Try 10 focused AACE CCP questions on Communication Competency, with answers and explanations, then continue with PM Mastery.
Use this focused AACE CCP page to drill Communication Competency decisions before returning to mixed practice, timed mocks, and the full PM Mastery question bank.
| Field | Detail |
|---|---|
| Exam | AACE CCP |
| Topic area | Communication Competency |
| Blueprint weight | 1% |
| Page purpose | Focused sample questions before returning to mixed practice |
Communication Competency is narrow in weighting but important in CCP preparation because the exam includes communication-memo judgment. Strong answers state the cost-control issue, cite the evidence, explain the impact, name the recommended next step, and make uncertainty visible instead of hiding it behind technical language.
Use this page to isolate Communication Competency for AACE CCP. Work through the 10 questions first, then review the explanations and return to mixed practice in PM Mastery.
| Pass | What to do | What to record |
|---|---|---|
| First attempt | Answer without checking the explanation first. | The fact, rule, calculation, or judgment point that controlled your answer. |
| Review | Read the explanation even when you were correct. | Why the best answer is stronger than the closest distractor. |
| Repair | Repeat only missed or uncertain items after a short break. | The pattern behind misses, not the answer letter. |
| Transfer | Return to mixed practice once the topic feels stable. | Whether the same skill holds up when the topic is no longer obvious. |
Blueprint context: 1% of the practice outline. A focused topic score can overstate readiness if you recognize the pattern too quickly, so use it as repair work before timed mixed sets.
These questions are original PM Mastery practice items aligned to this topic area. They are designed for self-assessment and are not official exam questions.
Topic: Communication Competency
A cost engineer is reviewing a draft memo recommendation for a compressor replacement project. The draft currently says, “Select the no-cost option and explain that the delay can be absorbed later.” Current controls data:
Which recommendation should the memo make?
Best answer: A
What this tests: Communication Competency
Explanation: A strong cost-engineering memo recommendation connects the requested decision to the consequences that matter to the audience. The no-recovery position is not supportable because the delay is 15 workdays and the outage window cannot move. The impact is not only schedule variance; it threatens an estimated $900,000 startup-benefit deferral. The low-cost factory acceptance test bypass is also weak because it conflicts with the approved quality plan and creates material field-rework risk with no waiver. The recovery plan costs $260,000, exceeding the project manager’s authority, so the memo should request owner action by Friday and clearly state the cost, schedule, quality, risk, and stakeholder consequences.
This recommendation addresses the cost approval threshold, schedule constraint, quality requirement, risk exposure, and owner decision need using the supplied data.
Topic: Communication Competency
A cost engineer reviews a draft memo for the project manager on recovery of a late process-unit turnover. The draft recommends immediate approval of a $900,000 second-shift field labor plan and states that it is the lowest-cost way to protect the milestone.
Relevant facts:
Which action should the cost engineer take before the memo is issued?
Best answer: A
What this tests: Communication Competency
Explanation: A professional cost memo should support the decision being requested, not simply advocate a convenient recovery action. Here, the draft recommendation is weak because it omits a material alternative, conflicts with the current schedule driver, and fails to disclose schedule-benefit uncertainty. The second-shift plan may help mechanical work, but the milestone is being driven by vendor drawings for control panels. The lower expediting quote is therefore decision-relevant and must be compared with the labor recovery plan. Because neither recovery action is in the approved baseline, the memo also needs to identify the change approval required. The deadline supports concise communication, not unsupported certainty.
The recommendation is not supportable until it addresses the material alternative, conflicting schedule fact, uncertainty range, and approval need.
Topic: Communication Competency
A cost engineer is closing a memo to the project manager after a control-account forecast review. The project manager may sponsor a change request, but only the change control board can approve a cost baseline change.
| Cost-report item | Data at 30 Jun |
|---|---|
| Approved control budget | USD 5.00 million |
| Forecast at completion for approved scope | USD 5.50 million |
| Approved budget changes | None |
| Pending vendor design trend | USD 0.35 million, not approved |
| Schedule recovery alternative | Overtime adds USD 0.18 million if date is held |
| Decision authority | PM may sponsor; board approves baseline |
Which closing paragraph provides the most professional handoff supported by the exhibit?
Best answer: C
What this tests: Communication Competency
Explanation: A professional cost-engineering handoff converts the cost record into a clear management decision without overstating authority. The approved-scope forecast is USD 5.50 million against a USD 5.00 million control budget, so the report should identify a USD 0.50 million forecast overrun. The vendor trend and recovery alternative are separate, unapproved items that may affect the path forward. Since the project manager may sponsor a change request but cannot approve a baseline change, the closing should ask for direction on sponsorship and analysis, then state how the cost engineer will maintain the forecast and change log. Evasive wording hides the decision need, unsupported directives imply authority that is not held, and excessive technical detail buries the handoff rather than helping the project manager act.
This wording states the supported cost condition, identifies the decision needed, preserves approval authority, and commits to a clear follow-up action.
Topic: Communication Competency
You are the project controls lead for a refinery turnaround project. A memo must open with a clear problem frame for the Capital Project Steering Committee. The committee must decide before bid validity expires on July 10 whether to authorize the exchanger bundle award. The approved cost baseline is $48.0 million; current vendor bids are $1.9 million above the procurement allowance, while only $1.2 million of project contingency remains. If award is delayed, the outage will likely slip three weeks and add about $2.25 million in indirect costs.
Which memo opening is most appropriate?
Best answer: D
What this tests: Communication Competency
Explanation: An effective cost-engineering memo opening should quickly orient the decision maker. It should state the stakeholder audience, the project problem, the decision required, and the likely impact on cost, schedule, or baseline control. Here, the Steering Committee is the audience because it must authorize the award or funding action before bid validity expires. The issue is not merely that bids are high; the bids exceed the procurement allowance by more than remaining contingency. The project impact is also material because delaying the award could shift the outage by three weeks and add indirect costs. The best opening therefore combines audience, decision context, cost baseline implication, timing, and project impact without blame or vague escalation language.
It identifies the audience, issue, decision deadline, baseline-related cost gap, and project impact in one decision-oriented opening.
Topic: Communication Competency
An owner’s operations vice president must decide whether to authorize a recovery plan for a process-unit expansion. You are drafting the opening section of the memo. Constraints:
Which information should be included early in the memo to best orient the vice president?
Best answer: C
What this tests: Communication Competency
Explanation: For a stakeholder without detailed cost-engineering background, the memo should begin by orienting the reader to the business problem, the decision required, and the practical impact. Early content should translate cost-control data into clear terms: approved budget versus current forecast, whether the recovery cost is approved or pending, how schedule float affects the required startup date, and any key assumption or uncertainty that limits the recommendation. Detailed formulas, account coding, and source records can support the memo later, but they should not delay the reader’s understanding of the issue and decision context.
This gives a nontechnical stakeholder the issue, impact, baseline comparison, uncertainty, and decision need before detailed support.
Topic: Communication Competency
A cost engineer is preparing a memo for the project sponsor before a funding review. The current cost report shows the forecast at completion is 6% above the approved control budget. The main driver is a pending design trend that has not yet been approved as a baseline change. The sponsor has asked for a two-page memo and must decide whether to authorize contingency use or defer scope until the next review. What is the best professional approach for the memo?
Best answer: D
What this tests: Communication Competency
Explanation: Professional cost-engineering communication should first orient the decision maker. A strong memo identifies the issue, explains the cost or schedule impact, and states the decision needed before presenting detailed analysis. In this case, the sponsor needs to decide on contingency use or scope deferral, so the memo should immediately connect the 6% forecast overrun to that decision. Because the design trend is pending, the memo should also distinguish the approved control budget from the forecast and disclose the approval status and assumptions. Detailed variance tables and calculations are useful, but they should support the framed problem rather than force the reader to discover it.
This structure gives the sponsor the decision context first while keeping the analysis traceable and honest about baseline and approval status.
Topic: Communication Competency
You are reviewing a one-paragraph memo summary for the project sponsor. The sponsor must decide whether to authorize mitigation funding now or wait for the next control cycle.
Constraints for the summary:
Project controls facts:
Which memo summary is most appropriate for the project sponsor?
Best answer: D
What this tests: Communication Competency
Explanation: A professional memo summary should be traceable to the available project-controls record and should not turn unresolved evidence into a conclusion. The validated data support a cost and schedule concern: actual cost plus accruals exceed earned value by USD 0.45 million, the forecast exceeds the approved control budget by USD 0.65 million, and piping is 10 working days late. The contractor’s USD 0.30 million claim is pending, so it should not be treated as an approved baseline change or added to the control budget. The cause is also not settled because the record includes both late isometrics and contractor crew shortages. The best summary gives the sponsor decision-quality information without overstating certainty, hiding unfavorable indicators, or assigning responsibility before the review is complete.
This summary uses the validated data, preserves the approved budget boundary, discloses the pending claim, and acknowledges the conflicting cause evidence.
Topic: Communication Competency
A cost engineer is reviewing a draft closing paragraph for a cost memo to the project manager. The memo will support a funding and recovery decision at the next steering meeting. Which revised closing statement should replace the draft closure?
| Item | Status |
|---|---|
| Approved control budget | $12.0M |
| Current forecast range | Low $13.2M; most likely $14.0M; high $15.1M |
| Pending change CR-17 | $0.6M submitted; not approved |
| Key forecast assumption | Productivity improves from 85% to 95% of plan within 4 weeks |
| Schedule implication | 4-week slip may affect startup commitment |
Draft closure: “I recommend closing the report at $13.4M because CR-17 should be approved soon. The variance is manageable, so no steering decision is needed now.”
Best answer: D
What this tests: Communication Competency
Explanation: Professional cost-engineering communication should distinguish approved budget, forecast cost, pending changes, assumptions, and uncertainty. The exhibit shows an approved control budget of $12.0M and a most-likely EAC of $14.0M, with a wider $13.2M-$15.1M range. CR-17 is submitted but not approved, so it should not be treated as budget relief or used to reduce the stated exposure. The productivity recovery assumption and startup schedule risk are material because they affect forecast credibility and stakeholder decisions. A fair memo closure should make the overrun, uncertainty, limitation, and decision need visible rather than presenting a single optimistic number or delaying escalation.
Fair communication requires separating the approved budget from the forecast, disclosing uncertainty and assumptions, and identifying the stakeholder decision needed.
Topic: Communication Competency
A cost engineer is preparing a one-page memo for an owner’s project sponsor before a funding gate. The sponsor must decide by Friday whether to authorize a $2.4 million draw from management reserve for a vendor acceleration plan. The approved cost baseline is $48.0 million; the current forecast is $50.1 million, including the pending acceleration request and $0.6 million of remaining risk exposure. The draft memo says:
CPI/SPI volatility by cost account indicates stochastic exposure. The controls team was not responsible for late design releases, so Finance should not question our numbers.
What is the best action before sending the memo?
Best answer: D
What this tests: Communication Competency
Explanation: Professional cost-engineering communication should be concise, factual, and aligned to the recipient’s decision. The sponsor needs to decide whether to authorize use of management reserve, so the memo should state the decision required, the cost impact against the approved baseline, the approval status of the acceleration request, the remaining uncertainty, and a clear recommendation. The draft fails because it uses technical shorthand, sounds defensive, and does not frame the funding decision. A better memo translates the analysis into decision-ready language without hiding assumptions or overstating certainty.
This directly addresses the executive decision need while translating project-controls data into a clear, supportable cost impact summary.
Topic: Communication Competency
A cost engineer must provide the recommendation sentence in a memo to the project manager for an owner review. The owner wants the lowest supported forecast cost while maintaining approved scope.
Which concise recommendation is best supported by the facts?
Best answer: D
What this tests: Communication Competency
Explanation: A strong cost-engineering recommendation should combine the decision, evidence, and next action. Here, the proposed overtime costs $150,000 but avoids only one week of site indirects worth $95,000, creating a net adverse forecast impact of $55,000. It also cannot recover the full delay because the remaining week is controlled by late vendor drawings. Since no approved baseline change exists, the baseline should not be revised merely to reflect a recovery idea. The concise and supportable recommendation is to reject the overtime as submitted, identify the net cost impact, and redirect attention to the constraint that is actually driving the remaining delay.
The recommendation uses the cost trade-off, schedule constraint, and baseline approval status to support a clear owner decision.
Use the AACE CCP Practice Test page for the full PM Mastery practice path, mixed-topic practice, timed mock exams, explanations, and web/mobile app access.
Read the AACE CCP guide on PMExams.com, then return to PM Mastery for timed practice.