Try 10 focused AACE Earned Value Professional (EVP) questions on analysis and management reports, with answers and explanations, then continue with PM Mastery.
Use this focused AACE EVP page to drill Analysis and Management Reports decisions before returning to mixed practice, timed mocks, and the full PM Mastery question bank.
| Field | Detail |
|---|---|
| Exam | AACE EVP |
| Topic area | Analysis and Management Reports |
| Blueprint weight | 41% |
| Page purpose | Focused sample questions before returning to mixed practice |
Use this page to isolate Analysis and Management Reports for AACE EVP. Work through the 10 questions first, then review the explanations and return to mixed practice in PM Mastery.
| Pass | What to do | What to record |
|---|---|---|
| First attempt | Answer without checking the explanation first. | The fact, rule, calculation, or judgment point that controlled your answer. |
| Review | Read the explanation even when you were correct. | Why the best answer is stronger than the closest distractor. |
| Repair | Repeat only missed or uncertain items after a short break. | The pattern behind misses, not the answer letter. |
| Transfer | Return to mixed practice once the topic feels stable. | Whether the same skill holds up when the topic is no longer obvious. |
Blueprint context: 41% of the practice outline. A focused topic score can overstate readiness if you recognize the pattern too quickly, so use it as repair work before timed mixed sets.
These questions are original PM Mastery practice items aligned to this topic area. They are designed for self-assessment and are not official exam questions.
Topic: Analysis and Management Reports
At the May status date, a control account manager submits this variance analysis for a work package that is below its reporting threshold.
| Item | Reported fact |
|---|---|
| PV | $1,200,000 |
| EV | $840,000 |
| AC | $930,000 |
| SPI | 0.70 |
| CPI | 0.90 |
| Root cause | 12 of 30 supplier drawings are still unapproved, blocking field installation |
| Proposed mitigation | Use weekend overtime after drawings are released |
| Follow-up stated | “Monitor recovery next month” |
| Residual exposure | Supplier backlog may continue for 4 more weeks; EAC assumes normal productivity |
Which professional judgment is best supported by the exhibit?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: A mitigation plan should connect the corrective action to the root cause, show how remaining exposure will be managed, and define measurable follow-up. Here, the performance problem is driven by unapproved supplier drawings that block installation. Weekend overtime may help recover field work after drawings are released, but it does not resolve the approval backlog. The plan also leaves residual exposure visible: the backlog may continue for four weeks, yet the EAC still assumes normal productivity. A stronger report would identify actions and owners for drawing approval, quantify expected recovery, update the forecast if needed, and define follow-up measures such as drawings approved per week, released work available, installation productivity, and forecast variance trend.
The exhibit shows the root cause is unapproved drawings, while the plan only adds later overtime and lacks quantified tracking or forecast treatment of the remaining exposure.
Topic: Analysis and Management Reports
At the June 30 status date, a control account manager submits the following progress report. The approved performance measurement baseline uses a 0/100 earned value rule for each installation work package: 100% EV is earned only when the acceptance test is passed.
| Measure | Amount/status |
|---|---|
| PV through June | $800,000 |
| Reported EV | $800,000 |
| AC | $950,000 |
| Work packages | 4 at $200,000 each |
| Acceptance passed | 2 of 4 |
| Failed test/rework open | 2 of 4 |
Which reporting interpretation is best supported?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: Under a 0/100 earned value technique, budgeted value is earned only when the defined completion criterion is met. Here, acceptance testing is the completion criterion, and only 2 of 4 equal-budget work packages have passed. Valid EV is therefore $400,000, not the reported $800,000. Compared with PV of $800,000, the work is behind schedule by $400,000. Compared with AC of $950,000, the work is also over cost by $550,000. The main reporting issue is not merely an unfavorable variance; it is that the reported EV is not supported by the approved measurement method.
The 0/100 rule allows EV only for the two accepted work packages, making EV less than PV and AC.
Topic: Analysis and Management Reports
At the month 8 status date, a project has crossed its management threshold with cumulative CPI 0.91 and SPI 0.94. The executive steering committee meets tomorrow to decide whether to authorize a recovery action and whether the current EAC remains credible.
Constraints:
What is the best analysis to prepare for the executive meeting?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: Executive earned-value analysis should support management decisions: what is driving the variance, what it means for cost and schedule outcomes, whether the forecast is credible, what actions are recommended, and what approvals or direction are needed. Working-level analysis for control-account managers, schedulers, and accounting is still important, but it serves a different purpose: root-cause detail, corrective-action ownership, schedule validation, and cost reconciliation. The unresolved schedule logic and accrual timing issue should be disclosed as data limitations, not allowed to overwhelm the executive decision. A customer report may require contract-specific formatting and traceability, but it is not automatically the right communication for internal executives.
Executives need concise, decision-oriented analysis that integrates performance, forecast credibility, risks, and required management action.
Topic: Analysis and Management Reports
At the month-end status date, a control account reports cumulative PV of $8.0 million, EV of $7.2 million, and AC of $7.8 million. The current period had planned work valued at $900,000, earned $450,000, and incurred $660,000. The control account manager has reduced the EAC from $12.4 million to $11.8 million against a BAC of $11.5 million, citing expected labor recovery and a potential supplier credit. No baseline change has been approved, and the supplier credit has not been recorded by accounting. What is the best management reporting action?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: An improving EAC can be valid, but it must be credible and traceable. Here, the current-period CPI is poor because the account earned $450,000 while incurring $660,000, and cumulative performance is also unfavorable. A lower EAC may still be possible, but the stated basis includes expected future recovery and a supplier credit that accounting has not recorded. Management reporting should not hide the adverse current-period signal or treat unverified assumptions as achieved cost improvement. The professional response is to report the forecast with clear caveats, identify the conflict with recent performance, and communicate the evidence needed to support the improvement.
The improved forecast conflicts with weak current-period performance, so it should be communicated with its assumptions, data limits, and management implications clearly identified.
Topic: Analysis and Management Reports
At the 31 March status date, a control account has an approved BAC of USD 1,200,000. The cumulative earned value is USD 600,000 and cumulative actual cost is USD 750,000. No approved baseline changes are pending, and the control account manager states that the remaining work is expected to continue at the same cumulative cost efficiency.
Use: CPI = EV / AC; EAC = AC + (BAC - EV) / CPI; ETC = EAC - AC; VAC = BAC - EAC.
Which management report statement best reflects the forecast implication?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: A forecast should distinguish the approved budget baseline from the current estimate of final cost. Here, CPI = EV / AC = 600,000 / 750,000 = 0.80. Since the remaining work is expected to continue at the same cost efficiency, the remaining budgeted work of USD 600,000 is divided by 0.80, producing an ETC of USD 750,000. Adding that ETC to the current actual cost gives an EAC of USD 1,500,000. The VAC is BAC - EAC, or USD 1,200,000 - USD 1,500,000 = -USD 300,000. The professional implication is not to change the baseline automatically, but to report a credible unfavorable forecast and identify corrective action or approved change if needed.
The CPI is 0.80, so the remaining work forecast is USD 750,000, giving an EAC of USD 1,500,000 and an unfavorable VAC of USD 300,000.
Topic: Analysis and Management Reports
At the 30 September status date, control account CA-210 has an active risk that a vendor test fixture failure could delay acceptance testing and require outsourced lab support. The control account manager states that the completed mitigation has significantly reduced future exposure.
Project procedure defines:
| Risk assessment | Probability | Remaining cost impact | Remaining schedule impact | Evidence |
|---|---|---|---|---|
| Before mitigation | 40% | $500,000 | 20 workdays | Prior fixture failure history |
| After mitigation | 15% | $300,000 | 12 workdays | Three successful validation runs completed on 28 September |
Which evidence best validates the claimed improvement in future exposure?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: A claimed improvement in future risk exposure should be validated with residual risk evidence, not simply current-period cost performance or the fact that the event has not yet occurred. Using the project’s defined method, the original expected cost exposure was 40% × $500,000 = $200,000, and the residual expected cost exposure is 15% × $300,000 = $45,000. The expected schedule exposure similarly decreased from 40% × 20 = 8.0 workdays to 15% × 12 = 1.8 workdays. The completed validation runs provide objective support for the revised probability and impact assumptions. This is stronger evidence than CPI movement, mitigation spending, or optimistic removal of an open risk.
This directly compares pre- and post-mitigation residual exposure using the defined probability-impact method and ties the reduction to objective mitigation evidence.
Topic: Analysis and Management Reports
A prime contractor is preparing the monthly customer earned-value report and the internal EAC review. A major subcontractor submitted cumulative data at the status date showing PV = $4.0 million, EV = $3.8 million, AC = $3.6 million, and EAC = $4.5 million. The subcontract represents 25% of the total BAC.
Constraints:
What is the best professional action?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: Subcontractor data can be integrated into customer reporting and forecast decisions only when it is reliable, traceable, and consistent with EVMS rules. Here, the submitted EV is not fully supported because the approved method is milestone-based and only 3 of 5 equal milestones have accepted evidence. Actual cost is also incomplete because work performed before the status date requires an accrual. The pending claim may affect future cost exposure, but it is not authorized baseline scope and should not be added to BAC or the performance measurement baseline. The appropriate action is to reconcile the subcontractor data, use objective accomplishment and complete actual-cost recognition, and clearly qualify any forecast that depends on unresolved subcontractor information.
This protects customer reporting and management forecasting by using traceable progress, complete actual cost, and only authorized baseline scope.
Topic: Analysis and Management Reports
At the month 8 status date, a control account is on the project critical path and is forecast to miss a contractual milestone by 4 weeks unless recovery action is taken.
| Measure | Amount (USD millions) |
|---|---|
| PV | 5.00 |
| EV | 4.50 |
| AC | 5.00 |
| BAC | 10.00 |
Additional facts:
Which management recommendation best balances schedule recovery, mitigation cost, and forecast credibility?
Best answer: B
What this tests: Analysis and Management Reports
Explanation: The schedule recovery plan has a favorable near-term schedule and exposure impact: USD 0.40 million avoids USD 0.60 million of contractual damages. However, recovering the milestone date does not erase cost inefficiency already shown by CPI. With CPI = 4.50 / 5.00 = 0.90, the remaining budgeted work is USD 5.50 million. Forecasting that remaining work at the current CPI gives USD 5.50 / 0.90 = USD 6.11 million. Adding current AC of USD 5.00 million and the USD 0.40 million recovery cost gives an EAC of about USD 11.51 million. The professional recommendation should support the recovery action while preserving forecast credibility and clearly reporting the expected cost overrun.
The recovery cost is less than the USD 0.60 million milestone exposure, but the forecast must still reflect the current CPI and the added recovery cost.
Topic: Analysis and Management Reports
A controls analyst is preparing the May 31 earned value status for a control account work package with a budget at completion of USD 600,000 for 100 identical panels.
What is the best May 31 progress-reporting action?
Best answer: C
What this tests: Analysis and Management Reports
Explanation: Earned progress must be tied to the approved accomplishment criteria, not to time passed, money spent, invoices paid, commitments, or optimism about future recovery. The work package budget is USD 600,000 for 100 panels, so each accepted panel earns USD 6,000. With 45 inspection-accepted panels, EV is USD 270,000. The 10 installed but unaccepted panels may support a narrative about near-term recovery, but they do not earn value under the stated rule. Actual cost is the incurred and accrued cost of USD 390,000; paid invoices and open commitments are different financial facts and should not be substituted for EV. The report should preserve the variance signal and explain the cause and forecast implications transparently.
EV should be based on the 45 inspection-accepted panels under the approved measurement rule, while actual cost and forecast expectations are reported separately.
Topic: Analysis and Management Reports
At the 30 September status date, a control account has a budget at completion of $2,500,000. A risk mitigation action for poor installation productivity was implemented on 1 September. The $100,000 tooling and training cost is included in September actual cost and is explicitly nonrecurring. No baseline change has been approved.
Use: CPI = EV / AC; recurring-period CPI = period EV / (period AC - nonrecurring mitigation cost); CV = EV - AC.
| Measure | Through August | September |
|---|---|---|
| Earned value | $1,000,000 | $300,000 |
| Actual cost | $1,250,000 | $385,000 |
Which statement best interprets the mitigation’s effect for management reporting?
Best answer: D
What this tests: Analysis and Management Reports
Explanation: Risk mitigation should be assessed against both historical performance and credible forward-looking evidence. Here, cumulative performance is still poor: cumulative EV is $1,300,000 and cumulative AC is $1,635,000, giving a $335,000 unfavorable cost variance. That past variance remains part of the performance history. However, the September data provide separate evidence about future prospects because the $100,000 mitigation cost is nonrecurring. Removing that one-time cost gives recurring September AC of $285,000 and a recurring-period CPI of about 1.05. That supports a management report saying the mitigation appears to have improved future cost performance, while still disclosing the unfavorable cumulative variance and the basis for any ETC update.
Excluding the nonrecurring mitigation cost, September recurring CPI is $300,000 / $285,000 = 1.05, while cumulative CV remains $1,300,000 - $1,635,000 = -$335,000.
Use the AACE EVP Practice Test page for the full PM Mastery practice path, mixed-topic practice, timed mock exams, explanations, and web/mobile app access.
Read the AACE EVP guide on PMExams.com, then return to PM Mastery for timed practice.