Try 10 focused AACE Earned Value Professional (EVP) questions on account considerations, with answers and explanations, then continue with PM Mastery.
Use this focused AACE EVP page to drill Account Considerations decisions before returning to mixed practice, timed mocks, and the full PM Mastery question bank.
| Field | Detail |
|---|---|
| Exam | AACE EVP |
| Topic area | Account Considerations |
| Blueprint weight | 13% |
| Page purpose | Focused sample questions before returning to mixed practice |
Use this page to isolate Account Considerations for AACE EVP. Work through the 10 questions first, then review the explanations and return to mixed practice in PM Mastery.
| Pass | What to do | What to record |
|---|---|---|
| First attempt | Answer without checking the explanation first. | The fact, rule, calculation, or judgment point that controlled your answer. |
| Review | Read the explanation even when you were correct. | Why the best answer is stronger than the closest distractor. |
| Repair | Repeat only missed or uncertain items after a short break. | The pattern behind misses, not the answer letter. |
| Transfer | Return to mixed practice once the topic feels stable. | Whether the same skill holds up when the topic is no longer obvious. |
Blueprint context: 13% of the practice outline. A focused topic score can overstate readiness if you recognize the pattern too quickly, so use it as repair work before timed mixed sets.
These questions are original PM Mastery practice items aligned to this topic area. They are designed for self-assessment and are not official exam questions.
Topic: Account Considerations
A control account manager is preparing the month-end earned value status as of March 31. The accounting system identifies actual cost for earned value reporting on an accrual basis: costs are actual when incurred and recorded through receipt or accrual, not when merely budgeted, committed, paid, or forecast.
| Cost item as of March 31 | Amount |
|---|---|
| Performance measurement baseline budget for the work package | $400,000 |
| Planned value through March 31 | $220,000 |
| Earned value from accepted physical progress | $180,000 |
| Supplier purchase order authorized | $260,000 |
| Materials received and accepted; accrual recorded | $140,000 |
| Supplier invoice paid in cash | $75,000 |
| Current forecast of supplier final cost | $310,000 |
Which interpretation is best supported for the earned value report?
Best answer: B
What this tests: Account Considerations
Explanation: For earned value reporting, actual cost should trace to the accounting basis defined for the project. Here, the accounting system uses accrual-based actuals, so actual cost is the cost incurred and recorded for materials received and accepted by the status date. The purchase order is a commitment, not actual cost. The cash payment is a disbursement and may lag the incurred cost. The forecast is an estimate of final cost, not the cost already incurred. Budgeted cost, such as planned value or BAC, is also not actual cost. Keeping these categories separate preserves traceability between the EVMS report and the accounting system.
The accrued cost for received and accepted materials is the accounting actual through the status date.
Topic: Account Considerations
At the May status cutoff, accounting replaced the provisional indirect rate with the approved year-to-date rate for the same control account. The scope, physical progress, and approved budget have not changed.
| Item | Value |
|---|---|
| Cumulative PV | $500,000 |
| Cumulative EV | $450,000 |
| Direct actual cost | $300,000 |
| Previous indirect rate | 40% of direct actual cost |
| Revised indirect rate | 50% of direct actual cost |
Which interpretation is supported by the exhibit?
Best answer: D
What this tests: Account Considerations
Explanation: An indirect-rate or overhead allocation change affects actual cost when the accounting system applies a different rate to recorded direct costs. It does not, by itself, create earned progress or revise the performance measurement baseline. Here, previous AC was direct cost plus 40% overhead: $300,000 + $120,000 = $420,000. Revised AC is direct cost plus 50% overhead: $300,000 + $150,000 = $450,000. EV remains $450,000, so CV changes from $30,000 favorable to $0, and CPI changes from 1.07 to 1.00. PV, EV, BAC, and baseline budgets should change only through approved baseline change control, not merely because accounting updates an indirect rate.
The indirect-rate change increases actual cost from $420,000 to $450,000 while PV, EV, and the baseline remain unchanged.
Topic: Account Considerations
At the April 30 status cutoff, a control account manager is reconciling cumulative actual cost for the monthly earned value report.
What is the best professional judgment for the April report?
Best answer: A
What this tests: Account Considerations
Explanation: For earned value reporting, actual cost must be reconciled to the reporting cutoff. The supplier invoice is in the ledger but relates to material received after the April 30 status date, so it should not be included in April actual cost. The labor accrual is for work performed before the status date, so it should be included even though it is not yet in the ledger charges. Reconciled actual cost is $495,000. With earned value of $460,000, the control account has an unfavorable cost variance of -$35,000 and a CPI of 0.93. Because the unfavorable cost variance exceeds the $25,000 threshold, variance analysis is required. Earned value should not be adjusted to match cost; it must remain tied to objective progress and the authorized measurement basis.
The cutoff reconciliation is $510,000 - $35,000 + $20,000 = $495,000, so CV is $460,000 - $495,000 = -$35,000 and CPI is 0.93.
Topic: Account Considerations
At the month-end status cutoff, Control Account 1.2.3 shows AC of USD 482,000 in the EVMS report, while the accounting ledger shows USD 516,000 charged to the same control account. The variance analysis is due tomorrow. The project controls analyst notes these constraints:
What is the best reconciliation step?
Best answer: B
What this tests: Account Considerations
Explanation: A proper reconciliation resolves the cause of the difference, not merely the total. EVMS actual cost should be traceable to the accounting system, but it must also respect status cutoff rules and correct control-account coding. Here, the ledger total includes a supplier invoice for work after the status date, so it should not be included in current-period AC. The miscoded labor charge should be corrected through the accounting process or a documented transfer to the proper control account. The reconciliation should leave an audit trail showing how the EVMS report ties to approved accounting records after cutoff and coding corrections. Changing budgets or substituting commitments would not resolve the accounting-to-EVMS discrepancy.
This action reconciles actual cost to accounting while preserving cutoff discipline, control-account traceability, and audit evidence.
Topic: Account Considerations
At the 30 September status date, a draft control account report shows the following amounts in thousands (K). Use \( \text{CPI}=\text{EV}/\text{AC} \) and \( \text{CV}=\text{EV}-\text{AC} \).
| Source | PV | EV | AC |
|---|---|---|---|
| Draft EV report | 1,000K | 900K | 820K |
| Accounting ledger, same cutoff | — | — | 890K |
The accounting ledger total includes approved direct labor, material accruals, and a subcontract invoice coded to this control account. The customer reporting procedure requires any AC reconciliation difference greater than 25K to be resolved or disclosed before final issue.
Which response best protects actual-cost traceability and report credibility?
Best answer: A
What this tests: Account Considerations
Explanation: Actual cost used in earned value reporting must be traceable to the accounting source for the same cutoff and reporting structure. The draft report shows AC of 820K, but the accounting ledger supports 890K for the same control account and status date, a difference of 70K. That exceeds the 25K reconciliation threshold. Using the draft values gives CPI = 900/820 = 1.10 and CV = 80K. Using the accounting-supported AC gives CPI = 900/890 ≈ 1.01 and CV = 10K. The professional response is to stop treating the favorable draft metrics as reliable until the AC mapping, cutoff, or coding issue is resolved, or to disclose the unreconciled condition if reporting cannot wait.
The 70K AC difference exceeds the reporting threshold and would change the performance message from strongly favorable to nearly on plan.
Topic: Account Considerations
A control account is preparing its monthly earned value report at the status date. The EVMS accounting guidance requires actual costs to reconcile to the accounting system, including approved burden applied to direct labor. The project’s management reserve is outside the performance measurement baseline and may be released only through approved change control. Accounting shows:
| Cost item | Amount | Status |
|---|---|---|
| Direct labor charged to the control account | $120,000 | Posted |
| Direct material charged to the control account | $45,000 | Posted |
| Labor burden from approved overhead pool | $36,000 | Posted |
| Possible future corporate overhead rate increase | $18,000 | Forecast only |
The control account manager asks to use management reserve to offset the burden and keep current cost performance from worsening. What is the best professional judgment?
Best answer: C
What this tests: Account Considerations
Explanation: Direct costs are specifically traceable to the control account, such as the posted labor and material. Indirect cost, overhead, or burden is not directly traceable in the same way, but it may still be part of actual cost when it is allocated through the approved accounting system. Therefore the current EV report should include the posted direct costs and the posted applied burden in actual cost. The possible future overhead rate increase is not yet a posted or accrued actual cost, so it belongs in forecast discussion, such as EAC risk or narrative assumptions. Management reserve is outside the performance measurement baseline and is controlled through change control; it is not a pool for absorbing unfavorable actual costs or improving CPI presentation.
Posted burden is an indirect cost allocated by the approved accounting method, while management reserve is not available to mask current actual cost performance.
Topic: Account Considerations
At the February 28 status date, Control Account 230 reports PV of $900,000, EV of $820,000, and AC of $760,000. The control account manager says the draft favorable cost variance will support a lower EAC. Accounting review shows that $180,000 of installed material for Control Account 230 was received before the cutoff date, but the invoice was coded to Control Account 320. The project procedure requires actual costs to be traceable to the responsible control account and to include approved cutoff accruals before variance analysis is finalized. What is the best professional action before issuing the cost variance and forecast?
Best answer: A
What this tests: Account Considerations
Explanation: Actual cost must be traceable to the correct control account and status period before cost variance or forecast conclusions are reliable. Here, the installed material belongs to Control Account 230 and was received before the cutoff date, but the cost was coded elsewhere. Leaving the error uncorrected understates AC for Control Account 230, overstates its cost performance, and can produce an unrealistically favorable CPI and EAC. The professional action is to reconcile with accounting, process the appropriate correction or accrual using the required audit trail, and then interpret the variance and forecast. If timing prevents completion before reporting, the data-quality limitation should be disclosed rather than treated as valid performance.
The apparent favorable variance is unreliable until actual costs are assigned to the correct control account and cutoff period.
Topic: Account Considerations
At the September 30 status cutoff, a control account report shows PV = USD 500,000, EV = USD 480,000, and AC = USD 310,000. The control account manager says the CPI looks unusually favorable and asks whether to report the cost underrun as real.
Relevant constraints:
What is the best professional action?
Best answer: B
What this tests: Account Considerations
Explanation: Earned value cost analysis depends on matching actual costs to the work performed through the status date. Here, the material was completed and accepted before September 30, so the late invoice explains why AC is understated. The correct response is to accrue the received goods or services, then reconcile the accrual when the invoice posts. The open commitment is useful for cost exposure and forecasting, but it is not actual cost by itself. EV should not be reduced merely because an invoice is late; EV is based on objective accomplishment criteria. Without the accrual, the CPI would overstate cost efficiency and could mislead management about true cost performance.
The material was received before the status date, so actual cost should include an accrual while excluding the unearned commitment balance.
Topic: Account Considerations
At the March 31 status cutoff, a control account manager is reconciling the period report. Use CV = EV - AC and CPI = EV / AC, rounded to two decimals. Which interpretation is supported by the exhibit?
| Control-account fact | Amount |
|---|---|
| Planned value | $500,000 |
| Earned value | $450,000 |
| Actual cost in preliminary cost-system extract | $430,000 |
Reconciliation notes:
Labor performed through March 31 was not yet posted; an accrual of $60,000 is required.
A supplier invoice in the extract is for material received April 4; exclude $25,000 from March 31 actual cost.
A. Report AC of $430,000, a favorable CV of $20,000, and CPI of 1.05.
B. Report adjusted AC of $490,000, an unfavorable CV of $40,000, and CPI of 0.92.
C. Report adjusted AC of $405,000, a favorable CV of $45,000, and CPI of 1.11.
D. Report adjusted AC of $465,000, an unfavorable CV of $15,000, and CPI of 0.97.
Best answer: D
What this tests: Account Considerations
Explanation: Actual cost for earned value reporting should reflect costs for work performed through the status cutoff, not merely the preliminary accounting extract. The missing labor cost relates to work performed before March 31, so it should be accrued into the reporting period. The supplier invoice relates to material received after the cutoff, so it should be excluded from March 31 actual cost. The reconciled AC is $430,000 + $60,000 - $25,000 = $465,000. With EV of $450,000, CV = $450,000 - $465,000 = -$15,000, which is unfavorable. CPI = $450,000 / $465,000 = 0.97 when rounded to two decimals.
The reconciled actual cost is $430,000 + $60,000 - $25,000 = $465,000, so CV is -$15,000 and CPI is 0.97.
Topic: Account Considerations
A control account includes a procurement-heavy work package for installing prefabricated skid assemblies. The month-end status package contains the following excerpt:
| Item | Status basis |
|---|---|
| Material budget | 100 skids at $5,000 each; separate lot freight/test budget of $40,000 |
| Earned value rule | Earn skid budget only when each skid is installed and accepted; earn lot freight/test budget only when the full lot is received and accepted |
| Purchase order | 100 skids at $5,200 each plus fixed lot freight/test of $42,000 |
| Receipt status | 70 skids received and accepted by receiving inspection |
| Installation status | 50 skids installed and accepted by quality control |
| Accounting status | Accrued invoice for 70 received skids plus the fixed lot freight/test charge; $250,000 cash paid to date |
Which interpretation should the EVP analyst use for month-end earned-value reporting?
Best answer: A
What this tests: Account Considerations
Explanation: For earned-value reporting, procurement events must be classified by what they represent. A purchase order creates a commitment, but it does not by itself create earned progress or actual cost. Material receipt may support accrual accounting, but it is not earned progress unless the work package’s measurement rule says receipt earns value. Here, skid budget is earned only when skids are installed and accepted, so EV is 50 × $5,000 = $250,000. The full lot freight/test budget is not earned because the full lot has not been received and accepted. Actual cost should follow the accounting status: 70 received skids at $5,200 plus $42,000 lot freight/test equals $406,000 accrued AC. Cash paid is not the same as actual cost when accruals are used.
This separates earned progress from receipt, actual cost from cash payment, and commitment from incurred cost.
Use the AACE EVP Practice Test page for the full PM Mastery practice path, mixed-topic practice, timed mock exams, explanations, and web/mobile app access.
Read the AACE EVP guide on PMExams.com, then return to PM Mastery for timed practice.