, while the recovery and change assumptions are uncertain and not yet authorized.
Topic: Perform Planning and Scheduling Duties
During baseline planning on 1 May, a control account manager is planning WP-310, a field installation work package with a budget of $600,000 and a 60-working-day planned duration. The project rule is that approved mitigation activities that will definitely be performed are time-phased as planned work, while contingency work for an uncertain event is authorized only if its trigger occurs. Risk reserve is calculated as probability × impact.
| Planning fact | Value |
|---|---|
| Risk trigger | Failed factory acceptance test by 20 May |
| Unmitigated probability | 30% |
| Unmitigated impact if triggered | 8 working days and $80,000 |
| Mitigation task | 2 working days and $18,000 |
| Mitigation schedule effect | Uses available float; no milestone slip |
| Residual probability after mitigation | 10% |
| Residual impact if triggered | 3 working days and $35,000 |
Management wants the earned-value plan that minimizes expected cost while preserving objective progress measurement. Which response is best?
Best answer: C
What this tests: Perform Planning and Scheduling Duties
Explanation: The planning response should distinguish certain, authorized mitigation work from uncertain contingency work. The unmitigated expected cost exposure is \(30\% \times \$80,000 = \$24,000\), with an expected schedule exposure of \(30\% \times 8 = 2.4\) working days. The mitigation costs $18,000 and fits within available float, so it can be planned without slipping the milestone. After mitigation, the residual expected exposure is \(10\% \times \$35,000 = \$3,500\) and \(10\% \times 3 = 0.3\) working day. The combined expected cost is $21,500, lower than the unmitigated expected cost. In earned-value planning, the mitigation activity can be objectively scheduled and budgeted because it will be performed, while the recovery work should remain tied to the defined trigger rather than being earned before the event occurs.
This treats the certain mitigation as authorized planned work and holds only the residual trigger-based contingency because \(10\% \times 3 = 0.3\) day and \(10\% \times 35,000 = 3,500\).
Topic: Perform Planning and Scheduling Duties
A project controls lead is preparing the readiness recommendation for an integrated baseline review on a newly authorized avionics work package. The review package shows these conditions:
What is the best professional judgment on IBR readiness?
Best answer: C
What this tests: Perform Planning and Scheduling Duties
Explanation: An integrated baseline review tests whether the performance measurement baseline is credible and executable. Readiness is not shown merely by having a WBS, schedule, and budget. The baseline must integrate authorized scope, objective schedule logic, time-phased budget, identified risks and mitigation plans, and clear organizational responsibility. In this case, approved mitigation work required before qualification test is absent from both schedule and budget, so the plan does not reflect known risk-response work. The responsibility conflict between the RAM and work authorization also weakens control account accountability. The best action is to correct or reconcile these inconsistencies before representing the package as ready for IBR.
An IBR should confirm that scope, schedule, budget, risk, and responsibility form one consistent performance baseline before accepting readiness.
Topic: Analysis and Management Reports
At the May data date, a fabrication control account shows cumulative PV of $2.4 million, EV of $2.0 million, and AC of $2.5 million. The variance analysis identifies excessive welding rejects as the main cause. A new fixture and added inspector training were completed in the final week of May. Since then, only 1 of the next 6 planned weld lots has passed first inspection, and no baseline change has been approved. The control account manager wants to lower the EAC from $3.4 million to $3.0 million and state that the issue is fixed.
What is the best professional recommendation for the management report?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: Risk mitigation or corrective action can explain why performance may improve, but completion of the action does not by itself prove that future productivity or quality has changed. The past cost and schedule variance should remain visible because the rejects already occurred and affected EV and AC. The report should identify the mitigation, explain the limited evidence available after implementation, and avoid an unsupported EAC improvement. If subsequent lots show a sustained lower reject rate, the forecast can then be revised using objective post-mitigation performance data. AACE EVP analysis should protect variance traceability and forecast credibility rather than treating a corrective action plan as demonstrated recovery.
This separates the cause of past variance from evidence needed to support improved future performance and forecast credibility.
Topic: Revisions and Data Maintenance
At the June 30 data maintenance review, the control account manager for CA-132 disputes a new unfavorable cost variance and states that one material charge belongs to another WBS element. Which interpretation is best supported by the reconciliation evidence?
| Reconciliation item | Fact |
|---|---|
| EV report for CA-132 | PV = $550,000; EV = $530,000; AC = $610,000 |
| Accounting ledger for CA-132 | AC = $610,000, including voucher V-778 for $120,000 |
| Voucher V-778 support | PO and receiving report identify WBS 1.4.1; voucher charge code entered as CA-132 |
| Baseline change log | No approved June baseline changes for CA-132 |
| Schedule status package | Accepted status supports EV of $530,000 |
| Report interface log | June 30 ledger file loaded with no rejected records |
Best answer: C
What this tests: Revisions and Data Maintenance
Explanation: Reconciliation should trace a discrepancy to the source record that explains the mismatch. Here, the EV report and accounting ledger agree on the CA-132 actual cost, so the issue is not a report interface failure. The accepted status package supports the earned value, so the issue is not the physical progress status. The baseline log shows no approved baseline change, so revising the PMB would not address the disputed actual cost. The decisive evidence is the voucher support: the transaction was charged to CA-132 even though the PO and receiving report identify WBS 1.4.1. That points to an accounting coding correction, with an audit trail, rather than a baseline, status, accrual, or reporting change.
The voucher was charged to CA-132, while the purchase order and receiving evidence identify WBS 1.4.1.
Topic: Analysis and Management Reports
At the month-end review, the project controls manager is preparing the management report for Control Account 3.2. Which interpretation and action is best supported by the exhibit?
| Item | Status at data date |
|---|---|
| BAC | $2,000,000 |
| PV | $1,200,000 |
| EV | $1,020,000 |
| AC | $1,360,000 |
| Latest EAC | $2,450,000 |
| Variance threshold | Any cumulative CV or SV over 10% requires corrective-action reporting |
| Management reserve remaining | $300,000, released only for approved in-scope work |
| Change log note | Customer-requested test scope is pending change review; not yet authorized in the baseline |
| Forecast note | EAC includes $180,000 for the pending test scope |
Best answer: B
What this tests: Analysis and Management Reports
Explanation: The exhibit supports more than a simple overrun message. The control account has CV = EV − AC = $1,020,000 − $1,360,000 = -$340,000 and SV = EV − PV = $1,020,000 − $1,200,000 = -$180,000. Both exceed 10% of the relevant earned or planned value basis commonly used for variance review, so corrective-action reporting is required. The EAC also includes $180,000 for customer-requested test scope that is not yet authorized in the baseline. That forecast condition should be disclosed, not hidden. Management reserve should not be released for a pending customer scope change unless it is approved and meets the reserve-use rules. The appropriate management response is transparent reporting, corrective action for current performance, and formal change review for the pending scope.
The data exceed variance thresholds, and the forecast contains pending unauthorized scope that must be disclosed and handled through change control.
Topic: Analysis and Management Reports
At the month-end status date, the EV analyst is preparing the variance root-cause paragraph for a pipe installation control account. The control account manager wants one statement that management can use to target corrective action.
Which root-cause statement is most appropriate for the management report?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: A useful earned-value root-cause statement separates different drivers instead of collapsing them into one favorable or unfavorable label. Here, labor productivity is unfavorable because 1,120 hours were used for only 800 installed units against a 1.0 hour-per-unit standard. Material receipt affects actual cost timing, but the measurement method earns value only for verified installed units, not for material merely received. The subcontract effect is separate because the testing milestone earns no value until complete under its 0/100 rule. A professional management report should preserve these distinctions so corrective action can target labor execution, material cost timing or accrual interpretation, subcontract milestone recovery, and measurement-rule compliance without changing earned value to make the variance look better.
This statement separates productivity, material timing, subcontract status, and the measurement rules that determine earned value.
Topic: Analysis and Management Reports
At the month-end data date, a control account manager must integrate a reimbursable subcontract into the customer earned-value report. The subcontract budget at completion is $1,000,000. The approved measurement method earns $100,000 only when each deliverable is accepted by the buyer. Four of ten deliverables are accepted, two have been submitted but rejected for rework, and four have not been submitted. Accounts payable has paid and recorded $800,000 of approved subcontract invoices as actual cost. The subcontractor’s current, supportable forecast to complete all work is $1,150,000, and no baseline change has been approved. What is the best professional reporting action?
Best answer: C
What this tests: Analysis and Management Reports
Explanation: Subcontract payment status is not evidence of physical progress or earned value. In this case, the approved earning rule is acceptance-based, so only the four accepted deliverables earn budget: $400,000. The $800,000 paid and recorded by accounts payable is actual cost, not progress. The two rejected deliverables do not earn value until they meet the acceptance criteria. Because no baseline change is approved, the BAC remains $1,000,000; however, forecast data is not the same as baseline budget. A supportable subcontractor forecast of $1,150,000 should be reflected in EAC analysis and explained as a forecast overrun or performance issue.
Accepted deliverables drive earned value, paid invoices drive actual cost, the approved BAC remains the baseline, and the supportable forecast informs EAC.
Topic: Account Considerations
A control account’s approved budget includes direct labor plus applied indirect cost using the project’s approved overhead treatment. At the current status date:
The control account manager wants to report CPI using AC of 700,000 and update the EAC from that CPI. What is the best professional action?
Best answer: A
What this tests: Account Considerations
Explanation: Indirect costs must be treated consistently between the performance measurement baseline, actual-cost collection, and management reporting. If the approved budget includes applied overhead and prior reports included overhead in AC, using direct costs only in the current period would understate AC and overstate CPI. That distorted CPI would also drive an optimistic EAC if used as the forecasting basis. The professional action is to reconcile the accounting ledger and control-account report, include or allocate the related indirect cost on the same basis used for the budget and prior reporting, and then explain the variance using the corrected data. A separate note alone does not fix the analytical distortion, and management reserve is not a place to park normal indirect actual costs.
CPI, EAC, and variance analysis must use a cost basis consistent with the budget and prior actual-cost treatment.
Topic: Communication Competency
An EVP is reviewing a brief status memo for a program sponsor who is not an EVMS specialist and must decide whether to authorize recovery funding next week.
Which draft statement is LEAST suitable for the sponsor memo?
Best answer: D
What this tests: Communication Competency
Explanation: Professional EVMS communication should be factual, evidence-backed, audience-appropriate, and clear about what is known versus unresolved. The supplied data support a simple message: EV is less than PV, indicating schedule performance weakness, and AC is greater than EV, indicating cost performance weakness. The documented driver is the late design release. However, the pending change request and possible missing accrual are not yet approved or reconciled, so they should not be used to dismiss the variance or promise recovery. A sponsor memo should clarify the decision need without burying the message in technical detail or overstating certainty.
This statement is unsupported and inconsistent with the facts because the change is not approved and the accounting impact is still unresolved.
Topic: Revisions and Data Maintenance
A project has an approved baseline change after the October status update. The customer performance report is due in two business days, and the draft report was prepared before the change-control board decision.
| Change-control fact | Status |
|---|---|
| Change request | CR-108 approved on October 29 |
| Scope effect | Adds qualification test support to WBS 3.2.4 |
| Responsibility effect | WBS 3.2.4 moves from Engineering CAM to Test CAM effective October 30 |
| Budget effect | $240,000 of management reserve is allocated to the Test control account |
| Data issue | $36,000 of October actual costs are still charged to the old Engineering control account |
| Draft customer report | Omits CR-108 and shows the pre-change reserve balance |
Which communication is most appropriate before the customer report is released?
Best answer: B
What this tests: Revisions and Data Maintenance
Explanation: An approved change that changes control-account responsibility and uses management reserve is not just a forecasting note. It changes the maintained baseline structure and must be communicated to the people who control the work, record actual costs, and prepare customer-facing performance data. The communication should identify the approved change, the effective responsibility transfer, the management reserve allocation, the need to reconcile actual costs charged to the old control account, and the required disclosure in the customer report. This preserves traceability between the change log, RAM/control-account structure, accounting records, reserve balance, and reported baseline. It also avoids misstating performance by treating a baseline revision as a variance recovery or by leaving the customer with obsolete reserve and responsibility information.
The approved change affects control-account ownership, management reserve, accounting traceability, and the customer report, so all affected parties need a clear baseline-maintenance communication.
Topic: Revisions and Data Maintenance
At the April 30 status close, project controls prepared this reconciliation note for Control Account 3.2 before issuing the monthly customer earned value report and updating the EAC. The contract requires customer reports to reconcile the baseline, status, and accounting data as of the data date.
| Area | Reconciliation note |
|---|---|
| Baseline | PMB agrees with the approved change log through CR-18; pending trend T-07 is excluded. |
| Schedule/status | 38 of 40 work packages have objective completion evidence; two late test work packages were set to EV = PV pending CAM status. |
| Accounting | General ledger is closed through Apr 30 and accruals are posted; USD 95,000 of supplier labor was charged to CA 3.1, with a correcting journal approved but not posted until May. |
| Report file | Draft report manually moves the USD 95,000 to CA 3.2 and shows CPI of 0.92. |
| Forecast | EAC uses the draft AC and prior-month ETC; the supplier delay behind the two test packages is not included in ETC. |
Which professional judgment is best supported by the exhibit?
Best answer: A
What this tests: Revisions and Data Maintenance
Explanation: Reliable reconciled earned value data must be traceable across the approved baseline, objective status, accounting actuals, and forecast assumptions. The baseline treatment is sound because the pending trend is excluded, but the other exceptions are material. Setting EV equal to PV without objective CAM status weakens physical progress credibility. Manually moving USD 95,000 in the report before the accounting correction posts creates a traceability gap between the report and the general ledger. Using a prior-month ETC while a supplier delay has already affected the test work packages makes the EAC incomplete. The appropriate professional judgment is to hold the final customer report and forecast update, or clearly qualify internal analysis, until the missing status evidence, posted accounting correction or approved reconciliation trail, and updated ETC are available.
Unsupported EV, an unposted accounting correction, and a stale ETC prevent the reconciled data from supporting final reporting or forecast update.
Topic: Perform Planning and Scheduling Duties
During baseline planning for an EVMS-controlled development project, the control account manager defines a work package as: “Perform vibration qualification test for the pump skid and issue the approved test report.” The requirement allocated to the work package is vibration not to exceed 0.25 in/sec RMS at three specified operating points. Earned value for the work package will be claimed only when objective completion evidence is available. The proposed technical performance measure is: “Pump skid vibration performance is acceptable based on engineering judgment.” What is the best professional action?
Best answer: A
What this tests: Perform Planning and Scheduling Duties
Explanation: A technical performance measure used for earned-value planning should describe the required technical outcome in objective terms and tie it to the work package definition. Here, the work package is limited to performing a vibration qualification test and issuing an approved test report. The allocated requirement already provides measurable criteria: a maximum vibration value at three operating points. The best action is to define the measure around those observed test results and the approved report. Subjective judgment, labor consumption, or broader reliability outcomes would not provide the same direct, auditable evidence of completing the authorized work package.
This makes the measure specific, measurable, and directly aligned with the work package scope and completion evidence.
Topic: Analysis and Management Reports
At the current status date, a control account has BAC = $4,000,000, EV = $1,600,000, and AC = $1,950,000. The cumulative CPI is 0.82, but the last three reporting periods after a documented methods change have CPIs of 0.97, 1.01, and 0.99. The remaining work is repetitive installation work using the corrected method, and there is no approved scope change or baseline revision. Management needs a defensible EAC for the monthly customer report. What is the best forecasting approach?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: EAC should reflect both actual performance already incurred and the most credible assumption for the remaining work. Here, the early adverse cost performance is real and remains in AC. However, the scenario states that a documented methods change has produced stable recent CPI near 1.0 and that the remaining work is repetitive installation using that corrected method. A defensible approach is therefore to calculate ETC from the recent demonstrated performance rate for the remaining work and add it to AC. This avoids overstating future inefficiency by blindly extending the old cumulative CPI, while also avoiding the improper removal of historical cost variance.
The remaining work is expected to follow the corrected recent trend, while the prior overrun must remain captured in AC.
Topic: Revisions and Data Maintenance
During the May closeout review, the project controls analyst finds that April actual costs of $85,000 were posted to the wrong control account. The accounting manager confirms the cost belongs to the same contract but to a different control account. The April customer report has already been issued, and there is no approved scope or budget change. Which documentation package best supports correcting the May EVMS database without obscuring April performance history?
Best answer: B
What this tests: Revisions and Data Maintenance
Explanation: A prior-period correction should be supported by evidence that shows what was wrong, who authorized the correction, what values changed, and how the change affects previously reported and current cumulative performance. Because the April report was already issued and no scope or budget change exists, the correction should not be treated as a baseline revision or used to erase the original performance history. The proper package preserves the audit trail between accounting records, control account actual costs, and management reporting. It also gives stakeholders a transparent explanation of the prior-period effect so current CPI, CV, EAC, and variance narratives can be interpreted correctly.
This supports the accounting correction while preserving traceability to the original reported period and explaining the effect on performance data.
Topic: Revisions and Data Maintenance
During month-end reconciliation for the June 30 earned-value report, the EV analyst finds:
What is the best action before the report is issued?
Best answer: A
What this tests: Revisions and Data Maintenance
Explanation: Reconciliation should protect the integrity of the current report and the control process. The accrual was valid for the June cutoff, so AC must be corrected from $820,000 to $1,060,000. With EV of $900,000, CV becomes -$160,000, which exceeds 10% of EV and triggers the required variance narrative. Because the PMB and physical progress are verified, this is not a baseline or earned-progress problem. The failed interface map is a process issue, so it should be escalated to the roles named in the procedure for correction and recurrence prevention. Since the customer report has not yet been submitted, issuing the corrected report is preferable to sending known inaccurate performance data.
The reconciliation identifies a valid actual-cost omission that changes reportable performance and also exposes a process defect requiring correction.
Topic: Analysis and Management Reports
At the June 30 status date, a subcontract control account has a BAC of $1,000,000 for five identical skid assemblies. The approved EV rule earns $200,000 only when an assembly passes technical acceptance; no partial EV is earned for installed but unaccepted work. The baseline planned four accepted assemblies by June 30.
Cumulative records show:
Using SV = EV - PV and CV = EV - AC, what should be reported for subcontract performance?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: Subcontractor progress should be integrated using objective accomplishment evidence that matches the approved earned value technique. The plan allows $200,000 of EV only for each assembly that passes technical acceptance. By the status date, three assemblies have been accepted, so EV is $600,000. The baseline planned four accepted assemblies, so PV is $800,000. Actual cost is the accrued $760,000 from the cost record. Therefore, SV = $600,000 - $800,000 = -$200,000, and CV = $600,000 - $760,000 = -$160,000. The professional response is to report both schedule and cost performance concerns and require variance analysis and forecast review, especially because one installed assembly failed acceptance.
Earned value is based on the three technically accepted assemblies, not the subcontractor’s self-reported percent complete or the accrued cost.
Topic: Analysis and Management Reports
At the 30 June status date, a control account has these cumulative values:
| Measure | Value |
|---|---|
| BAC | $1,500,000 |
| PV | $900,000 |
| EV | $810,000 |
| AC | $870,000 |
Additional facts:
Use CV = EV - AC and EAC = AC + ETC. Which management-report statement best interprets the mitigation-related information?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: A planned mitigation activity is a risk response action, not automatically a variance explanation, baseline change, reserve transfer, or forecast adjustment. Here, the $45,000 mitigation was already authorized, budgeted in the PMB, and completed as planned, so it should remain in AC and be described as executed mitigation. The current cost variance is EV - AC = $810,000 - $870,000 = -$60,000. The stated cause of the performance shortfall is lower weld productivity. The forecast effect is separate: the remaining work is expected to cost $30,000 more than the remaining baseline budget, so that belongs in EAC/ETC analysis. Because no baseline change or management reserve transfer has been approved, the report should not revise BAC or move reserve to improve the variance picture.
The mitigation was authorized and completed as planned, while the unfavorable cost variance and higher EAC are driven by performance and forecast data, not by an approved baseline or reserve action.
Topic: Account Considerations
A control account manager is preparing the April 30 earned value status for CA-240. The measurement rule earns budget only for assemblies accepted by quality inspection by the status date.
| CA-240 status item | Amount or quantity |
|---|---|
| Cumulative planned units through April 30 | 450 assemblies |
| Budget per accepted assembly | $1,000 |
| Assemblies accepted by April 30 | 400 assemblies |
| Assemblies delivered May 2, not accepted by April 30 | 30 assemblies |
| Direct costs posted to CA-240 ledger | $360,000 |
| April subcontract work accepted but not yet posted; accrual required | $70,000 |
| Cost posted to CA-240 but documented as another control account’s work | $20,000 |
Which interpretation is best supported by the exhibit?
Best answer: A
What this tests: Account Considerations
Explanation: Earned value reporting must align the baseline, physical status, and actual cost cutoff for the same control account and status date. Planned value comes from the approved time-phased baseline: 450 planned assemblies at $1,000 each, or $450,000. Earned value follows the stated measurement rule, so only 400 quality-accepted assemblies earn budget, or $400,000; May 2 deliveries are outside the April 30 cutoff and were not accepted. Actual cost must be reconciled to the work performed for the control account at the same cutoff. The posted $360,000 is incomplete because accepted April subcontract work requires a $70,000 accrual, and it is overstated by a $20,000 mischarge belonging to another control account. The reconciled AC is therefore $410,000.
The status date, acceptance rule, accrual, and mischarge support PV of 450 units, EV of 400 accepted units, and AC of $360,000 + $70,000 - $20,000.
Topic: Organizing
A project team is building the EVMS control structure for a fixed-scope engineering and fabrication contract. The approved WBS is deliverable-oriented, and management wants the OBS finalized before the responsibility assignment matrix is baselined.
Constraints:
Which OBS structure is the best professional choice?
Best answer: C
What this tests: Organizing
Explanation: In an earned value control structure, the WBS defines the scope of work, while the OBS defines the organizations accountable for performing that work. The responsibility assignment matrix then connects the two, typically creating control accounts at the intersection of a WBS element and a responsible organization. Because the contract already has a deliverable-oriented WBS and the accountable budget and actual-cost owners are Engineering, Procurement, Fabrication, and Test, the OBS should be organized around those performing organizations. Customer reporting by deliverable can still be achieved through the WBS and reporting structure, but it should not redefine organizational accountability. A staffing list may support work authorization and resource planning, but it is too granular and unstable to serve as the OBS for accountable organizational ownership.
The OBS should identify responsible organizations so the RAM can link accountable ownership to WBS scope without turning deliverables into organization names.
Topic: Analysis and Management Reports
A prime contractor is preparing the monthly customer earned-value report and the management EAC review. The largest subcontractor submitted the following status package for the same data date.
| Item | Subcontractor submission | Prime verification |
|---|---|---|
| BAC for subcontract work | $4,000,000 | $4,000,000 |
| PV at data date | $2,400,000 | $2,400,000 |
| EV claimed | $3,000,000 | $2,200,000 accepted physical progress |
| AC reported | $2,100,000 cash paid | $2,650,000 including accrued received material |
| EAC submitted | $4,000,000 | Productivity trend supports $4,700,000 |
| Change status | $300,000 request included in subcontractor narrative | Not approved or in baseline |
Which interpretation is best supported before integrating the subcontractor data into the customer report and management forecast?
Best answer: C
What this tests: Analysis and Management Reports
Explanation: Subcontractor performance data must be traceable to objective progress, compatible actual-cost cutoff rules, and a credible forecast basis before it is integrated into customer reporting or management EAC decisions. Here, the subcontractor claimed EV of $3,000,000, but the prime verified only $2,200,000 of accepted physical progress. The reported AC is cash paid, not the accrual-based cost of work and received material, so it understates actual cost for earned-value analysis. The EAC remains at BAC even though the verified trend supports $4,700,000, and the subcontractor narrative includes a pending change that is not approved or in the baseline. The professional response is to reconcile and qualify the data, not to report favorable metrics that are unsupported by objective evidence.
The exhibit shows unsupported EV, incomplete AC, an unchanged EAC despite adverse productivity, and a pending change treated as if it were approved.
Topic: Analysis and Management Reports
At the May status date, a control account shows PV of $2,400,000, EV of $2,000,000, and AC of $2,100,000. The schedule variance exceeds the reporting threshold. The control account manager’s draft narrative says, “Supplier delay is being mitigated by expediting; no further management action is needed.”
Reporting constraints:
TBD and no response status.What is the best professional action before issuing the report?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: Mitigation reporting must be traceable to evidence, not just activity. In this case, the variance is real and above threshold, but the claimed mitigation is unsupported. The cause is not clear, the risk owner is not assigned, the response status is blank, and residual exposure remains because the schedule still shows a three-week delay with no accepted recovery date. The appropriate action is to report the variance transparently and require a corrected analysis before describing the mitigation as effective. Starting an expediting purchase order may be a response activity, but it does not prove recovery or define remaining risk exposure.
The mitigation claim is not supportable because the required cause, ownership, response status, and remaining exposure are not yet evidenced.
Topic: Analysis and Management Reports
At the April status date, the project controls lead is preparing the variance narrative for a mechanical control account. The control account manager provided this excerpt:
| Item | Current status |
|---|---|
| BAC | $4,000,000 |
| PV | $1,600,000 |
| EV | $1,360,000 |
| AC | $1,520,000 |
| Approved baseline changes this period | None |
| Management reserve movement | None |
| Current EAC | $4,120,000 |
Which interpretation is best supported for the management report?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: A mitigation action is a planned response intended to reduce the probability or impact of a future risk. It should not be confused with the explanation for a variance that has already occurred. Here, the current schedule and cost variances are explained by late vendor drawings and overtime. The proposed extra fit-up inspection is a forward-looking action to reduce the chance of weld rework next month. The exhibit also states that there were no approved baseline changes and no management reserve movement, so the report should not imply a baseline revision or reserve transfer. The EAC has already been stated separately; the mitigation note supports risk and recovery discussion, but it is not itself proof of a baseline change or a different variance cause.
The exhibit identifies the inspection as a future risk response, while the actual variance causes are late drawings and overtime.
Topic: Perform Budgeting Duties
A control account work package has a budget at completion (BAC) of USD 180,000 to install and acceptance test 90 identical supports. The approved performance measurement rule is:
\(EV = (\text{accepted installed supports} / 90) \times \text{BAC}\)
At the status date, 45 of 60 planned workdays have elapsed, USD 110,000 of actual cost has been recorded, 36 supports are installed and accepted, and 9 additional supports are fabricated but not installed. Which interpretation best protects the earned value baseline for this status report?
Best answer: B
What this tests: Perform Budgeting Duties
Explanation: Earned value should reflect objective accomplishment under the approved measurement rule, not effort consumed. The accepted installed support count is 36 out of 90, so EV is \(36/90 \times 180{,}000 = \text{USD }72{,}000\). Using actual cost as progress would set EV equal to USD 110,000 and reward spending. Using elapsed time would report \(45/60 \times 180{,}000 = \text{USD }135{,}000\) and reward calendar passage. Both would make performance look better than the completed accepted work supports and could distort variance analysis and forecasts. Fabricated but uninstalled supports also do not meet the stated acceptance criterion.
The approved rule earns value only for accepted installed supports, so spending or elapsed time would overstate accomplishment.
Topic: Revisions and Data Maintenance
At the June 30 status cutoff, a project has an approved customer change that adds a new deliverable. The change was authorized on June 28, but the added work is scheduled to start in July.
Current reported values before incorporating the change:
| Measure | Value |
|---|---|
| BAC | $2,000,000 |
| PV | $1,000,000 |
| EV | $900,000 |
| AC | $950,000 |
| EAC | $2,100,000 |
Constraints:
What is the best professional action for the June report?
Best answer: C
What this tests: Revisions and Data Maintenance
Explanation: An approved scope change should be incorporated through disciplined baseline revision, using the authorized budget for the added work. Because the added work has not started and has no actual cost before the June 30 cutoff, current cumulative PV, EV, and AC for June should not be increased. Earned value is based on objective accomplishment, not approval of scope. The baseline BAC increases from $2,000,000 to $2,250,000. The forecast should also reflect the control account manager’s expected cost for performing the added scope, so EAC increases from $2,100,000 to $2,375,000. That produces a forecast overrun against the revised BAC, rather than hiding the impact by changing history or replacing budget with forecast cost.
The approved change increases the baseline budget for future authorized work, while the forecast must include the expected $275,000 cost without restating earned value history.
Topic: Perform Budgeting Duties
A control account covers installation and acceptance testing of 100 identical field devices. The authorized budget at completion (BAC) is $200,000. The approved plan is to complete 20 devices in Month 1, 30 in Month 2, 25 in Month 3, and 25 in Month 4. Earned value is to be based on devices accepted by quality control. At the end of Month 2, 35 devices have been accepted and accrued actual cost (AC) is $90,000.
Use: PV = planned accepted devices / total devices × BAC; EV = accepted devices / total devices × BAC; EAC if current cost efficiency continues = BAC / CPI.
Which baseline structure and status interpretation best supports objective progress measurement, variance analysis, and forecast-at-completion reasoning?
Best answer: C
What this tests: Perform Budgeting Duties
Explanation: A performance measurement baseline should be time-phased and tied to objective accomplishment criteria. Here, the approved plan calls for 50 devices by the end of Month 2, so PV is $100,000. Only 35 devices are accepted, so EV is $70,000. With AC of $90,000, CPI is $70,000 / $90,000 = 0.78. If that cost efficiency continues, EAC is approximately $200,000 / 0.78 = $257,000. This structure reveals both the physical progress shortfall and the unfavorable cost efficiency, while supporting a credible forecast-at-completion discussion.
The unit-based, time-phased baseline ties planned value and earned value to objective acceptance evidence and supports variance and EAC analysis.
Topic: Analysis and Management Reports
A prime contractor is preparing the March subcontract performance input for a customer EVMS report. The subcontract is a fixed-price design package within one control account.
| Item | March status |
|---|---|
| Subcontract BAC | $500,000 |
| EV method | Accepted milestones only: 30% preliminary design, 40% IFC drawings, 30% test report |
| Planned by March 31 | Preliminary design and IFC drawings accepted |
| Objective evidence | Preliminary design accepted; IFC drawings returned revise/resubmit; test report not started |
| Subcontractor submission | Reports 80% complete and invoices $400,000 |
| Contract/accounting note | Payment and cost booking require accepted milestone support or an approved accrual package |
Which action best supports the March EVMS report?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: Subcontract performance must be integrated using the authorized measurement method and objective evidence, not unsupported status claims or invoice amounts. The milestone method earns value only when the defined milestone is accepted. As of March 31, only the preliminary design milestone has been accepted, so EV is 30% of $500,000, or $150,000. The IFC milestone is late and not accepted, so it should not earn value. The invoice cannot be treated as earned progress, and the accounting note requires accepted milestone support or an approved accrual package before cost booking. The appropriate management action is to report the supported EV, reconcile or hold unsupported cost treatment through accounting, and obtain objective status and a recovery forecast for the late subcontract deliverable.
Only the accepted 30% milestone supports earned value, while the unsupported invoice and late deliverable require reconciliation and subcontract management action.
Topic: Analysis and Management Reports
A control account status report dated 30 June shows BAC $2,000,000, PV $1,200,000, EV $1,000,000, and AC $1,300,000. The variance analysis attributes 70% of the $300,000 unfavorable cost variance to field rework caused by revised engineering drawings being released after fabrication started.
Management requires the mitigation plan to address the documented root cause, reduce residual cost exposure to no more than $75,000, and include measurable follow-up for the next monthly report. Residual cost exposure is calculated as residual probability × remaining potential cost impact.
Which mitigation plan should be reported as best meeting management’s requirement?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: A mitigation plan is credible only if it connects the variance cause to a control action, quantifies the remaining exposure, and defines how management will know whether the action is working. The unfavorable cost variance is driven mainly by rework caused by late engineering drawing releases. A release gate before fabrication directly addresses that cause. Its residual exposure is 20% × $300,000, or $60,000, which is below the $75,000 management limit. The proposed follow-up measures also link to the cause and effect: approved releases before fabrication and weekly rework hours. A plan that merely spends overtime, reserves funds, or adds downstream inspection may be useful for recovery or detection, but it does not adequately prevent recurrence of the documented root cause.
This plan targets the late drawing-release root cause, leaves residual exposure below the $75,000 limit, and defines measurable follow-up indicators.
Topic: Perform Budgeting Duties
At the August 31 status date, a control account manager is preparing the earned value status for a material-heavy work package.
| Item | Status information |
|---|---|
| Work package budget | $120,000 in the approved performance measurement baseline |
| Earned value rule | 50% earned when valves are received onsite; 50% earned when installation is accepted |
| Physical status | Valves received onsite; installation has not started |
| Purchase order commitment | $150,000, including future vendor installation support |
| Supplier invoice recorded | $90,000 for received valves |
| Accounting accrual | $42,000 for received valves not yet invoiced |
| Cash paid | $60,000 |
Which interpretation is best supported for the earned value status report?
Best answer: C
What this tests: Perform Budgeting Duties
Explanation: Budgeted cost of work performed, or earned value, is the budget value assigned to objectively accomplished scope. Here, the approved budget is $120,000 and the earning rule grants 50% when the valves are received onsite, so earned value is $60,000. Actual cost is not the same as budget, commitment, invoice alone, or cash paid. For earned value reporting, actual cost should reflect the cost incurred for the work performed at the status cutoff. The received valves have $90,000 recorded by invoice and $42,000 recognized by accrual, so actual cost is $132,000. The $150,000 purchase order is a commitment that includes future support, and the $60,000 cash payment is a settlement activity, not a measure of earned progress.
The budgeted cost of work performed is based on the 50% earning rule, while actual cost includes the invoice plus accrual for received work.
Topic: Organizing
During an internal EVMS readiness review, the project controls lead finds that the WBS coding in the scheduling tool does not match the control account structure in the responsibility assignment matrix. The contract requires monthly earned-value reporting by contract WBS level 3, and each control account must be traceable to a single WBS element and accountable manager. The baseline scope and budget are approved, but no scope change has been authorized. Actual costs for two deliverables are currently being collected under one shared charge code. What is the best corrective action?
Best answer: D
What this tests: Organizing
Explanation: When WBS coding does not align with control accounts or contract reporting needs, the corrective action should restore traceability without changing the approved baseline unless an authorized change exists. In an EVMS, each control account should connect the contract WBS scope, responsible organization or CAM, authorized work, schedule activities, budget, earned value, and actual costs. A shared charge code across two WBS deliverables creates actual-cost ambiguity and weakens variance analysis. The best action is to correct the coding relationships across the RAM, work authorization, schedule, and accounting interface, then reconcile any affected actual costs with an audit trail. This supports contract reporting and preserves baseline integrity.
This preserves the approved scope and budget while restoring traceability among WBS scope, control accounts, responsibility, and actual costs.
Topic: Perform Planning and Scheduling Duties
A control account manager is finalizing the earned value measurement method for a discrete work package in the baseline. The work package produces testable hardware units, and the customer has asked how progress will be supported at each status date.
| Work package fact | Current evidence |
|---|---|
| Scope | Build and qualify 8 interface modules |
| Technical requirement | Each module must pass an approved functional test |
| Acceptance evidence | Signed test report and quality release per module |
| Status date data | 70% of planned labor hours charged; 5 modules assembled; 3 modules have signed test reports |
Which measurement approach best supports earned value based on work accomplished?
Best answer: C
What this tests: Perform Planning and Scheduling Duties
Explanation: For discrete earned value work, progress should be measured against objective accomplishment criteria established in the plan. The exhibit shows that technical completion is not merely assembly or labor consumption; each module must pass an approved functional test and have a signed quality release. Therefore, earned value should be credited only when those measurable events occur, either as completed units or as weighted milestones if the baseline defines interim objective steps. Labor hours charged may explain cost performance, but they do not prove technical accomplishment. Similarly, assembled-but-untested modules may represent work in process, not earned completion, unless the measurement plan assigns objective interim credit to assembly with defined evidence.
Signed test reports and quality releases provide objective technical evidence that discrete work has been accomplished.
Topic: Organizing
At the May status cutoff, a control account manager reports 15% earned value on an installation interface work package. The interface activity is still in a draft change proposal, the customer has not approved it, the performance measurement baseline contains no budget or schedule for it, and no signed work authorization has been issued. Labor charges have already begun against a general support code. Which action best prevents performance measurement on unauthorized or prematurely started work?
Best answer: D
What this tests: Organizing
Explanation: Work authorization is the control that links approved scope to responsible ownership, budget, schedule, and cost collection before work is released for earned-value measurement. In this case, the activity is not yet authorized scope: the change is only in draft, the PMB has no budget or schedule for it, and no signed authorization exists. Labor that has already occurred should remain traceable for accounting and change evaluation, but it should not create earned value or baseline budget. Opening earned-value credit before authorization would blur scope control, misstate progress, and potentially hide out-of-scope work inside approved performance data.
This protects baseline integrity by allowing performance measurement only after scope, responsibility, budget, schedule, and cost collection are formally authorized.
Topic: Organizing
A project is establishing its responsibility assignment matrix before releasing work authorization for a major equipment installation. The WBS is deliverable-oriented, the accounting system can collect actual costs only when a unique charge number is assigned, and monthly earned-value reports must support corrective action by the responsible manager. Two functional departments will perform work within the same deliverable. Which organizational assignment best supports control-account ownership, actual-cost collection, and management action?
Best answer: B
What this tests: Organizing
Explanation: In an earned value management structure, a control account should be positioned where authorized scope and organizational responsibility intersect. Assigning one accountable control account manager supports clear performance responsibility, timely corrective action, and traceable variance analysis. Because the accounting system requires unique charge numbers to collect actual costs, those charge numbers must align with the authorized control-account scope rather than a shared or informal collection point. Functional departments may support the work, but shared ownership weakens accountability and can obscure who must explain variances or implement recovery actions.
This establishes clear single-point ownership while preserving traceability from authorized scope to actual costs and management action.
Topic: Analysis and Management Reports
A control account has cumulative PV of $4.8 million, EV of $4.0 million, and AC of $5.0 million at the status date, giving a CPI of 0.80. The remaining budget is $6.0 million: $4.0 million for a material package now covered by firm supplier quotes and $2.0 million for installation labor using the same crew and methods as the completed work. The variance analysis shows the poor CPI was partly caused by a start-up rework issue that has been closed. The approved baseline has not changed, and accounting data have been reconciled. What is the best way to prepare the EAC for management reporting?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: Current CPI is important evidence, but it should not be applied mechanically to all remaining work when the remaining scope has different cost drivers or when conditions have changed. Here, the remaining work includes a material package supported by firm supplier quotes and installation labor that may still be affected by the demonstrated productivity trend. A credible EAC should segment the ETC, use the best available evidence for each segment, and document assumptions. The approved baseline remains the basis for measuring performance; the forecast is updated to reflect expected final cost, not to rewrite history or hide variances.
The forecast should reflect changed conditions and apply performance trends only where they are representative of the remaining work.
Topic: Account Considerations
As of the August 31 status date, Control Account 2.4 is being reconciled for the monthly earned value report. Use cumulative values through August 31 unless noted.
| Item | Amount |
|---|---|
| Planned value (PV) | $300,000 |
| Earned value (EV) | $250,000 |
| Actual cost posted to the ledger | $210,000 |
Additional reconciliation facts:
For this report, actual cost includes incurred costs through the status date, including accruals for work performed, and excludes unreceived commitments and customer cash receipts. Cost variance is calculated as \(CV = EV - AC\).
What is the best management reporting conclusion for August 31?
Best answer: D
What this tests: Account Considerations
Explanation: At a status cutoff, actual cost should reflect costs incurred for authorized work performed through the status date. The missing labor was performed by August 31, so it should be accrued to the control account: $210,000 posted AC + $70,000 labor accrual = $280,000 reconciled AC. With EV of $250,000, the cost variance is -$30,000. The control issue is not a baseline change, reserve use, or payment matter; it is a cutoff and accounting reconciliation problem that affects the accuracy of the control-account status. The September-effective change may affect a later baseline, the unreceived purchase order is only a commitment, and the customer payment is cash flow rather than actual cost.
The unposted labor was incurred before the status date, so AC should be $210,000 + $70,000 = $280,000 and CV should be $250,000 - $280,000 = -$30,000.
Topic: Revisions and Data Maintenance
At the May status cutoff, the project controls analyst finds that April actual costs were posted to the wrong control account. The April customer performance report has already been issued, and the accounting system corrected the posting in May. The contract reporting procedure requires traceability of prior submitted values and explanations for any prior-period adjustments. The control account manager asks the analyst to overwrite the April report file so the historical trend chart “looks clean.” What is the best professional action?
Best answer: C
What this tests: Revisions and Data Maintenance
Explanation: When a prior-period error is discovered after a report has been issued, disciplined data maintenance should preserve the original submitted record and maintain a clear audit trail. The accounting correction still needs to be reflected, but it should be documented as a prior-period adjustment or reconciliation item according to the reporting procedure. Overwriting historical records without explanation destroys traceability and can make variance trends, customer reports, and EVMS surveillance evidence unreliable. The appropriate action is transparent correction, not silent replacement. This protects data integrity while allowing management to understand the effect of the corrected actual cost posting.
This preserves prior-period traceability while transparently reconciling the accounting correction in the current reporting cycle.
Topic: Revisions and Data Maintenance
At the April month-end close, the project controls analyst finds a reconciliation difference after the March customer report has already been issued.
What is the best data maintenance action?
Best answer: A
What this tests: Revisions and Data Maintenance
Explanation: When a prior-period accounting error is discovered after an issued earned-value report, data maintenance should correct the record without erasing history. The supporting evidence identifies a real March labor accrual and an accounting correction voucher, so the actual cost data should be corrected. However, because the March report was already issued and the procedure requires traceability and disclosure, the correction should preserve the original reported values, retain source references, and explain the cumulative impact in the next report. There is no approved baseline change, so changing the budget would compromise baseline integrity. The professional control concern is not merely getting the database number to match; it is maintaining a clear audit trail from source accounting evidence through reported earned-value impacts.
This preserves the audit trail while correcting traceable actual-cost data and explaining the impact of the prior-period correction.
Topic: Analysis and Management Reports
At the 30 June status review, a control account has BAC of $1,200,000, EV of $800,000, and AC of $920,000. The remaining authorized critical-path work is 4,000 EV-hours, and the contractual milestone is due in 6 weeks. Use:
The current plan finishes in 8 weeks with an ETC of $420,000. The customer needs a recovery decision by 5 July. The program manager can approve up to $75,000 of incremental recovery cost before that date; anything higher requires a change board on 20 July, which is too late for the customer decision. No scope reduction has been approved.
| Alternative | Timing and production | ETC |
|---|---|---|
| Continue current plan | No lead; 500 EV-hr/week | $420,000 |
| Existing-team overtime | No lead; 675 EV-hr/week | $472,000 |
| Subcontract critical work | 2-week lead; 1,050 EV-hr/week | $565,000 |
| Defer verification work | No lead; 500 EV-hr/week on 3,000 EV-hr | $315,000 |
Which recommendation best balances recovery feasibility, remaining work, cost exposure, and stakeholder decision timing?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: The best management recommendation must consider both numeric feasibility and governance timing. Continuing the current plan has an EAC of $1,340,000, but it finishes in 8 weeks, which misses the 6-week milestone. Existing-team overtime finishes in 4,000 / 675 = about 5.9 weeks, with EAC of $1,392,000 and an incremental recovery cost of $52,000 over the current plan, which is within the $75,000 immediate approval limit. The subcontract alternative also appears schedule-feasible at about 5.8 weeks including mobilization, but its incremental cost is $145,000, requiring a later change board that misses the customer decision window. Deferring verification work is not a valid recovery basis because no scope reduction has been approved. The professional recommendation is therefore the feasible recovery action that preserves authorized scope and supports timely stakeholder action with controlled cost exposure.
Overtime meets the 6-week need, adds only $52,000 versus the current plan, and can be approved before the customer decision date.
Topic: Perform Planning and Scheduling Duties
At the May status update, the scheduler is validating the CPM forecast used for earned-value planning. The project calendar uses workday numbers, all listed relationships are finish-to-start with zero lag, and no baseline change has been approved.
| Item | Value |
|---|---|
| Status date | End of workday 40 |
| Baseline completion milestone | End of workday 70 |
| Remaining critical-path activity A | 8 workdays |
| Remaining critical-path activity B | 12 workdays |
| Remaining critical-path activity C | 14 workdays |
| Total float on this path after status | 0 workdays |
What schedule implication is supported by the exhibit?
Best answer: B
What this tests: Perform Planning and Scheduling Duties
Explanation: For CPM schedule interpretation, compare the remaining duration on the driving path with the workdays available to the baseline completion milestone. The path has 8 + 12 + 14 = 34 workdays remaining. From the end of workday 40 to the end of workday 70, only 30 workdays are available. Therefore, the current forecast completion is workday 74, creating a 4-workday negative schedule implication against the baseline milestone. In an earned-value environment, this should be reported as a forecast schedule delay and used to support recovery planning or change-control evaluation. The performance measurement baseline should not be revised merely to match a forecast unless an approved baseline change exists.
The remaining critical-path duration is 34 workdays from workday 40, which forecasts completion at workday 74 versus the baseline milestone at workday 70.
Topic: Analysis and Management Reports
A project controls analyst discovers a status-data error while preparing the March earned-value report. The control account uses monthly current-period and inception-to-date cumulative performance measures.
| Fact | Status |
|---|---|
| Status date | March 31 |
| Error found | A completed February milestone was not loaded into the February status file |
| Objective evidence | Customer acceptance dated February 24 |
| Earned value affected | $120,000 EV omitted from February |
| Actual cost treatment | Related actual costs were already recorded in February AC |
| Baseline/change status | No approved baseline change; March work status is otherwise correct |
Which status-data correction best preserves comparability between current-period and cumulative performance measures?
Best answer: C
What this tests: Analysis and Management Reports
Explanation: Current-period measures should represent performance that occurred in the current reporting period, while cumulative measures should reflect all valid performance through the status date. The exhibit shows that the milestone was completed and accepted in February, and that the related actual costs were already captured in February. Treating the omitted EV as March progress would overstate March current-period performance and distort trend comparisons. The disciplined correction is to process a prior-period status correction with an audit trail, update inception-to-date EV, and show the adjustment separately so management can compare March performance to March PV and AC without mixing in a February accomplishment.
This preserves March current-period performance while making cumulative EV accurate and traceable to the February accomplishment evidence.
Topic: Perform Planning and Scheduling Duties
At the 31 May status date, a critical-path installation control account has these schedule facts:
Use: remaining duration = remaining quantity / current production rate.
Which interpretation should the controls analyst give the control account manager?
Best answer: B
What this tests: Perform Planning and Scheduling Duties
Explanation: A risk is an uncertain future event; an issue is a condition that has already occurred and now requires management action. Here, the physical progress shortfall is already present: planned quantity was 8,000 ft, but only 6,000 ft was accepted, producing earned value of $300,000 versus planned value of $400,000. More importantly for scheduling, 4,000 ft remain and the current rate of 1,500 ft per workweek gives 2.67 workweeks of remaining duration. Only two workweeks remain to the 14 June baseline finish. That makes the schedule impact current and forecastable, not merely a future uncertainty. The weather item may remain a risk, but it is not the primary classification for the existing production shortfall.
The work is already behind the plan and the current production rate forecasts completion about 0.67 workweek after the required baseline finish.
Topic: Analysis and Management Reports
A contractor is preparing the monthly earned value customer report for a control account on a flight-test support contract. The customer program manager has asked that the report identify the management decision needed, not just restate variances.
| Status item | Evidence at 30 June |
|---|---|
| Planned value | 5.0M |
| Earned value | 4.1M |
| Actual cost | 4.4M |
| Budget at completion | 10.0M |
| Current estimate at completion | 11.8M |
| Contract reporting trigger | Cumulative SV or VAC worse than -10% |
| Schedule driver | Qualification retest forecast 5 weeks late |
| Change status | No approved baseline change; pending supplier claim is not authorized |
| Recovery alternative | Add second shift: increases ETC by 0.3M and recovers 4 weeks |
Which stakeholder decision should the report be written to support?
Best answer: C
What this tests: Analysis and Management Reports
Explanation: The report should support the decision implied by the earned value evidence. Schedule variance is unfavorable because EV is 4.1M versus PV of 5.0M, a 0.9M shortfall. The forecast also shows a VAC of -1.8M against a 10.0M BAC, which breaches the stated reporting trigger. The exhibit identifies the driver, the absence of an approved baseline change, and a specific recovery alternative that trades added ETC for schedule recovery. Therefore, the customer-facing report should frame the decision around whether to accept the late milestone or authorize the recovery path with its cost consequence. It should not use a pending claim to revise the baseline, wait for cash activity, or dismiss the condition as only accounting timing.
The variance and forecast evidence show a threshold breach and a clear cost-schedule tradeoff requiring stakeholder direction.
Topic: Perform Planning and Scheduling Duties
A control account manager is preparing month-end status for a hardware qualification deliverable. The performance measurement baseline and schedule were approved before work started.
| Status item | Exhibit fact |
|---|---|
| Status date | 31 Mar |
| Baseline EV milestone | 100% earned when the customer-accepted test report and signed acceptance form are complete |
| Baseline budget for milestone | $120,000 |
| Technical status | All test steps were run, but two nonconformances remain open |
| Acceptance status | Customer has not signed the acceptance form |
| Reported status | Milestone marked complete; EV of $120,000 claimed; AC of $118,000 recorded |
Which correction is best supported by the exhibit?
Best answer: A
What this tests: Perform Planning and Scheduling Duties
Explanation: Earned value recognition must follow the approved objective accomplishment criteria in the baseline. Here, the baseline milestone earns 100% only when the customer-accepted test report and signed acceptance form are complete. Running all test steps is useful technical progress, but it does not satisfy the acceptance criterion, especially with open nonconformances. The proper correction is to reverse the unsupported earned value, leave actual costs traceable to the period in which they were incurred, and update schedule/status information for the remaining work needed to meet acceptance. Changing the criterion after the fact or moving actual costs would damage baseline integrity and accounting traceability.
The approved accomplishment criterion requires customer acceptance, so earned value should not be recognized until that objective evidence exists.
Topic: Analysis and Management Reports
At the May status date, a control account manager submits the following forecast note for a mechanical installation control account. The contract requires EAC updates when current performance indicates a material forecast change.
| Item | Status at May data date |
|---|---|
| BAC | $2,000,000 |
| PV | $1,200,000 |
| EV | $1,000,000 |
| AC | $1,250,000 |
| Current approved baseline change | None |
| Accounting reconciliation finding | Actual costs trace to the correct control account |
| Management reserve authorization | None |
| CAM note | Remaining work will require about $1,100,000 based on observed crew productivity |
Which interpretation is best supported?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: An EAC is a forecast of the expected final cost; it should be updated when current performance or a credible estimate of remaining work indicates the prior forecast is no longer realistic. Here, actual costs reconcile correctly, there is no approved scope or baseline change, and no management reserve authorization has been issued. The CAM’s estimate of $1,100,000 to complete the remaining work supports an EAC of AC plus ETC, or $1,250,000 + $1,100,000 = $2,350,000. That forecast should be reported as a likely overrun against the existing BAC, not used to alter the baseline or mask the variance.
The exhibit supports an EAC forecast update because the remaining-work estimate has changed, while no approved baseline change, reserve authorization, or accounting correction exists.
Topic: Analysis and Management Reports
A control account manager submits the following monthly progress report for a work package as of the September 30 status date:
Which evaluation best supports reliable downstream variance analysis and forecast update?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: Reliable variance analysis depends on consistent status-date data for planned value, earned value, and actual cost. PV remains $360,000 because 300 of 500 units were planned by the status date. EV must reflect objective accomplishment: $600,000 × 250 / 500 = $300,000. AC should include costs incurred for the same cutoff period, not only cash paid or costs already posted, so AC is $310,000 + $80,000 = $390,000. The submitted report would incorrectly show zero schedule variance and favorable cost performance. Corrected data show SV = $300,000 - $360,000 = -$60,000 and CV = $300,000 - $390,000 = -$90,000, which are essential inputs for credible variance analysis and forecast updates.
EV must be based on accepted units and AC must include incurred accruals through the status date, producing unfavorable variance data for reliable analysis.
Topic: Perform Planning and Scheduling Duties
During an integrated baseline review for Control Account 3.2, the review team compares the authorized scope, CPM schedule, and time-phased budget.
| IBR evidence | Finding |
|---|---|
| Authorized work package scope | Build, integrate, and acceptance-test 12 interface modules |
| CPM schedule | 12 module acceptance milestones, four per month in July, August, and September |
| Time-phased budget | Budget loaded for only eight modules, all in July and August |
| CAM planning assumption | September modules will be absorbed through expected productivity improvement |
| Approval evidence | No approved scope deletion, budget transfer, or change request |
What is the most appropriate professional response?
Best answer: A
What this tests: Perform Planning and Scheduling Duties
Explanation: An integrated baseline review tests whether the performance measurement baseline is executable, internally consistent, and traceable to authorized scope. Here, the authorized scope and schedule include 12 modules, but the time-phased budget covers only eight. The September work is not supported by approved scope deletion, budget transfer, or change control, and the CAM’s productivity assumption is not objective planning evidence. The proper response is to document the deficiency and require correction before accepting the affected baseline. A credible control account plan must align scope, schedule, budget, responsibility, and earned value measurement assumptions so that future performance data will be meaningful.
The evidence shows missing budget for authorized scope and an unsupported planning assumption, so the control account is not ready for baseline acceptance.
Topic: Analysis and Management Reports
A control account manager is preparing the June 30 management report for a control account with a budget at completion (BAC) of $2,000,000. The current period appears favorable, but the team has updated the remaining-work forecast based on a vendor productivity problem that has already affected future work packages.
Use these formulas: current-period cost variance = EV − AC; EAC = cumulative AC + approved ETC; VAC = BAC − EAC.
| Measure | Amount |
|---|---|
| Current-period EV | $315,000 |
| Current-period AC | $310,000 |
| Cumulative AC | $1,250,000 |
| Approved ETC for remaining work | $950,000 |
Which management conclusion best supports the required performance decision?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: Managerial analysis should not stop at the current-period variance when the forecast indicates a material impact at completion. Here, the current-period cost variance is $315,000 − $310,000 = $5,000 favorable. However, the approved estimate to complete changes the completion outlook: EAC = $1,250,000 + $950,000 = $2,200,000. Therefore, VAC = $2,000,000 − $2,200,000 = $200,000 unfavorable. A small favorable current-period result does not offset a credible forecast showing the control account will exceed its budget. The management report should direct attention to the forecast impact, cause, corrective action, and decision need rather than emphasizing only the favorable monthly variance.
The current period is slightly favorable, but the approved ETC drives an EAC above BAC, making the forecast overrun the management issue.
Topic: Analysis and Management Reports
A project controls manager is reviewing a customer monthly report before submittal. The contract requires any cumulative CV or SV worse than -10% to include cause, impact, corrective action, forecast effect, and any customer decision needed. Based on the exhibit, which professional judgment is best supported?
| Status at June 30 | Value |
|---|---|
| PV | 2,000 USD thousands |
| EV | 1,700 USD thousands |
| AC | 1,950 USD thousands |
| BAC | 5,000 USD thousands |
| EAC | 5,700 USD thousands |
Variance note: Late customer interface data delayed the integration work package by 3 weeks; a second test crew is planned from July 10.
Accounting note: June accruals are posted and reconciled; no material timing difference remains.
Change note: CR-17 for an added environmental test is pending customer disposition and is not in the PMB.
Draft report excerpt: “Integration is on track with minor timing slippage. Cost growth is mainly accounting timing. Recovery is expected; no customer decision is needed.”
A. Submit the report as written because it is concise and avoids unnecessary technical detail for the customer.
B. Revise the report to disclose the threshold variances, cause, impact, recovery plan, EAC/VAC effect, and the pending CR-17 decision.
C. Defer all customer reporting until CR-17 is approved and can be added to the PMB.
D. Revise the PMB immediately to match the EAC so the customer report reflects the current forecast.
Best answer: B
What this tests: Analysis and Management Reports
Explanation: A customer management report should be factual, complete enough to support decisions, and traceable to EVMS data. Here, SV is negative because EV is less than PV, and CV is negative because EV is less than AC. Both exceed the stated -10% reporting threshold. The draft also incorrectly attributes cost growth to accounting timing even though accruals are reconciled. It omits the 3-week schedule impact, the recovery action, the EAC overrun versus BAC, and the pending customer disposition of CR-17. A professional report should not hide unfavorable performance or replace baseline control with optimistic wording; it should connect the variance, cause, impact, forecast, and requested decision clearly.
The exhibit shows material cost and schedule variances, a reconciled actual-cost basis, a forecast overrun, and a pending customer decision that the draft report does not address.
Topic: Account Considerations
A control account covers installation of 100 isolation valves with a total budget of $200,000. The status date is September 30. The performance measurement baseline planned 60 owner-accepted valves by that date. Earned value is credited only for owner-accepted valves using:
\(EV = \text{accepted valves} \times \$2,000\)
Accounting policy for actual cost at the status date includes incurred direct costs for work performed through September 30, including needed accruals, and excludes future commitments and work after the status date.
Status data:
Which status-date conclusion is best supported?
Best answer: D
What this tests: Account Considerations
Explanation: At the status date, the three core values must be derived from consistent sources but they are not the same type of measure. Planned value comes from the approved time-phased baseline: 60 planned valves × $2,000 = $120,000. Earned value comes from objective accomplishment: 50 owner-accepted valves × $2,000 = $100,000. Actual cost should reflect costs incurred for work performed through the cutoff date, not merely cash paid or ledger postings. The $18,000 September material cost was incurred and should be accrued, so AC should be $112,000 + $18,000 = $130,000. The October installations and October purchase commitment are outside the September 30 cutoff and should not be used to increase EV or AC for this status date.
PV follows the time-phased baseline, EV follows accepted physical progress, and AC must include incurred September cost even if it has not yet posted.
Topic: Revisions and Data Maintenance
A control account manager is reconciling the monthly earned-value report before customer submittal. The accounting system and commitment log use the same status date, and no baseline change is pending.
| Item at status date | Amount |
|---|---|
| PV | $500,000 |
| EV | $450,000 |
| AC currently in EV report | $430,000 |
| Posted direct costs in accounting system | $390,000 |
| Approved accrual for received material not yet invoiced | $70,000 |
| Open purchase commitment for future delivery | $120,000 |
Which interpretation or action is best supported by the reconciliation?
Best answer: B
What this tests: Revisions and Data Maintenance
Explanation: For reconciliation, actual cost should reflect costs incurred for work received as of the status date. Posted direct costs of $390,000 plus the approved accrual of $70,000 give reconciled AC of $460,000. The $120,000 purchase commitment is not actual cost because the related future delivery has not occurred. With EV of $450,000, the corrected cost variance is \(EV - AC = \$450,000 - \$460,000 = -\$10,000\). This is a data maintenance correction to actual-cost reporting, not a reason to change the performance measurement baseline or alter earned value without objective progress evidence.
Actual cost should include posted costs plus the approved accrual, but not the open commitment for future delivery.
Topic: Organizing
During an integrated baseline review, the EVMS lead examines the proposed Level 2 structure that will be used to assign control accounts and measure earned value.
| Proposed Level 2 element | Basis shown in baseline excerpt |
|---|---|
| Engineering Department | Responsible manager and labor cost codes |
| Procurement Department | Buyer group and purchase order register |
| Construction Department | Field superintendent reporting line |
| Monthly Progress Reports | Recurring reporting activity |
Which interpretation is best supported by the exhibit?
Best answer: C
What this tests: Organizing
Explanation: A deliverable-oriented WBS decomposes the authorized project scope into the products, services, or results to be delivered. It is the scope backbone for earned-value control and supports assignment of control accounts through the RAM. The exhibit does not show deliverables; it shows functional departments, cost collection groupings, reporting lines, and a recurring reporting activity. Those may be useful for the OBS, accounting structure, schedule, or management reporting, but they do not replace a WBS. If control accounts are built on this structure, earned value may be tied to who performs work or how costs are collected rather than what scope has been objectively accomplished.
The listed elements are organizations, cost-code groupings, reporting lines, and activities rather than decomposed deliverable scope.
Topic: Perform Budgeting Duties
An EVP practitioner is reviewing candidate control-account structures before the performance measurement baseline is frozen. The contract requires objective earned value, schedule traceability, and actual-cost reconciliation at the control-account level. Which structure should be selected?
| Proposed structure | Basis | Visible control result |
|---|---|---|
| Functional department | One account per OBS department | Actuals by manager; mixed WBS scope |
| Deliverable/CAM | WBS deliverable × responsible OBS | Work packages tie schedule, budget, EV, charge codes |
| Cost element | Labor, material, subcontract accounts | Costs visible; scope and schedule split |
| Summary WBS | One account at WBS 1.2 | Multiple CAMs and deliverables combined |
Best answer: B
What this tests: Perform Budgeting Duties
Explanation: A control account should be established at the management control point where the WBS scope and responsible OBS manager intersect. That structure allows work packages and planning packages to be assigned within a defined scope, time-phased budget, schedule activities, earned value method, and actual-cost collection path. The deliverable/CAM structure is therefore the best fit because it supports integrated performance measurement and accountability. A structure based only on functional departments, cost elements, or a high-level WBS rollup may produce useful summaries, but it weakens traceability between authorized scope, scheduled accomplishment, budget, earned value, and actual costs. Control accounts should be detailed enough to preserve accountability and performance visibility without becoming mere accounting categories or reporting summaries.
This structure creates a control point where scope, responsibility, schedule activities, budgets, earned value methods, and actual-cost charge codes can be integrated.
Topic: Perform Planning and Scheduling Duties
A control account manager is reviewing the technical performance measure to be used as earned-value completion evidence for a cable-installation work package.
WP-3.2.4 Cable RunsWhich proposed measure is specific, measurable, and aligned with the work package definition?
Best answer: C
What this tests: Perform Planning and Scheduling Duties
Explanation: A technical performance measure used for earned-value planning should describe the physical or technical accomplishment expected from the work package, define how it will be measured, and rely on objective completion evidence. Here, the work package is limited to installing, terminating, labeling, and testing 48 cable runs. The signed test record is the stated evidence of acceptance, so counting accepted cable runs directly supports measurable earned progress. Measures based on money spent, later commissioning results, or subjective judgment do not provide reliable technical completion evidence for this defined work package.
This measure matches the defined scope, uses objective evidence, and quantifies completion against the 48 accepted cable runs.
Topic: Account Considerations
A project cost analyst is reviewing charges proposed for Control Account CA-230, Pump Skid Fabrication, at the April status cutoff. The project procedure states that direct costs must be specifically identifiable with authorized scope in a work package or control account.
| Proposed charge | Supporting fact |
|---|---|
| Welder labor, 38 hours | Timecards cite WP-230.04 for installing pump skid PS-17, which is in the authorized work package scope. |
| Fabrication supervisor salary allocation | Monthly department allocation spread across all shop jobs. |
| Seismic bracket redesign effort | Work started from a field request; the change request is submitted but not approved. |
| Shop calibration service | Annual service supports equipment used by several projects and departments. |
Which cost-treatment conclusion is best supported by the exhibit?
Best answer: C
What this tests: Account Considerations
Explanation: Direct cost capture in an EVMS depends on traceability to authorized work scope, not merely on whether an activity seems related to the project. The welder labor has a timecard reference to a specific authorized work package and a specific pump skid deliverable, so it belongs as a direct charge to the control account. The supervisor allocation is a department-wide allocation, so it is not specifically identifiable to the control account as a direct cost. The seismic bracket effort is tied to a pending change, so charging it to the baseline control account before authorization would weaken baseline and actual-cost discipline. The calibration service supports multiple projects and departments, so it should be treated according to the organization’s indirect or shared-cost procedure rather than directly charged to this control account.
The welder labor is specifically traceable to authorized work package scope, while the other items are indirect, shared, or not yet authorized.
Topic: Organizing
A project team is preparing the EVMS control structure for baseline approval. The project controls lead has these constraints:
RAM excerpt:
Which RAM weakness should be corrected before approving the baseline?
Best answer: A
What this tests: Organizing
Explanation: A responsibility assignment matrix links the WBS scope to the OBS responsibility structure and establishes control-account accountability. For reliable baseline control, each control account must have a clear accountable manager who owns the authorized budget, the earned-value method, actual-cost review, and variance response. Joint assignment of one control account to two managers without a defined budget or scope split creates ambiguity: progress could be claimed by one group, costs collected under one code, and variance explanations disputed between functions. Planning packages, unnamed future crew members, and level-of-effort work can be acceptable when they are properly authorized and controlled. The decisive weakness is the lack of single-point accountability for WBS 1.2.
A control account needs clear single-point accountability so earned value, actual costs, and variance response can be traced to an accountable manager.
Topic: Account Considerations
At the July status date, the project controls analyst is reconciling actual costs from the accounting system to the earned value report. The EVMS procedure requires actual costs to be traceable to authorized work and reported by control account.
| Source | Relevant facts |
|---|---|
| Baseline authorization | CA-1.2.1 and CA-1.2.2 are separate authorized control accounts under the same WBS branch. |
| Accounting export | Transactions include project ID, GL account, department, vendor, and a generic charge string ENG-100. |
| Reconciliation finding | July labor and material charges using ENG-100 could belong to either CA-1.2.1 or CA-1.2.2. |
| EV report issue | Actual costs cannot be assigned reliably to the control account that earned the related value. |
Which action is best supported by the exhibit?
ENG-100 charges to the engineering department manager because both control accounts are in the same department.Best answer: D
What this tests: Account Considerations
Explanation: Actual cost traceability depends on a reliable link from accounting transactions to the authorized work being measured. In an EVMS environment, the key link is not just the project number, GL account, department, or vendor; it must identify the cost collection point that maps to the applicable control account, work package, or authorized charge number. Here, the same generic charge string can feed two different control accounts, so the reported actual cost cannot be matched with the earned value for each account. The correct action is to establish or enforce a unique accounting charge code or equivalent cost collection structure tied to authorized control accounts. That preserves reconciliation, variance analysis, and report credibility.
A control-account-level accounting link is needed so actual costs can be traced from transactions to authorized work and matched to earned value reporting.
Topic: Analysis and Management Reports
At the May status date, the project controls lead is reviewing a control account forecast before it is included in the monthly management report.
| Measure | Cumulative value |
|---|---|
| BAC | USD 12.0 million |
| PV | USD 7.2 million |
| EV | USD 6.0 million |
| AC | USD 7.5 million |
| CAM’s proposed EAC | USD 12.3 million |
Additional constraints:
What is the best professional judgment about the proposed EAC?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: A credible EAC must be traceable to current performance, remaining work, known cost exposure, and supportable recovery assumptions. Here, CPI is unfavorable because EV is USD 6.0 million while AC is USD 7.5 million, and the remaining work is similar to the work that caused the variance. The proposed EAC of USD 12.3 million is only slightly above BAC, yet it does not account for USD 0.4 million of incurred cost missing from AC and relies on an unproven corrective action. A forecast may assume improved performance only when the basis is documented and supported by evidence, such as measured productivity improvement or reduced technical risk. Baseline approval rules do not prevent updating the forecast; they prevent unauthorized changes to the performance measurement baseline.
The proposed EAC assumes recovery that is not yet supported and omits known cost and risk information needed for a defensible forecast.
Topic: Perform Budgeting Duties
A control account manager is preparing the month-end earned value report. The status date is March 31, and values are shown in $000. Planned value is to be reported cumulatively from the authorized performance measurement baseline through the status date.
| Baseline item | Jan | Feb | Mar | Apr | Status |
|---|---|---|---|---|---|
| WP-10 Design | 50 | 70 | 80 | 0 | Authorized |
| WP-20 Prototype | 0 | 40 | 60 | 100 | Authorized |
| WP-30 Test fixture | 0 | 0 | 0 | 30 | Authorized |
| Supplier change request | 0 | 0 | 40 | 0 | Not approved |
What planned value should be reported for the control account at the status date?
Best answer: B
What this tests: Perform Budgeting Duties
Explanation: Planned value is the time-phased budget for authorized work scheduled to be accomplished as of the status date. Here, the March 31 PV is cumulative through March, not just the March slice. WP-10 contributes $200,000 and WP-20 contributes $100,000 through March. WP-30 has no budget scheduled until April, so it contributes nothing at March 31. The supplier change request is not approved, so it is not part of the performance measurement baseline and cannot be included in PV. Therefore, the reportable PV is $300,000.
Cumulative PV through March is 50 + 70 + 80 + 40 + 60 = 300 in $000, excluding future and unapproved budget.
Topic: Analysis and Management Reports
A project controls analyst is preparing the monthly earned value management report for a control account at the May status date. The baseline has not been revised this month, actual costs have been reconciled to the accounting system, and the reporting procedure requires variance analysis when either SPI or CPI is below 0.90.
| Measure | Cumulative value |
|---|---|
| Planned value | $1,200,000 |
| Earned value | $1,050,000 |
| Actual cost | $1,260,000 |
What is the best professional judgment for the report?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: Schedule variance is calculated as EV − PV, so the control account has SV = $1,050,000 − $1,200,000 = −$150,000. SPI is EV ÷ PV = 0.875, or about 0.88. Cost variance is EV − AC, so CV = $1,050,000 − $1,260,000 = −$210,000. CPI is EV ÷ AC = 0.833, or about 0.83. Because both SPI and CPI are below the 0.90 reporting threshold, the report should clearly identify both unfavorable conditions and trigger variance analysis. Since actual costs are reconciled and no approved baseline revision exists, the proper action is analysis and forecast review, not baseline adjustment or deferral.
EV is less than PV and AC is greater than EV, so both schedule and cost performance breach the stated threshold.
Topic: Analysis and Management Reports
At the month 8 status date, a control account manager is preparing the forecast for a management report.
What is the best professional judgment for the report?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: The forecast should preserve baseline integrity while showing the expected cost outcome from current performance. With no approved scope change and no documented recovery plan, the stated procedure requires a cumulative CPI-based forecast. Remaining budgeted work is BAC − EV = USD 1,100,000. Dividing that by CPI 0.80 gives an ETC of USD 1,375,000. Adding current AC of USD 1,125,000 gives an EAC of USD 2,500,000. Therefore, VAC = BAC − EAC = USD -500,000. The TCPI to finish at BAC is (BAC − EV) / (BAC − AC) = 1,100,000 / 875,000, or about 1.26, which is a major improvement over the current CPI of 0.80 and should be highlighted as a forecast credibility concern.
Using cumulative CPI, EAC = AC + (BAC − EV) / CPI, and the TCPI to meet BAC is (BAC − EV) / (BAC − AC).
Topic: Analysis and Management Reports
At the June 30 status date, a cost-reimbursable subcontract is on the critical integration path and represents 30% of the project’s remaining ETC. The project-level EAC will be submitted to the customer tomorrow.
The customer requires EACs to be based on objective performance and authorized scope. Which action best supports a credible project-level EAC and management action?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: A credible project-level EAC must integrate subcontract data only when the cost, progress, scope, and forecast basis are traceable. Here, the subcontractor’s EAC at BAC is not supported by current performance: EV is below PV, AC exceeds EV, accepted test points lag the plan, and the recovery statement is only an assertion. The prime also has an accounting reconciliation issue because June labor accrual is missing from subcontractor AC. The pending change may affect future cost, but it is not authorized scope and should not be folded into the baseline EAC as if approved. The best professional action is to reconcile actual cost, require a substantiated subcontract ETC using objective progress and productivity evidence, and communicate the pending change separately so management can decide on recovery, authorization, or contingency actions.
This preserves actual-cost traceability, uses objective subcontract performance for the forecast, and separates unauthorized change from the authorized-scope EAC.
Topic: Analysis and Management Reports
At the May 31 status date, a control account has the following cumulative earned value data:
| Measure | Cumulative value |
|---|---|
| Planned value (PV) | $3,200,000 |
| Earned value (EV) | $2,880,000 |
| Actual cost (AC) | $3,024,000 |
Use these formulas: CV = EV - AC; CV% = CV / EV; SV = EV - PV; SV% = SV / PV. An adverse variance requires formal variance analysis if its dollar magnitude is at least $250,000 or its percent magnitude is at least 8.0%.
Which management-report conclusion is best supported?
Best answer: C
What this tests: Analysis and Management Reports
Explanation: Variance reporting should combine the arithmetic result with the reporting threshold. The cost variance is EV - AC, or $2,880,000 - $3,024,000 = -$144,000. As a percentage of EV, -$144,000 / $2,880,000 = -5.0%, so the adverse cost variance does not meet the $250,000 or 8.0% threshold. The schedule variance is EV - PV, or $2,880,000 - $3,200,000 = -$320,000. As a percentage of PV, -$320,000 / $3,200,000 = -10.0%, so the adverse schedule variance exceeds the threshold. The management report should therefore focus formal variance analysis, root cause, and corrective action on schedule performance, while continuing to monitor cost performance.
SV is -$320,000 and -10.0%, meeting both schedule thresholds, while CV is -$144,000 and -5.0%, below both cost thresholds.
Topic: Analysis and Management Reports
A control account for qualification testing is at the month 8 status date. Cumulative performance is:
| Measure | Value |
|---|---|
| PV | £6.0 million |
| EV | £5.1 million |
| AC | £5.8 million |
| BAC | £12.0 million |
| Current EAC, using current CPI | £13.6 million |
Constraints:
What is the best risk mitigation action for the earned value analyst to recommend?
Best answer: C
What this tests: Analysis and Management Reports
Explanation: The data show both schedule and cost pressure: CPI is about 0.88 and SPI is 0.85, with an EAC of £13.6 million against a £12.0 million BAC. Because the trend is worsening and the next test window is a near-term schedule constraint, management needs more than a variance narrative. The analyst should support a mitigation decision by quantifying forecast exposure, identifying recovery actions that are actually feasible under the overtime and subcontractor limits, and making clear what authorization is required. A pending customer change should not be incorporated into the performance measurement baseline until approved. Management reserve also should not be used simply to hide or absorb poor performance without an approved management action and clear forecast basis.
This action links the unfavorable trend to forecast exposure, tests recovery feasibility against known constraints, and gives the sponsor a timely decision basis.
Topic: Revisions and Data Maintenance
At the month-end status date, a control account has no approved scope change pending. The EVMS procedure requires actual cost to include costs incurred for work performed through the status date, including required accruals, but to exclude commitments for future work. The project manager is reconciling the EV report before it is issued.
| Item | Amount |
|---|---|
| BAC for the control account | $1,200,000 |
| Cumulative PV | $540,000 |
| Cumulative EV | $500,000 |
| Actual cost posted in accounting | $420,000 |
| Required accrual for received services not yet posted | $60,000 |
| Open purchase commitment for material not yet received | $90,000 |
What is the best professional action or judgment for the report?
Best answer: C
What this tests: Revisions and Data Maintenance
Explanation: For EVMS reconciliation, actual cost should reflect costs incurred for authorized work performed through the status date. A required accrual for services already received is an incurred cost even if it has not yet posted or been paid. An open commitment for material not yet received is not actual cost; it is a procurement obligation for future cost recognition. Therefore, reconciled AC is $420,000 + $60,000 = $480,000. With EV of $500,000, cumulative cost variance is EV − AC = $20,000 favorable. Because there is no approved scope change, BAC and the performance measurement baseline should not be changed to absorb a commitment or improve the report.
The incurred but unposted accrual belongs in AC, while the future commitment does not, so CV is $500,000 − $480,000 = $20,000 favorable.
Topic: Account Considerations
At the May status date, an EV analyst is preparing the monthly EVMS performance report. The project controls file contains actual costs imported from a spreadsheet, but finance states that the corporate accounting system is the system of record. The report must be reconcilable by control account and cost element, and May accruals were posted after the preliminary extract. Which data check best validates whether the actual costs are reconcilable with the accounting system for EVMS use?
Best answer: A
What this tests: Account Considerations
Explanation: For EVMS use, actual costs must be traceable to and reconcilable with the accounting system, not merely reasonable or useful for variance analysis. The best validation checks the EVMS actual-cost values against accounting transaction detail at the level needed for reporting, such as control account, cost element, and accounting period. Because accruals were posted after the preliminary extract, the reconciliation must also address status-period cutoff and timing differences. Documented reconciling items show whether differences are explainable rather than hidden data-quality problems. Variance analysis and manager judgment may support performance interpretation, but they do not prove that actual costs reconcile to the official accounting records.
This check directly confirms traceability from EVMS actual costs to the accounting source of record at the required level of control detail.
Topic: Account Considerations
A project controls analyst is reconciling the May status for control account CA-220 before the customer EVMS report is issued.
| May status fact | CA-220 record |
|---|---|
| Status date | May 31 |
| BAC | USD 500,000 |
| PV | USD 300,000 |
| EV | USD 300,000 |
| AC posted in accounting | USD 180,000 |
| Installed material accepted May 28, invoice not received | USD 140,000 |
| Approved baseline changes in May | None |
| Management reserve action | None |
| Customer progress payment | Due June 10 |
Which interpretation is best supported by the exhibit?
Best answer: A
What this tests: Account Considerations
Explanation: The decisive issue is the relationship between the status cutoff and actual-cost recognition. The exhibit shows that material was installed and accepted before the May 31 status date, but the invoice had not yet been received and the cost was not posted. For earned value reporting, AC should reflect costs incurred for authorized work through the status date, commonly by accrual or reconciliation when invoices lag. This is a control-account accounting and cutoff problem, not a reason to change the performance measurement baseline. It is also not a contract-payment issue; cash timing and progress payments do not determine earned progress or incurred cost. Management reserve is not appropriate because no approved scope change or reserve draw is identified.
The accepted material belongs in May actual cost for the control account even though the supplier invoice and customer payment occur later.
Topic: Analysis and Management Reports
A control account manager asks whether the cumulative CPI should be applied to all remaining work in the EAC. Values are cumulative at the June status date and in USD millions.
| Measure | Amount |
|---|---|
| BAC | 100.0 |
| PV | 40.0 |
| EV | 36.0 |
| AC | 45.0 |
| Remaining budget | 64.0 |
Which forecasting judgment is best supported by the exhibit?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: A cumulative CPI of 36.0 / 45.0 = 0.80 indicates unfavorable cost performance to date, but EAC forecasting should consider whether past performance is representative of remaining work. Here, a major part of the overrun came from completed prototype rework caused by a corrected design defect. The remaining work also has a different cost-risk profile: a fixed-price subcontract and internal installation using the corrected design. The current variance should remain visible in performance history, but the ETC should be developed by segmenting the remaining work and documenting the assumptions. Mechanically applying the cumulative CPI to all remaining work would likely overstate future cost growth if the prior conditions no longer apply.
The cumulative CPI is relevant history, but the completed one-time rework and changed remaining work mix make a mechanical CPI extension inappropriate.
Topic: Account Considerations
At the March 31 status cutoff, control account CA-220 has earned value (EV) of $480,000. The accounting ledger shows actual cost (AC) of $455,000. Reconciliation identifies two cutoff items:
Use CV = EV - AC and CPI = EV / AC. Which statement best describes the reconciled control-account result?
Best answer: B
What this tests: Account Considerations
Explanation: Actual cost for earned-value reporting should reflect costs incurred for work performed by the status cutoff, not simply cash paid or invoices received. The accepted subcontract work occurred before March 31, so it should be accrued into AC. The April mobilization payment does not support work performed by the March 31 cutoff, so it should be removed from March AC. After these reconciliation adjustments, AC becomes $475,000. Comparing EV of $480,000 to adjusted AC gives a small favorable cost variance of $5,000 and a CPI of about 1.01. The professional conclusion is that the control account is roughly on budget after proper cutoff treatment, rather than significantly underrunning or overrunning cost.
The reconciled AC is $455,000 + $35,000 - $15,000 = $475,000, giving CV = $5,000 favorable and CPI = 1.01.
Topic: Revisions and Data Maintenance
A control account manager submits the following approved data maintenance correction before the April customer performance report is issued. The project uses cumulative CPI for the monthly EAC unless a documented management forecast supersedes it.
| Item | Before correction | Approved correction |
|---|---|---|
| BAC | $2,400,000 | No change |
| March cumulative PV | $900,000 | No change |
| March cumulative EV | $860,000 | Reduce by $80,000 for duplicate milestone credit |
| March cumulative AC | $920,000 | No change |
| April cumulative PV | $1,200,000 | No change |
| April cumulative EV | $1,100,000 | Reduce by $80,000 for the same prior-period error |
| April cumulative AC | $1,250,000 | No change |
Which interpretation is best supported by the correction?
Best answer: D
What this tests: Revisions and Data Maintenance
Explanation: A retroactive correction to duplicate earned value changes the affected historical EV record, not the authorized budget or actual cost. Because EV is reduced by $80,000, March cost variance and schedule variance each become $80,000 more unfavorable. The same correction also lowers April cumulative EV from $1,100,000 to $1,020,000, so cumulative CPI decreases from 0.88 to 0.816. Under the stated EAC rule, a lower CPI increases the formula-based EAC. The professional reporting response is to restate the affected prior-period data, preserve the audit trail, and explain the effect on current forecast and trends. It is not appropriate to hide the correction in the current period, alter actual costs, or change the baseline without an authorized scope or budget change.
Removing previously overstated EV worsens prior variances, lowers current cumulative CPI, increases the formula-based EAC, and requires transparent stakeholder reporting.
Topic: Analysis and Management Reports
A monthly customer earned value submittal is due for a control account that exceeds the contract variance threshold. The report must disclose variance causes, corrective actions, and forecast risk.
As of the status date:
Which wording should be used in the customer report?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: Customer earned value reporting should be evidence-backed and decision-oriented. The data show both schedule and cost weakness: EV is below PV, AC is above EV, and the EAC exceeds BAC. The report should identify the known cause, state the corrective action, and disclose the remaining forecast risk. Because the second shift and vendor support have just begun, there is not yet objective performance evidence that recovery is working. A professional report can say the actions are underway, but it should not promise recovery or suppress the forecast impact. It also should not revise the baseline unless an approved change authorizes that action. The best wording preserves transparency while giving the customer a clear view of the issue, response, and uncertainty.
This wording is factual, discloses the variance cause and corrective action, and avoids claiming recovery before evidence exists.
Topic: Organizing
A project controls lead is reviewing the EVMS setup before the integrated baseline review. The project has these constraints:
What is the best way to use the OBS in this setup?
Best answer: A
What this tests: Organizing
Explanation: In an EVMS control structure, the WBS describes the project scope by deliverable, while the OBS identifies the organization responsible for performing and managing the work. The two are linked through the responsibility assignment matrix to establish control accounts and accountable managers. Cost account codes support cost collection and traceability, but they do not by themselves define managerial responsibility. Functional reporting lines may help show who reports to whom, but they should not replace the deliverable-oriented WBS. Contract package names may be useful for procurement administration, yet they are not a substitute for the internal responsibility structure needed for earned value accountability.
The OBS identifies organizational responsibility and, when linked to the WBS in the RAM, supports accountable control account ownership.
Topic: Organizing
A contractor is setting up the EVMS control structure for an approved engineering and installation scope. The project manager wants the WBS to use the same first two levels as the functional organization chart so each department can report its own work. The cost team also wants to use the accounting cost-code list as the WBS numbering system. The contract requires earned value to be traceable to authorized deliverables, and control account managers must be accountable for measurable scope. What is the best professional judgment?
Best answer: D
What this tests: Organizing
Explanation: In an EVMS, the WBS should decompose the authorized project scope into deliverable-oriented elements. It is not the same as an organization chart, cost-code list, schedule activity list, or reporting hierarchy. The OBS identifies responsible organizations, cost codes support accounting collection, and schedule activities support time-phased execution and status. These structures should be cross-referenced, not substituted for the WBS. In this situation, the contract requirement for traceability to authorized deliverables is decisive. A deliverable-based WBS provides the scope framework for control accounts, while the RAM links WBS elements to responsible managers and accounting codes support actual-cost traceability.
A deliverable-oriented WBS preserves scope traceability while allowing responsibility and accounting codes to be mapped without replacing the WBS.
Topic: Analysis and Management Reports
A control account manager is preparing the month-end variance report for a work package. The project control procedure requires a formal variance analysis when an unfavorable cost or schedule variance meets both the dollar and percentage thresholds.
| Status measure | Value |
|---|---|
| Planned value (PV) | $1,800,000 |
| Earned value (EV) | $1,650,000 |
| Actual cost (AC) | $1,820,000 |
| Threshold rule | Unfavorable variance of at least $150,000 and at least 10.0% |
| Percent formulas | CV% = CV / EV; SV% = SV / PV |
Which interpretation is supported by the exhibit?
Best answer: A
What this tests: Analysis and Management Reports
Explanation: Variance threshold status should be based on the stated reporting rule, not on a general impression of progress. Cost variance is calculated as EV minus AC: $1,650,000 - $1,820,000 = -$170,000. Using the stated formula, CV% is -$170,000 / $1,650,000 = -10.3%, so the cost variance meets both the dollar and percentage thresholds. Schedule variance is EV minus PV: $1,650,000 - $1,800,000 = -$150,000. Although the schedule variance meets the dollar threshold, SV% is -$150,000 / $1,800,000 = -8.3%, so it does not meet the 10.0% percentage threshold. The supported management-reporting action is to formally address the cost variance with cause and corrective action while monitoring the schedule variance under the stated rule.
CV is $170,000 unfavorable and 10.3% unfavorable, while SV is $150,000 unfavorable but only 8.3% unfavorable.
Topic: Perform Budgeting Duties
At the May 31 status date, a project controls analyst is reconciling budget categories for the monthly earned value report. Use the project rule: undistributed budget is approved budget for authorized scope that has not yet been distributed to control accounts.
What should be reported as undistributed budget, and what is the correct budgeting treatment?
Best answer: A
What this tests: Perform Budgeting Duties
Explanation: Undistributed budget is not simply any budget that lacks detailed work-package planning. It is budget for authorized work that has been approved but not yet distributed to control accounts. In this case, CR-17 has been approved for $900,000 and the scope is authorized, but the budget has not yet been assigned to control accounts, so it is undistributed budget. Planning-package budget is already inside assigned control accounts and supports future work that is not yet planned in detail. Management reserve is held outside the performance measurement baseline for unknowns within scope and is not undistributed budget. The cost variance is performance data, calculated as EV - AC, and does not create budget authority.
The approved change is authorized scope with budget not yet distributed to control accounts, which is the defining condition for undistributed budget.
Topic: Revisions and Data Maintenance
At the May 31 status date, a control account was reported as follows:
| Measure | Reported cumulative value |
|---|---|
| Planned value (PV) | $1,000,000 |
| Earned value (EV) | $900,000 |
| Actual cost (AC) | $850,000 |
During reconciliation on June 5, the project controls analyst finds two errors affecting the May 31 report:
Use CPI = EV / AC. There is no approved scope change or baseline change. What is the best action?
Best answer: B
What this tests: Revisions and Data Maintenance
Explanation: Reconciliation of EVMS data should preserve performance integrity. The omitted accrual means AC was understated: $850,000 + $160,000 = $1,010,000. The unsupported milestone claim means EV was overstated: $900,000 - $100,000 = $800,000. The corrected CPI is $800,000 / $1,010,000, or about 0.79. Because these are reporting and data-quality errors at the status date, the professional action is to correct the cumulative performance data, keep an audit trail, explain the effect on prior reporting, and update management reporting and forecasts as appropriate. A baseline change is not justified because no approved scope or budget change exists.
The reconciliation identifies data errors, so the reported performance should be corrected with traceability rather than hidden in baseline or forecast changes.
Topic: Analysis and Management Reports
At the May 31 status date, a control account manager is preparing the monthly earned-value analysis. The approved performance measurement baseline (PMB) contains only the original deliverable scope; no baseline change has added the risk-response activity as earned scope. Management has authorized a supplier-risk mitigation action, and the risk has not occurred.
Use:
| Measure | Amount |
|---|---|
| BAC for baseline deliverable scope | $1,000,000 |
| EV from completed baseline deliverables | $630,000 |
| Baseline-scope AC included in accounting | $630,000 |
| Total AC to date, including mitigation already spent | $690,000 |
| Remaining authorized mitigation cost | $40,000 |
Which performance-analysis statement should be reported?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: Risk-response spending is not the same as earned performance unless the response activity is part of authorized baseline scope with defined accomplishment criteria. Here, EV remains $630,000 because only completed baseline deliverables earn value. Baseline-scope CPI is $630,000 / $630,000 = 1.00, so the ETC for remaining baseline work is ($1,000,000 - $630,000) / 1.00 = $370,000. The total EAC includes all actual cost already incurred, plus the remaining baseline ETC, plus the remaining authorized mitigation cost: $690,000 + $370,000 + $40,000 = $1,100,000. The correct management message is that mitigation cost is a forecast impact and cost-management issue, not evidence of additional physical progress.
The mitigation cost affects the forecast, but it does not create additional EV because it is not authorized baseline deliverable scope.
Topic: Perform Planning and Scheduling Duties
A baseline planning team is reviewing a control account before the integrated baseline review. The risk register says the test article delivery date may slip by up to 10 business days, and receiving inspection is required before integration testing can begin.
| Baseline item | Current plan |
|---|---|
| Control account | CA-230 Integration Test |
| Work package budget | $480,000, phased September-October |
| Predecessor milestone | Supplier test article delivery on September 2 |
| Current logic | Delivery milestone FS+0 to test start |
| Missing work | 3-day receiving inspection has no activity |
| EV method | Weighted milestones: start test, dry run, final report |
| Authorized mitigation | $30,000 for expedited receiving inspection support |
Which mitigation action best protects the earned-value planning basis?
Best answer: B
What this tests: Perform Planning and Scheduling Duties
Explanation: A sound mitigation action should preserve the integrity of the schedule model and the performance measurement baseline. Here, receiving inspection is required work and is a logical predecessor to integration testing, but it is missing from the schedule. The authorized mitigation also has a budget that must be assigned and time-phased to the work it supports. Adding the activity, linking it to delivery, and retaining objective milestone-based EV prevents hidden logic, unsupported budget movement, and premature earned value. The mitigation does not eliminate the supplier risk, but it makes the planned response measurable and traceable within the control account.
This action makes the real dependency, mitigation work, budget phasing, and objective earned-value criteria visible in the baseline plan.
Topic: Organizing
A project controls analyst is preparing the initial work authorization for a new control account. The project manager gives these constraints:
Authorized baseline status may be opened for execution.A identifies the accountable control account manager and responsible OBS organization; S identifies a support organization.| WBS work element | Baseline status | Avionics Software OBS | Systems Test OBS |
|---|---|---|---|
| 1.2.3 Flight Software Integration | Authorized | A - Dana Lee | S - Omar Patel |
| 1.2.4 Simulation Lab Upgrade | Pending change | S - Dana Lee | A - Omar Patel |
| 1.3.1 Acceptance Test | Authorized | S - Dana Lee | A - Omar Patel |
Which work authorization setup is best supported by the RAM?
Best answer: C
What this tests: Organizing
Explanation: A responsibility assignment matrix links the WBS work element to the OBS organization responsible for managing that scope. The control account is normally established at that intersection, with the named accountable manager serving as the control account manager. Support organizations may contribute work, but they do not replace the accountable OBS assignment unless the RAM is changed through the proper authorization process. Here, WBS 1.2.3 is authorized, Avionics Software is marked accountable, and Dana Lee is named at that accountable intersection. Systems Test is marked only as support for that same work element. Pending-change work should not be opened for execution as an authorized control account, and combining separate WBS elements would weaken scope and responsibility traceability.
The authorized WBS element 1.2.3 has Dana Lee’s OBS marked accountable and Systems Test marked as support.
Topic: Perform Budgeting Duties
A control account manager is preparing the month-end earned value update for a discrete installation work package. Review the status snapshot:
| Item | Status at data date |
|---|---|
| Work package budget | 100,000 budget units |
| Planned value | 80,000 budget units |
| Planned labor hours | 1,000 hours |
| Labor hours charged | 720 hours |
| Actual cost recorded | 86,000 budget units |
| Assemblies installed and accepted | 38 of 100 |
| Completion rule in work instruction | No earned credit until an assembly is installed and accepted |
Which interpretation is best supported by the exhibit?
Best answer: C
What this tests: Perform Budgeting Duties
Explanation: For discrete work, the earned value measurement technique should reflect objective accomplishment of the authorized work scope. The exhibit states that credit is earned only when an assembly is installed and accepted. Therefore, the defensible earned progress is based on 38 accepted assemblies out of 100, or 38% of the work package budget. Labor hours charged, actual cost, and elapsed schedule plan may explain effort, spending, or timing, but they do not prove that the deliverable has been completed. A technique based on hours used would reward effort rather than completed work and would overstate accomplishment when productivity is below plan.
The exhibit shows that earned value should be tied to accepted assemblies, not effort expended or cost incurred.
Topic: Perform Budgeting Duties
A control account manager is selecting a performance measurement technique for a 4-month work package to install 120 identical valve assemblies. Each assembly has the same budgeted labor content, can be counted independently, and earns contractual acceptance only after inspection sign-off. Supplier invoices will arrive in large batches that do not match installation progress, and the project manager wants to minimize subjective progress estimates. Which earned value technique best fits this work package?
Best answer: C
What this tests: Perform Budgeting Duties
Explanation: A units-complete technique is appropriate when work consists of many similar, measurable items and completion can be verified objectively. Here, each valve assembly has the same budgeted labor content and earns acceptance only after inspection sign-off, so earned value can be credited in proportion to accepted units. This avoids confusing supplier invoice timing with physical progress and reduces measurement risk from subjective estimates. Level of effort is better for support activities that do not produce measurable discrete outputs. Fixed-formula methods such as 50/50 can be useful for short-duration, low-value tasks, but they would not reflect the actual number of accepted valves. Subjective percent complete is weaker when objective count and acceptance evidence are available.
The work is repetitive, objectively countable, and has clear acceptance evidence for each completed unit.
Topic: Revisions and Data Maintenance
At the September status cutoff, the project controls lead is reviewing a proposed month-end adjustment for Control Account 2.3.
| Item | Status |
|---|---|
| Current BAC | USD 2,000,000 |
| PV | USD 1,600,000 |
| EV | USD 1,450,000 |
| AC | USD 1,720,000 |
| Current EAC before adjustment | USD 2,280,000 |
| Approved change CR-21 | Added inspection scope, USD 150,000 budget authorized, not yet incorporated |
| Productivity trend T-09 | Forecasts USD 130,000 additional cost to finish original scope; no scope change |
| Risk R-14 | Possible supplier premium later; not triggered |
The proposed adjustment is to increase the control account budget by USD 280,000 and reduce management reserve by USD 130,000 so the reported VAC is zero. Which interpretation is best supported by the exhibit?
Best answer: D
What this tests: Revisions and Data Maintenance
Explanation: Baseline revisions should be tied to authorized changes, not used to absorb unfavorable performance. CR-21 is an approved scope change with authorized budget, so it should be incorporated through baseline change control. The productivity trend is cost growth on the original authorized scope; it should affect the EAC or ETC and be addressed in the variance explanation and corrective action, not added to the performance measurement baseline to erase VAC. Management reserve is controlled separately from the PMB and should not be reduced merely to offset an overrun or create a zero variance. The untriggered supplier risk also does not justify a current baseline or actual-cost adjustment.
Only the authorized scope change supports a baseline revision; the productivity impact belongs in forecast and variance analysis.
Topic: Analysis and Management Reports
At the June 30 status date, a draft customer report mixes legacy and current earned-value terms for one control account. Use these equivalences: BCWS = PV, BCWP = EV, and ACWP = AC. Use SV = EV - PV and CV = EV - AC.
| Item at June 30 | Amount |
|---|---|
| Time-phased budget for scheduled work | $250,000 |
| Budgeted value of physically completed work | $200,000 |
| Actual cost recorded in accounting | $230,000 |
The draft report labels BCWP as PV and BCWS as EV, then states that the control account is ahead of schedule. What is the best response?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: Legacy earned-value terminology must be translated consistently before interpreting performance. BCWS is the budgeted cost of work scheduled, which is the same as planned value. BCWP is the budgeted cost of work performed, which is the same as earned value. ACWP is actual cost. At the June 30 status date, PV is $250,000, EV is $200,000, and AC is $230,000. Therefore, SV = EV - PV = $200,000 - $250,000 = -$50,000, showing less work was earned than planned. CV = EV - AC = $200,000 - $230,000 = -$30,000, showing the work performed cost more than its earned budgeted value. The professional response is to correct the mixed labels before management uses the report.
BCWS maps to PV, BCWP maps to EV, and ACWP maps to AC, so both schedule and cost variances are unfavorable at the status date.
Topic: Analysis and Management Reports
As of the June 30 status date, a control account has no approved scope change and no approved management reserve request. Management rules state that CPI or SPI below 0.95 requires corrective action, and a forecast VAC greater than 5% of BAC must be disclosed in the monthly management report. Use:
Values are in thousands of dollars.
| BAC | PV | EV | AC |
|---|---|---|---|
| 5,000 | 3,000 | 2,700 | 3,000 |
Which management decision is best supported by the data?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: The performance data indicates both schedule and cost weakness. CPI is \(2,700 / 3,000 = 0.90\), and SPI is \(2,700 / 3,000 = 0.90\), so corrective action is required. Using the stated forecast method, EAC is \(3,000 + (5,000 - 2,700) / 0.90 \approx 5,556\), producing a VAC of about -556, or -11.1% of BAC. That exceeds the 5% disclosure rule. Because there is no approved scope change or approved reserve request, the PMB should not be changed merely to absorb poor performance. The appropriate management response is transparent forecast disclosure and corrective action while preserving baseline integrity.
CPI and SPI are both 0.90, and the forecast VAC is about -$0.56 million, exceeding the disclosure threshold without justification for changing the baseline.
Use the AACE EVP Practice Test page for the full PM Mastery practice path, mixed-topic practice, timed mock exams, explanations, and web/mobile app access.
Read the AACE EVP guide on PMExams.com for concept review, then return here for PM Mastery practice.